SJVN Ltd Q4 FY2025 Concall Summary

Source transcript PDF: https://www.stockscans.in/document/t3zi9y25o5c6sgtodllgyhl4.pdf

Key Takeaways


Operational Performance

Management: "Though as a good corporate governance practice most of the industry players are not there with the impairment, but being a CPSU and we follow the highest of the corporate governance practices, so we provided for whatever will feel, as you know that impairment as would be done on every balance sheet date."

Capacity Addition & Commissioning Schedule


PPA & Offtake Security

Bhupender Gupta: "This is really a great significant development because once we generate then we need to sell the power also so to sign the PPA prior to commissioning is a big achievement for any company."

REIA Vertical: The New Earnings Engine


Capex, Debt & Regulated Equity


Himachal Dispute & Other Updates

R. P. Goyal: "They will be reimbursing all the costs which we have already incurred and which we are going to incur till the final decision is taken. The reimbursement will be along with interest."

Guidance & Commitments

CommitmentSpecificsTimeline
Buxar Thermal Unit 1 CODSynchronization and commercial operation15th July 2025
Buxar Thermal Unit 2 CODCommissioningOctober to December 2025
Bikaner Solar full commissioningBalance of 1,000 MW projectBy October 2025
FY26 capacity addition4,995 MW (1,320 MW thermal + 3,675 MW renewable)FY26
FY26 capex₹8,300 croreFY26
FY27 capex₹12,000 croreFY27
REIA PPA/PSA signingsRemaining 7.3 GW of 12.7 GW awardedFY26
REIA bottom-line contribution~₹200 crore trading marginFY27
REIA bottom-line contribution~₹1,200 crore trading marginBy 2030
Minimum regulated equity~₹1,945 croreEnd of FY26 and FY27
Italian hydro investment approvalCabinet Committee approvalEnd of September or October 2025
Attunli clearancesForest and environment clearanceSeptember/October 2025
Solar impairment reversalMay reverse if generation situation improvesNo date; conditional on recovery

Key Metrics

MetricQ4 FY25
Total generation1,064.7 crore units in FY25, up 25.44% YoY from 848.9 crore units
Nathpa Jhakri generation742.14 crore units in FY25, up from 631.18 crore units in FY24
Rampur generation207.4 crore units in FY25, up from 177.8 crore units in FY24
Incentive income₹115 cr in Q4: capacity incentive ₹35 cr, secondary energy ₹76 cr, UI charges ₹4 cr
Other incomeDeclined nearly 50% in Q4, attributed to deployment of capital into under-construction projects
Depreciation & amortizationIncludes impairment loss of ₹143 cr in Q4, related to solar assets
Exceptional itemsNone in FY25 P&L
Capex incurred~₹7,800 cr in FY25
Capex guidance₹8,300 cr for FY26, ₹12,000 cr for FY27
Capacity added~190 MW (solar) in FY25; 320 MW commissioned up to May 2025
Capacity addition target4,995 MW for FY26: 1,320 MW thermal (Buxar), 3,675 MW renewable
Capacity addition target FY27~2,000 MW: 69.5 MW hydro, ~1,930 MW solar and wind
Regulated equity₹1,076 cr currently (Nathpa Jhakri ₹825 cr, Rampur ₹251 cr); minimum ₹1,945 cr by end FY26/FY27 with Buxar adding ₹869 cr
REIA tenders floated18.6 GW cumulative; LoAs issued for 13.748 GW; PPAs signed for 5.188 GW
REIA PPAs signed in FY25~3 GW; 2.3 GW signed in FY24
REIA trading margin₹7 per unit; ~₹50 cr successive income in FY25; ~₹200 cr expected in FY27 bottom line