SJVN Ltd Q1 FY2025 Concall Summary

Source transcript PDF: https://www.stockscans.in/document/imizptkic8xiuz5g3mthaw9i.pdf

Key Takeaways


Project Execution & Milestones

Sushil Sharma: "With the commissioning of this project, our total installed capacity of SJVN now stands at 2466.50 MW."

Portfolio Expansion & New Business


Financials & Capital Management


Tariff & Disclosure Pushback

Management: "You can put your questions through mail, and we will reply properly. I think it won't be proper to just guess and everything. We will come out with the exact figures."

Guidance & Commitments

CommitmentSpecificsTimeline
Buxar Thermal Unit 1 commissioningFirst 660 MW unit onlineFY25
Buxar Thermal Unit 2 commissioningSecond 60 MW unit onlineFY26
Arun-3 Hydro commissioning900 MW project CODQ3 FY26 (by Dec 2025/Jan 2026)
Lower Arun civil works award669 MW Nepal project civil works contractNext 2-3 months
SGEL stake dilution20% stake sale, targeting ₹2,000 croresFY25, subject to DIPAM approval
FY25 capacity addition2,638 MW added, taking total to ~5,000 MWEnd of FY25
FY26 capacity addition5,673 MW including Arun-3, Dhaulasidh, Buxar Unit 2, wind/solarFY26
FY25 revenueApproximately ₹3,200 croresFY25
Debt addition~₹6,500 crores incremental debtNext 2 years
Nathpa Jhakri securitization~₹2,000 crores asset securitizationNot specified

Key Metrics

MetricQ1 FY25
Revenue from operations₹831.73 cr, against ₹664.62 cr in Q1 last year
Profit after tax₹327.15 cr, against ₹270.20 cr in Q1 last year
Incentive income (UI + capacity)₹65 cr
Revenue guidance for FY25₹3,200 cr
Total installed capacity2,466.50 MW
Capacity addition target for FY252,638 MW, taking total to approximately 5,000 MW by end of FY25
Capacity addition target for FY265,673 MW, including 966 MW hydro and 60 MW thermal
Plant availability factor – Nathpa Jhakri104.94%
Plant availability factor – Rampur104.83%
Total consolidated debt~₹21,000 cr, expected to reach ~₹28,000 cr by end of next year
SJVN Green Energy Q1 revenue₹41 cr, profit of ~₹29 cr
Tenders floated in FY25 (Q1)4.8 GW out of targeted 10.8 GW for FY24-25
Stake dilution target in SJVN Green Energy₹2,000 cr through 20% dilution in FY24-25
Omkareshwar Floating Solar Project cost₹649 cr, expected annual revenue of ~₹64 cr