SJVN Ltd Q3 FY2024 Concall Summary

Source transcript PDF: https://www.stockscans.in/document/sk1o9nud5j4spr6lg3m4x0lf.pdf

Key Takeaways


Hydro Performance & the Shortfall

Geeta Kapur: "You are right there is overall shortfall off 45.26 crore units as against our design energy of 896.45 crore units but I would like to inform you that this is a part and parcel of hydro projects. Even in the year 2018 and 19 we were not able to meet our design energy but this year again we have had reasonable snowfall and so we are hopeful of making it up in next year."

Renewable Energy: Commissioning Pipeline & Delays

AK Singh: "It was there but it is not possible because there is DCR sales in this model to be manufactured from the domestic sale and the domestic sale capacity has not come up, constructing a plant in Tuticorin but this plant is delayed."

Arun-3 & Nepal: The Nearest Value Unlock


Thermal & Other Updates


Regulatory & Financial Risks

Geeta Kapur: "As far as HP water cess issue is concerned the matter is subjudice in the honorable high court of HP and even arguments have been completed and we are expecting the judgment very soon. I would say that we are very hopeful that this will not be leveled as this tax is not as per the stature as on date."

Rooftop Solar & New Opportunities


Guidance & Commitments

CommitmentSpecificsTimeline
Q4 renewable commissioning240 MW (50 MW UP solar, 100 MW Raghanesda, 90 MW Omkareshwar floating solar)By March 2024
Bikaner solar commissioning1,000 MW, partial start then full completionPartial Sep 2024, full Dec 2024
Buxar thermal commissioningFirst unit, then second unitJun 2024, Sep 2024
Arun-3 hydro commissioningProject completion per PDAFeb 2025
Arun-3 PPA signing50% of capacity with PTC/Renew PowerWithin one month
Tender awards4,500 MW under finalizationWithin current quarter (Mar 2024)
12 GW capacity targetPortfolio capacity achievedBy end of FY26
25 GW / 50 GW long-term targetsPortfolio in operationBy 2030 / 2040

Key Metrics

MetricQ3 FY24
Revenue from operationsDecreased 2.7% YoY
Profit after taxDecreased by ₹155.64 cr YoY
Net worthIncreased marginally by ₹163 cr
Capacity charges₹42.24 cr, vs ₹63.47 cr in Q3 FY23
UI charges₹7.54 cr, vs ₹85.42 cr in Q3 FY23
RAC₹1.4 cr, vs ₹0.04 cr in Q3 FY23
Total incentive income₹51.18 cr, vs ₹71.93 cr in Q3 FY23
Installed capacity2,227 MW, after addition of 135 MW
Hydro generation (NGPH)Decreased 13.36% YoY
Hydro generation (RHP)Decreased 12.79% YoY
Renewable energy generationIncreased 13.50% YoY
Overall generation shortfall vs design energy45.26 cr units shortfall against design energy of 896.45 cr units
Project portfolio54,370 MW
Capacity under construction (total)4,938 MW (hydro 1,558 MW, thermal 1,320 MW, RE 2,060 MW)
Interim dividend₹1.15 per share, maintained