SJVN Ltd Q4 FY2026 Concall Summary

Source transcript PDF: https://www.stockscans.in/document/cmlp2vmr1ojlr568g0yxg646.pdf

Key Takeaways


Profitability Drag: Subsidiary Losses

Gupta: "beyond 70% PLF only, we start generating the profit. But now this year, we will be commissioning the second unit also. And everything has been stabilized in Unit-1 also. So, we are very much sure that during this FY '27, we are going to have a profit from the Buxar Thermal Power plant."

Revenue: The Tariff Order Boost


Project Pipeline & Commissioning


The REIA Pipeline: Awards vs Reality

Gupta: "Very, very difficult to say anything as of now. We are trying very hard because I told you it is the problem of the component of that, power of the tender particularly."

Guidance & Commitments

CommitmentSpecificsTimeline
Buxar Unit-2 commercial operation660 MW unit synchronized 8 May 2026End of May 2026
Buxar profitabilityPlant turns profitable when PLF crosses 70%; management "very much sure" of profit in FY27FY27
SGEL loss reductionLosses to "improve substantially" in FY26-27FY27
Bikaner full capacitySVR reactor commissioning enables full 1,000 MWBy October 2026
Dhaulasidh Hydro commissioning69.5 MWBy March 2027 [4-5]
Arun-III Nepal hydro commissioningAll four units (900 MW total)By December 2028
Capacity addition FY27Buxar 660 MW + Dhaulasidh 69.5 MW + ~1,555 MW solarFY27
Capacity addition FY28~650 MW solarFY28
Capacity addition FY29-30~2,500 MWFY29-30
DividendFinal ₹0.35/share + interim ₹1.15/share = total ₹1.5/share for FY26FY26

Key Metrics

MetricQ4 FY26
Revenue from operations₹2,934 cr, up 109% YoY from ₹446 cr in Q4 FY25
Revenue from operations (full year)₹3,545 cr, up 22% YoY from ₹2,897 cr in FY25
Profit after tax₹125 cr, up 308% YoY from ₹31 cr in Q4 FY25
Profit after tax (full year)₹1,008 cr, up 4% YoY from ₹970 cr in FY25
Other income₹114 cr, down 10% YoY from ₹127 cr in Q4 FY25
Finance cost (full year)₹910 cr, up from ₹726 cr in FY25, driven by ₹206 cr exchange rate variation
Depreciation, amortization and impairment (full year)₹632 cr, up from ₹450 cr in FY25, includes ₹174 cr impairment loss under Ind AS 36
Tax expenses (full year)₹569 cr, up from ₹313 cr in FY25, due to higher PBT and increased MAT credit utilization
Trade receivables₹1,299 cr as of 31 Mar 2026, vs ₹262 cr as of 31 Mar 2025
Unbilled debtors₹906 cr as of 31 Mar 2026, vs ₹136 cr as of 31 Mar 2025, includes ₹776 cr from tariff orders
Total generation (full year)1,330.2 cr units, up 25% YoY from 1,064.6 cr units in FY25
Total installed capacity4,196 MW as of 31 Mar 2026, after 1,730 MW addition in FY26 (1,070 MW solar, 660 MW thermal)
Capacity addition guidance FY27~2,284 MW planned: 660 MW Buxar Unit-2, 69.5 MW Dhaulasidh hydro, ~1,555 MW solar
CAPEX guidance FY27~₹9,400 cr planned
Dividend per share (full year)₹1.50, comprising ₹1.15 interim and ₹0.35 final, on face value of ₹10
Buxar Unit-1 PLF~60% during initial three months of operation
SGEL revenue (full year)₹510 cr, up from ₹232 cr in FY25; net loss of ₹258 cr
REIA signed PSAs~6 GW signed out of ~16 GW awarded projects