SJVN Ltd Q2 FY2025 Concall Summary

Source transcript PDF: https://www.stockscans.in/document/y1kn9tgifuxm93it33mbm9u6.pdf

Key Takeaways


Execution & Commissioning Pipeline

Singh: "Maybe some slight changes may be there because of the many problems during the execution stage. Some -- might be some shortfall or some slippage will be there."

Portfolio Expansion & New Mandates


REIA Tariff Risk & PPA Challenges

Singh: "Day by day, the prices are getting reduced. Those — there may be 1 or 2 cases of hybrid tender where the price — the tariff discovered is more. In case we are not getting PPA signed with the state, then it will be PSA signed with the state. Then maybe we may have to think of terminating the PPA."

Capital Structure & Subsidiary Moves


PSU Constraints & Strategic Choices

Singh: "But having a government company, we have to take a lot of approval... There is CAG. There is a CVC. There is a CVI. So we cannot take decision like them to go start a work or start a new venture."

Guidance & Commitments

CommitmentSpecificsTimeline
Buxar Unit 1 commissioning660 MW synchronized and operationalJanuary 2025
Buxar Unit 2 commissioningSecond 660 MW unit onlineJune 2025
Bikaner solar (CPSU)500 MW commissioned; remaining 5 MWMarch 2025; June 2025
Arun-3 hydro commissioningProject begins generationSeptember 2025
Green energy subsidiary IPOProcess completed (subject to ministry/DIPAM approval)March 2025
FY25 capacity addition~1,800 MW commissioned (with acknowledged possible slippage)FY25
FY25 capex₹9,000 croreFY25
Buxar land acquisition settlementCompensation finalized via LARRA Court6-7 months

Key Metrics

MetricQ2 FY25
Revenue₹1,026 cr, +8% YoY and +2% QoQ
Incentive income₹80 cr, vs ₹59.44 cr in Q2 FY24
Interest cost~₹200 cr per quarter, expected to remain similar
Regulated equity (operational projects)₹7,339 cr
Total installed capacity246.65 crore units
Capacity under operation2,467 MW, across 12 projects and 2 transmission lines
Capacity under construction4,836 MW, comprising 4 hydro (1,558 MW), 1 thermal (1,320 MW), 11 solar (1,958 MW)
FY25 capacity addition target1,800 MW, revised from 2.6 GW guided in Q1
FY25 capacity addition (H1 actual)90 MW, Omkareshwar solar project
FY25 capex guidance₹9,000 cr, revised from ₹12,000 cr
FY26 capex guidance₹12,000 cr
FY27 capex guidance₹12,000–₹13,000 cr
Tenders floated (cumulative)18.6 GW floated, 8.1 GW awarded till date
REIA PPA signed~4 GW signed, out of ~8 GW LOI issued
Renewable portfolio (operational)494 MW
Renewable portfolio (under construction)1,958 MW
Naitwar Mori H1 generation19.7 crore units, H1 revenue ₹76 cr
Nathpa Jhakri quarterly generation345.1 crore units, highest ever quarterly generation
Rampur Hydro Power Station quarterly generation95.56 crore units, highest ever quarterly generation
Green energy arm IPO₹1,000 cr to be raised, process expected to complete by March '25