Smarten Power Systems Ltd Guidance Report - SOIC x StockScans Report
as of Nov 2026
- China subsidiary commenced, 2-3 shipments done
Partial - At the Q2 FY27 call, management stated the China subsidiary has been commenced/opened with 2-3 shipments already done from China direct to Africa (merchant trading) and more in the pipeline. In the Q2 FY27 result filing, the subsidiary was incorporated but as at 30th September 2026 no remittances have been made and no transactions undertaken by it during the period.
- IPO proceeds capex item completed within March 2026 timeline
Partial - The IPO offer document committed ₹40.01 Cr of proceeds across objects, including funding capital expenditure requirements of ₹4.46 Cr, with the capex item proposed for completion by March 31, 2026. As of 30th September 2026 the Gurgaon Plant capex had ₹70.00 lakhs unutilised (₹795.05 of ₹865.05), and the Monitoring Agency flagged a three-month delay as of 30th June 2026; all other objects were fully utilised.
- Battery production around 11,000 units/month at Baddi
Pending - At the Q2 FY27 call, management targeted around 11,000 batteries per month at the Baddi plant as capacity is increased, with no deadline stated. The Baddi plant capacity is stated at 8,000 units/month, with the highest monthly in-house production of approximately 6,600 units in June 2026 and \~80% of installed capacity utilised as of Nov 2026; no capacity expansion is disclosed in our record.
- Manufacturing-vs-trading mix of 70-30 this year
On track - At the Q2 FY27 call, management guided the manufacturing-vs-trading mix could be "70-30, I guess" this year, manufacturing rising from the 60-40/40-60 split stated elsewhere on the call. H1 FY27 sales split was 40% trading / 60% assembling, and the current trading-vs-manufacturing split is about 60-40, with the Jhajjar plant not yet operational.
- Capex of around ₹3.5 crore next year, no major expansions
Pending - At the Q2 FY27 call, management guided \~INR50-60 lakhs for minor expansion, \~INR2-3 crores pending payments for the Jhajjar plant, and total capex for next year of around INR3.5 crores with no immediate major expansions. Previous capex commitments are nearly complete with work inside the factory and battery facility almost finished; no FY28 capex actuals yet, and CWIP moved from 4.58 in FY25 to 6.89 in FY26.
- FY28 revenue of ₹525 crore
Pending - At the Q2 FY27 call, management guided FY28 revenue of "you can assume it is 525" crore, calling the plan conservative. No FY28 actuals yet; FY27 guidance is ₹370-380 crore, implying \~40% growth needed in FY28 to reach ₹525 crore.
- FY27 revenue of ₹370-380 crore
On track - At the Q2 FY27 call, management said "we will be touching around 370-380" crore and MD Arun Bhardwaj stated "we are targeting about 375 in this year," calling it conservative. H1 FY27 revenue was ₹204.54 crore, +77.5% YoY, with H2 FY27 guided to "be the replication of the H1," implying \~₹410 crore for the full year; no FY27 actual yet.
- 350+ distributors in FY27 via 108 new appointments
Delivered - The announcement of 17th June 2026 targeted expanding the distributor network to more than 350 distributors during FY 2026-27 by appointing 108 new distributors from a base of 250+. By the Q2 FY27 call the network had grown from 327 to 427 domestic distributors, and the Q2 FY27 PPT shows 427 domestic and 32 global distributors.
- Battery plant utilisation rising from \~65% over two months
Delivered - The FY26 Annual Report expected higher in-house battery production to lift the battery plant's \~65% utilisation, and the announcement of 9th April 2026 guided utilisation to rise over the next two months. In-house production reached a record \~6,600 units in June 2026, and \~80% of installed capacity was utilised per the Q2 FY27 PPT.
- FY26 revenue of ₹230-240 crore (\~20% growth)
Delivered - At the Q3 FY26 call, Arun Bhardwaj quantified FY26 revenue at "about INR230-INR240 crores... It should go up to INR240 crores" versus last year's "about INR203 crores," with Ravi Dutt guiding "normal growth like 15%, 20%". FY26 revenue was ₹242.66 crore, 20.3% growth over ₹201.75 crore in FY25.
- Exide Europe distribution, first-year ₹15-20 crore
Pending - At the Q3 FY26 call, Arun Bhardwaj set a first-year target of "only INR15 crores, INR20 crores only" for the Exide Europe distribution business while cautioning it was early to say more. No revenue figure for the Exide arrangement is disclosed in our record; the agreement with Exide Technologies Europe covers the Indian market for project-based applications, and the Q2 FY27 PPT lists Smarten as authorized channel distributor for Exide Industries.
- Hybrid inverter in-house design by H1 2027, visible by Q3 FY27
On track - At the Q3 FY26 call, Ravi Dutt said hybrid inverters would come "in the first half of 2027" with the in-house design in the market "within next 6 months," visible "by Q3 FY '27"; later updates guided mass production "within 1 month or 2 months" and commercialisation for H2 FY2027. Field trials are active, the 2-in-1 Grid-Tie Inverter was launched per the Q2 FY27 PPT, and mass production of hybrid inverters is not yet confirmed in our record.
- EBITDA margin 9-10% for FY27
On track - At the Q3 FY26 call, Arun Bhardwaj guided EBITDA margin of "about 9% to 10%" for FY27, helped by the acquired battery plant and own-manufacturing cost reductions, with "early double digit" when the top line doubles; at the Q2 FY27 call management called the 8.3% margin sustainable with 1-3% more expected once Jhajjar is operational. H1 FY27 EBITDA margin was 8.3%, with the Jhajjar plant cited as the key margin driver not yet operational.
- Jhajjar plant operational by March 2026, capacity doubling to 1,200 units/day
Partial - At the Q3 FY26 call, management committed to the Jhajjar (MET) plant becoming operational "in the end of March, 2026," scaling production from 600 units/day to 1,200 units/day across 41,903 sq. ft., with the revised guidance being commencement within 3 months from Nov 2026 and production expected by end of FY27. The plant was not operational by March 2026; as of the Q2 FY27 PPT the pre-engineered building was 90% and civil works 60% complete, with no commissioning disclosed as of 11 Nov 2026.