Snowman Logistics Ltd Q4 FY2025 Concall Summary

Source transcript PDF: https://assets.stockscans.in/docs/qpmhh3gqtjs3my49aqwq1fpu.pdf

Key Takeaways


The Q4 Numbers: What's Real and What's Accounting

Samvid Gupta: "There was a big one-time hit on, it's a provision, it's not a cash payout yet, but of about Rs. 12.8 crores."

Warehousing: The Margin Reset Is Structural

Ishaan Gupta: "So, as of now, on a pan-India basis, we are still the leader by a large margin in terms of capacity. On a regional level, at every new location, there are some cold storages who we compete with. And on the 5PL side, we don't have any competition as of now."

Rail: Waiting on the DFC's Last Mile


Kashipur ICD: A Concentrated Bet

Samvid Gupta: "It's about a four-to-five-year payback for us, which was better than a Greenfield ICD project."

Expansion: Land Is the Bottleneck

Samvid Gupta: "We have almost finalized a couple of parcels and then due diligence doesn't go through. Some title issue is there. Some people back out last minute on price. So, we are looking for viable projects only and we don't want to expand for the sake of expanding."

Gateway and Snowman: Together but Separate

Ishaan Gupta: "You know, unfortunately, because of an NDA, we are not able to disclose the details of the contract with our customers. But we can assure you that we have built enough safety which guarantees us, that we will not be at a loss."

Guidance & Commitments

CommitmentSpecificsTimeline
Rail volume recoveryQ1 volumes much better, in line with Q2/Q3/Q4 levelsQ1 FY26
Double-stacking improvementTarget 42–43% (from 41% in Q4)Going forward
JNPT corridor completionFull road-to-rail shift advantage possibleBy March 2026
Kolkata facility ramp-upFaster than earlier expected on current inflow and seasonalityStarting June 2025
Krishnapatnam Phase 1First phase operationalJuly 2025
Krishnapatnam Phase 2Second phase expansionJuly 2026
5PL gross margin range6–8% depending on product mixOngoing
Jaipur legal resolutionTribunal ruling in company's favor, issue resolvedWithin next 1–2 years
Gateway CAPEX (ex-new terminals)~₹30 crFY26
Gateway CAPEX (warehousing + vehicles)~₹60 crNext two years
Snowman CAPEX₹100–150 cr per yearFY26–27
Kashipur ICD paybackFour-to-five-year paybackFrom acquisition

Key Metrics

MetricQ4 FY25
Consolidated revenue (Snowman)₹145 cr for full year FY25, consolidated since December
Consolidated EBITDA (Snowman)~₹25 cr for full year FY25
Consolidated PAT (Snowman)₹3.5 cr for full year FY25
Warehousing margin11% for FY25, down from 18–19% three years ago; impacted by 5PL mix, Park 'n' Pay model, and Amazon exit
5PL gross margin target6% to 8%, revised from 8–9% due to product mix change and new Unilever business
Rail EBITDA per TEU₹9,500–9,600 for Q4
CFS EBITDA per TEU₹1,300–1,400 for Q4
Rail volumes~92,000–93,000 TEUs per quarter, stable over last 2–3 quarters
Double-stacking percentage41% in Q4, up from ~38% earlier; targeting 42–43%
NCR rail market share17% in Q4, steady; full year also 17%
Ludhiana rail market share27% in Q4, regained from 23–24% last year; full year 25%
Kashipur rail market share37% in Q4, regained; full year 28%
Warehousing like-for-like growth (ex-Amazon)~5% increase, compensating for Amazon topline loss of ₹10–11 cr
Existing customer renewal pricing increase~4% on contract basis
Meat, seafood, poultry segmentDown 15% YoY, impacting warehousing margins
Goodwill impairment (Snowman consolidation)₹258 cr non-cash hit; net goodwill remaining ₹131 cr; linked to share price decline from ~₹75 to ~₹50
Stamp duty provision (Gateway)~₹12.8 cr provision, non-cash, for past merger
Depreciation impact (useful life reassessment)₹3.5–4 cr lower in Q4 only, not backdated
Trade receivables provision (Snowman)~₹4 cr, covering 180 days
Planned CAPEX (Snowman)₹100–150 cr per year, 80% debt-funded
Planned CAPEX (Gateway, ex-new terminals)~₹30 cr per year; ₹60 cr over next two years for warehousing and vehicles
Kolkata facility addition~6,000 pallets, commencing June 2025
Krishnapatnam facility first phaseJuly 2025 start; second phase July 2026
5PL new customers added2 (Unilever and Kopi Kenangan)
Park 'n' Pay pallets outsourced~60,000 pallets, 500x growth this year