SJVN Ltd Q3 FY2025 Concall Summary

Source transcript PDF: https://www.stockscans.in/document/e6vff4et7miah2y043yjra88.pdf

Key Takeaways


Operational Performance

R.K. Chaudhary: "I must assure you that are the best PSU having the O&M yardstick. Our Jhakri plant is running at 110 PF and the Rampur project is also 109 PF."

Project Execution & Delays

R.K. Chaudhary: "Unfortunately, at dam site, we are facing certain geological challenges. And because of that geological challenges, the commissioning is expected to be -- to get delayed. And during the last quarter of the financial year '27, we will commission the Arun 3."

Growth Pipeline & Offtake Risk

R.K. Chaudhary: "We are expecting that the things will improve within the next -- within 2 months."

Capacity Addition Trajectory

R.P. Goyal: "As of now, we are doubling our capacity in FY '26. And every year, we are going to — by FY '26, we are going to add, say, roughly around 3 gigawatt of capacity every year."

Strategic & Financial Considerations


Guidance & Commitments

CommitmentSpecificsTimeline
PSA/PPA logjam resolutionMNRE to hold meeting with state utilities to push PSA signingsImprovement expected within 2 months
Buxar Unit 1 commissioningFirst 660 MW unit CODMay 2025
Buxar full commissioningSecond 660 MW unit COD, 4 months after Unit 1FY26 (this year)
Bikaner solar commissioning1,000 MW project CODQ3 FY26 (hoped for)
Arun 3 commissioningFull project COD, delayed by geological challengesLast quarter of FY27
FY26 capacity additionBuxar (1,320 MW) + solar (200-250 MW) + Bikaner (1,000 MW)FY26
Annual capacity addition run-rateRoughly 3 GW per yearStarting FY26, ongoing
Arunachal largest hydro awardTender award for 3,097 MW projectFY26
Arunachal 5 GW portfolio commissioningLargest hydro project commissioningFY30-31
SJVN Green Energy listingPotential IPO of renewable subsidiaryQ3 or Q4 FY26 (tentative)

Key Metrics

MetricQ3 FY25
Total installed capacity2,466.5 MW, up from 2,334.5 MW after Omkareshwar and Raghanesda additions
Total power generation (9M FY25)1,008.4 crore units, +26.3% YoY vs 798.7 crore units
Nathpa Jhakri generation (9M FY25)683.02 crore units, vs 573.11 crore units in 9M FY24
Rampur generation (9M FY25)190.51 crore units, vs 161.2 crore units in 9M FY24
Incentive income₹68.49 cr, vs ₹51.18 cr in Q3 FY24
Interest expenseIncreased YoY, driven by capex borrowings for 2–2.5 GW commissioning in FY26 and securitization of return on equity
DepreciationIncreased YoY, 9 months depreciation charged on Naitwar Mori (commissioned Q3 FY24)
Under-construction portfolio4,936 MW: 4 hydro (1,558 MW), 1 thermal (1,320 MW), 12 solar (2,058 MW)
REIA tenders floated in FY257.5 GW against a target of 10.8 GW
REIA awarded capacity in FY252.4 GW
Renewable portfolio (generator vertical)7.2 GW, 100% PPA-backed, average tariff ~₹2.8
FY26 capacity addition target~3 GW: ~1.5 GW solar (incl. 1 GW Bikaner) + ~1.3 GW thermal (Buxar)
Buxar Thermal first unit CODMay 2025 (660 MW); second unit 4 months later, full 1,320 MW in FY26
Arun 3 hydro (900 MW) commissioningQ4 FY27, delayed from FY25 due to geological challenges at dam site
Foreign currency borrowings\$3,400 cr (USD) and ₹1,500 cr (JPY) outstanding