SJVN Ltd Q4 FY2024 Concall Summary

Source transcript PDF: https://www.stockscans.in/document/qvno16l3rqcaj788amtdr0r5.pdf

Key Takeaways


Project Execution & Slippages

Sushil Sharma: "Because of agitation by local farmers and disruption in our plant activities, this Buxar commissioning has been slipped to three, four months from June and because of a challenge in dam area in this Arun-3 Project, see, though the commissioning target has slightly also slipped further..."

Financial Performance & One-Offs

Sushil Sharma: "The tariff of the Sadla wind power project is 2.43 per unit, whereas during the period it was commissioned in '18-'19, the tariff was almost above Rs. 3. But somehow we were not having the PPA, and we were compelled to sign PPA with the juvenile at the lower tariff and that's why we have to go for the impairment loss."

Capacity Addition & New Wins


Strategic Initiatives & Partnerships

Akhileshwar Singh: "IOCL in itself is a consumer. They need a lot of power and they have also target to become the net zero and we will venture into the green sector and with our collaboration, 50-50 percent joint venture partnership, we will be able to take more investment in the project in hydro also and renewable also plus the hydrogen sector also we will go jointly."

Balance Sheet & Funding

Akhileshwar Singh: "In fact, during the construction we have to pay the interest only, not the payment of the principal amount. And that we are having sufficient projection."

Upcoming Tenders & Pumped Storage


Guidance & Commitments

CommitmentSpecificsTimeline
Buxar thermal Unit 1 commissioningUnit 1 onlineQ3 FY25
Buxar thermal Unit 2 commissioningUnit 2 onlineQ4 FY25
Arun-3 hydro commissioning900 MW onlineQ2 or Q3 FY26 (Oct-Nov 2025)
Bikaner solar commissioning1,000 MW online, panels from JuneQ3 FY25
Renewable capacity commissioning2,048 MW under construction onlineFY25
Balance renewable commissioning477 MW onlineFY26
Nepal PPA conclusionPPA signed and consumableWithin 2-3 months / within this year
IOCL JV incorporationApprovals secured, company incorporated2-3 months
Lower Arun tender issuanceTender out1-2 months
Etalin tender issuanceTender out in multiple packages6-12 months
Nepal transmission land acquisitionLand acquisition complete3-4 months
SGEL QIP10-15% (max 20%) equity offeredCurrent fiscal year
Sadla impairment reversalRs. 101 crore reversed if situation improvesNext year (conditional)

Key Metrics

MetricQ4 FY24
RevenueNot explicitly stated for Q4 FY24
Total incentive income (full year FY24)₹182 cr, down from ₹253.92 cr in FY23
Q4 incentive income₹5 cr, down from ₹24.45 cr in Q4 FY23
Capacity incentive (Q4)₹1.37 cr, down from ₹25.36 cr in Q4 FY23
UI incentive (Q4)₹3.66 cr
Impairment of assets₹138.70 cr booked in Q4, primarily Sadla (₹101 cr) and Khirwire (₹34.88 cr) wind projects
Exceptional item gain₹104 cr from reversal of arbitration provision for Nathpa Jhakri project
Design energy shortfall (FY24)25 cr units shortfall against design energy of 853.3 cr units; ₹41 cr billed for shortfall
Installed capacity2,377 MW, up 150 MW QoQ with commissioning of Gujrai and Raghanesda solar projects
Under-construction capacity4,926 MW (1,558 MW hydro, 1,320 MW thermal, 2,048 MW solar)
Renewable energy pipeline7.2 GW total, of which 2,048 MW under construction and 477 MW under award process
FY25 capacity addition target3,818 MW (1,320 MW thermal, 2,498 MW solar/wind)
FY26 capacity addition target5,506 MW (1,176 MW hydro, 4,330 MW solar/wind)
FY25 CAPEX expectation₹12,000 cr
FY26 CAPEX expectation₹12,000-13,000 cr
Total regulated equity (operational + under construction)₹15,438 cr (operational: ₹7,440 cr, under construction: ₹7,998 cr)
Plant availability factor (hydro)Almost 100%