Supreme Petrochem Ltd Q1 FY2025 Concall Summary

Source transcript PDF: https://assets.stockscans.in/docs/6pynoxaoynvyanuowrhbq145.pdf

Key Takeaways


Volume & Demand Seasonality

Nayyar: "In the next two or three years the demand will grow up also so that there is always a surplus capacity otherwise when the demand goes up immediately the plants cannot be set up. So there is always cushion in the capacity and the demand."

Spreads, Freight & Import Dynamics


ABS Project: Technology, Differentiation & Timeline

Nayyar: "The next financial year we will be in the market, but then that will be the first year when the product would be supplied to the market and by the time the market gets used to it and starts accepting the material will take some time but starting 26-27 financial year, yes, it will be fully accounted and will add to the top line and the bottom line both."

Expansion Projects & Capex Pipeline

Nayyar: "SMMA market as such was very small and so, we are only considering doing may be some SMMA compounds but not actually going into SMMA."

Competitive Positioning & Market Structure


Guidance & Commitments

CommitmentSpecificsTimeline
Volume growth8–9% for the full fiscal yearFY25
ABS plant start of productionPlant to begin operationsQ4 FY25
ABS market entry and revenue contributionProduct supplied to market in FY26; fully accounted in top and bottom lineFY26–27
EPS expansion completionThrough by end of calendar year or last quarter of this financial yearCY24 / Q4 FY25
XPS expansionSometime in next financial yearFY26
Haryana facility operationalLikely start from FY28; fully operational with ABSFY28–29
Ultimate ABS capacity target75,000 tonnes, adding lines as demand requiresNo fixed date

Key Metrics

MetricQ1 FY25
Operating income₹1,574 cr, +28% YoY
Operating EBITDA₹161 cr, +78% YoY
Total EBITDA₹184 cr
Revenue from trading~20% of revenue
Volume93,000 tonnes
Volume growth guidance (FY25)8–9% (management's prior guidance)
Capacity utilization>83%, blended basis
Polystyrene market share~55%
Polystyrene demand (India)~325,000 tonnes
ABS consumption (India)2,80,000–3,00,000 tonnes
ABS imports as share of consumption~50%
Monthly PS imports (recent)3,500 tonnes, down from 6,500–7,000 tonnes
Freight rate increase (solid cargo)~$150/tonne in last couple of months
New projects revenue potential₹3,500–4,000 cr (ABS, EPS, Haryana combined)