SJVN Ltd Q2 FY2026 Concall Summary

Source transcript PDF: https://www.stockscans.in/document/vf2xscf4wla5fmvqsax5u32x.pdf

Key Takeaways


Buxar Thermal: The Near-Term Catalyst

Gupta: "Yes, regarding Buxar, as I told earlier, that we are going to declare the commercial operation of the plant within one or two days because already full load operation has been completed."

The Revenue Flatline: Why New Capacity Has Not Lifted the Top Line


REIA Tenders: A Growing Book With a PPA Problem

Gupta: "The problem, frankly speaking, you must be knowing yourself also because there is a lot of like tenders which are coming out in the market, specifically for solar, there is some issue now because of the grid connectivity, there are transmission line shortage and because of that power is not getting evacuated even for the commission plant."

Project Pipeline: What Commissions When


Capex: Steady State, Not Accelerating

Gupta: "So in the beginning when we start any hydro project the capex is not very high but after one or two years then the capex start increasing. So that is the reason why the capex is in the same range and not increasing year on year basis."

Strategic Positioning & Other Updates

Gupta: "SJVN Limited is in a very sound footing. There is no issue as of now regarding the growth of the company and we are slightly trying to consolidate our position as of now, mainly the under-construction projects which are there and we just want to complete them fast so that we can start generating the revenue."

Guidance & Commitments

CommitmentSpecificsTimeline
Buxar Unit 1 commercial operationDeclaration of CODImminent (within 1-2 days of the call)
Buxar Unit 2 CODCommissioning of second 660 MW unitJanuary or February 2026; definitely within FY26
Bikaner solar addition320 MW incremental capacityThis month or max by 15 December 2025
FY26 RE solar commissioning~650 MW total (Bikaner 320 MW, Jamui 75 MW, Assam 120 MW, Bagodara 35 MW, Nawa 100 MW)Current financial year
FY26 capex₹7,500 crore total (₹3,600 cr spent in H1)FY26
FY27 capex₹8,000 croreFY27
Next-year solar commissioning~1.5 GWNext year (FY27)
Nepal hydro construction startLower Arun (680 MW) and Upper Karnali (900 MW)Q1 of next financial year
REIA untied PPA clarityStakeholder consultation outcome on action for untied power/PPAsTwo to three months
SJVN Green Energy listingNo plan to listAt least one year

Key Metrics

MetricQ2 FY26
Total installed capacity3,146.52 MW; 320 MW to be added by mid-December, taking operational capacity to ~3,500 MW
Total generation (H1 FY26)944.2 crore units, up ~56.2 crore units or ~6.3% YoY
Nathpa Jhakri generation178.5 crore units, up from 177.4 crore units YoY
Revenue~₹1,000 cr (per analyst observation), comparable to Q2 FY25; lost ₹50–60 cr due to lower plant availability from floods and silt
Depreciation₹171 cr, up from ₹133 cr in Q2 FY25
Finance costIncreased by ~₹50 cr vs Q2 FY25
Incentive income (H1 FY26)₹104.45 cr
Tax expense impact₹52 cr decrease in income due to expiry of 80 IEA benefit for one plant
Bank interest incomeDecreased by ₹26 cr YoY
Late payment surchargeDecreased by ₹17 cr YoY
Capex (FY26)₹7,500 cr target; ₹3,600 cr spent in H1
Capex (FY27)~₹8,000 cr planned
Total debt~₹30,000 cr
Under-construction portfolio5,091 MW: 4 hydro (1,558 MW), 1 thermal (1,320 MW), 14 solar (2,213 MW)
Buxar Thermal (Unit 1, 660 MW)COD expected within days of Nov 10; 72-hour full-load run completed Nov 5; PPA tariff ~₹5.4 per unit
Buxar Thermal (Unit 2, 660 MW)COD targeted January or February 2026
Bikaner Solar (1,000 MW)680 MW COD achieved in phases; remaining 320 MW commissioning next month
RE solar commissioning (FY26)~650 MW expected: Jamui 75 MW, Assam 120 MW, Bagodara 35 MW, Nawa 100 MW, plus Bikaner 320 MW
RE solar commissioning (FY27)~1.5 GW expected
Average solar tariff~₹2.60 per unit, at ~25% PLF assumption
REIA tenders floated19.8 GW cumulative
REIA LOAs issued13.74 GW
REIA PSAs/PPAs signed3.74 GW; another ~3.75 GW expected in next two months
Battery Energy Storage tender~1,250 MW, to be floated within a month or two
Wind power tender~1,200 MW floated
Nepal projects (upcoming)Lower Arun 680 MW, Upper Karnali 900 MW; construction expected to start Q1 FY27
Etalin hydro project (Arunachal)3,097 MW; forest and environment clearance received; ~70% land compensation paid
Attunli hydro project (Arunachal)688 MW; progressing alongside Etalin