SJVN Ltd Q1 FY2024 Concall Summary

Source transcript PDF: https://www.stockscans.in/document/xuy85shj3gpzcwjafegpy9vn.pdf

Key Takeaways


The Quarter: A Weather-Driven Drop

Sharma: "in the coming three years, our installed capacity portfolio is going to be multiplied or increased by about six times."

The 25 GW Roadmap: From Ambition to Allotment

Sharma: "our target of 25 gigawatt by 2030 is rightly and quite visible. So we will definitely achieve that target of 25 gigawatt by 2030."

The Three-Year Commissioning Wave

Sharma: "delay, if any, is there in the next three years, I do not rule out this fact that there will not be delay. But delays will be only in months, not in years."

Financial Trajectory: The 4x Promise

Sharma: "We have targeted ROE of at least 16.5% on this. It will be more than that even."

Generation Outlook & Hydrology Risk


Guidance & Commitments

CommitmentSpecificsTimeline
Installed capacity milestoneCross 10,000 MWWithin 3 years
25 GW targetAchieve 25 GW installed capacityBy 2030
Naitwar Mori commissioning60 MWWithin a month
Buxar Thermal Unit 1 commissioning660 MWBy March 2024
Buxar Thermal Unit 2 commissioning660 MWBy September 2024
Arun-3 commissioning900 MWSeptember to December 2024
Bikaner Solar (Phase 1) commissioning250 MWThis FY
Bikaner Solar (remaining) commissioning750 MWAfter one year
Arun-3 dam construction restartRepairs complete, construction resumesBy September end 2023
Etalin construction startAll formalities complete1-1.5 years
Etalin completion3,097 MW operational6-7 years
Arunachal MOU signing5 projects, 5,097 MWAugust 12, 2023
PAT trajectoryINR1,900 crores (next year); INR3,000-3,300 crores (after 2 years); INR3,500-4,000 crores (end of 3 years)FY25-FY27
Revenue trajectoryINR14,000-15,000 croresEnd of 3 years
Debt trajectory~INR27,000-28,000 crores consolidatedEnd of 3 years
PSP capacity build-out5,000 MW, INR45,000-50,000 crores capex7-8 years

Key Metrics

MetricQ1 FY24
Revenue from operations₹664 cr, down 34% YoY from ₹1,006 cr; ₹71 cr of the decline from lower generation, ₹289 cr from prior-year arrear absence, ₹19 cr from lower UI charges
Total income₹738 cr, down 31% YoY from ₹1,070 cr
Total expenses₹358 cr, down ~₹62 cr YoY from ₹420 cr
Profit before tax₹380 cr, down 41% YoY from ₹650 cr
Profit after tax₹270 cr, down ~55% YoY from ₹607 cr
Earnings per share₹0.69, down from ₹1.55 YoY
Net worth₹14,091 cr, up 2.6% YoY from ₹13,735 cr
Total generation206.1 crore units, down ~25% YoY from 273.5 crore units
Plant availability factor~110% (maximum load), machines running on full load
Total incentives67.96, down ~22% YoY from 87.59, primarily due to lower UI charges under new DSM regime
Trade receivables₹329 cr, improved from ₹1,058 cr YoY; J&K receivables down to ₹80 cr from >₹600 cr
Installed capacity~2,100 MW, comprising two hydro, two wind, four solar projects
Projects under construction~16 projects, ~4,500 MW capacity
Capacity addition guidance (next 3 years)~10,000 MW total; ~1,500 MW in year 1, ~5,200 MW in year 2, ~3,300 MW in year 3
Revenue guidance (3-year)₹14,000–15,000 cr total revenue after 3 years, up 4–5x from current ₹2,500–3,000 cr
PAT guidance (3-year)₹3,500–4,000 cr at end of 3 years, up ~4x from current ₹1,000–1,400 cr
Consolidated debt~₹15,000 cr as on date; projected ~₹27,000–28,000 cr by end of 3 years
Regulated equity₹6,200 cr on commissioned projects; diluted equity of under-construction projects ₹7,800 cr; total ~₹14,000 cr when completed