Key Takeaways
- Volume-led quarter, demand intact: Q4 volumes jumped to 11.52 lakh tons, driven by strong Northeast demand and an expanding dealer network outside the region.
- A ₹2,000 crore doubling-down: Management committed to a ₹2,000 crore CAPEX plan that will more than double clinker capacity and almost double cement capacity over the next two years.
- Cost structure has a Northeast premium: Raw material costs run structurally higher than All-India peers because fly ash and coal must be sourced from outside the region, a dynamic that is not changing.
- Green energy push is a margin lever, not just a story: Biomass already substitutes ~10% of energy needs, with a target of 15–17% in 6–7 months from renewable or green sources, providing a tangible buffer against fuel cost volatility.
- What to watch next quarter: The pace of construction commencement on the new clinker line, the receipt of environmental clearance for the Meghalaya expansion, and whether the post-flood demand recovery materializes as quickly as management expects.
Demand & Volume Outlook
- Northeast demand anchored by public spending: Management is "very bullish" because government infrastructure investment is expected to drive aggregate demand over the next 4–5 years, if not the decade.
- Outside-Northeast push working: Volume growth is coming from both the core Northeast market and areas in the East that the company serves, supported by an uptick in the dealer network outside the Northeast.
- No new competitive supply: Management sees no new capacity entering the region because the subsidy-linked economics that attracted earlier capacity additions are no longer viable.
- Near-term disruption from floods: Heavy flooding in the Northeast has dented demand in the current week, but the forecast suggests clearing in a week’s time, with demand expected to pick up immediately after.
- FY23 volume target: The company aims for ~0.4 crore tons, implying roughly 17% growth over FY22’s ~0.34 crore tons.
Tushar Bhajanka: "The volume growth I'm very bullish about Northeast and also the areas in east that we serve."
Expansion Plan & CAPEX
- The headline build: One 0.3 crore-ton clinker plant and two 0.2 crore-ton grinding units, for a total CAPEX of ₹2,000 crores, spread roughly 50% each year over the next two years.
- Timeline locked on orders, not just intent: Most machinery orders for the clinker plant and grinding units have already been placed, and the ₹2,000 crore figure already factors in increased costs.
- Construction starts now: The clinker plant construction is set to begin next month (June 2022), with commissioning expected by December 2023. The Guwahati grinding unit will commission around the same time.
- Third grinding unit in South Assam: Capacity is still being finalized at ~1.5 to 2 lakh tons, with commissioning expected 2–3 months after the other plants.
- Clinker debottlenecking adds quick tons: Technical changes already made will lift clinker capacity from ~0.26 crore tons to ~0.27 crore tons in FY23, a small but immediate gain.
- Environmental clearance imminent: The public hearing for the Meghalaya expansion is already cleared, and final environmental clearance is expected by end of May 2022.
- Peak debt is manageable: Peak debt during the expansion is expected at ₹500–650 crores, with most CAPEX funded by internal cash flows and the debt repaid within the first year of commissioning.
Management: "We want to be about more than double our clinker capacity and almost double our cement capacity. That is the aspiration that we have for the next 2 years."
Costs & Margins
- Raw material cost structurally higher: Fly ash and coal must come from outside the Northeast, making both more expensive than for All-India or East-region peers, which drives up clinker cost and thus raw material cost.
- Freight cost spiked on seasonal factors: Freight cost rose 4.5% QoQ in Q4 despite stable diesel prices and a slightly lower lead distance of ~217–218 km, because the March quarter sees truck availability issues across the Northeast as the year closes.
- Lead distance improving: FY22 lead distance was 219 km, slightly down from ~222 km in prior quarters, a small but favorable trend.
- Branding spend normalizing: Branding expenditure was elevated at ~₹43–45 crores in FY22 to support the Siliguri plant launch and dealer network build-out; going forward, it will not exceed ₹32–33 crores annually.
- GST refunds cleaned up: Other current assets reduced by ~₹100 crores as the government released all pending GST refunds, clearing the entire receivable this year.
- Freight subsidy largely collected: ~₹25 crores received in April (FY23), leaving only ~₹8–12 crores outstanding.
Fuel & Energy Strategy
- Biomass substitution providing breathing room: The company is substituting ~10% of total energy requirements from biomass, which has helped manage costs over the last 4–5 months.
- AFR system ordered: A basic system for 5% substitution in the kiln has been ordered, with installation expected in the next 6 months, implying contribution from Q3 onward.
- Total green energy target: Management expects renewable and alternative fuel substitution to reach 15–17% of energy requirements in the next 6–7 months.
- Coal supply managed despite rake issues: Some disruption occurred due to rake availability, but healthy stock levels prevented any cost pass-through.
- No steep fuel cost rise expected: Management does not foresee a significant rise in fuel prices in the next 1–2 quarters, though Coal India prices may increase modestly if shortages emerge.
- SFA fuel contracts locked: Fixed for 5 years and started last year; the benefit should accrue in coming years.
- IEX price volatility contained: IEX prices fluctuated from ~₹10 down to ~₹6; grinding units face this exposure, but the clinker plant has seen no increase in fuel costs.
Management: "I do not think that we will face a very significant rise in our fuel prices going ahead."
Balance Sheet & Capital Allocation
- Debt approach is conservative: Management expects to take some debt on a 2–3-year horizon but intends to pay it off as soon as possible, stating the debt situation will not be a concern.
- Peak debt quantified at ₹500–650 crores: Most CAPEX will be paid from internal cash inflows, with debt repaid in the first year of commissioning.
- WHRS spend on track: ~₹78–80 crores spent on the existing WHRS project up to March FY22, out of a total ~₹150 crores; the remaining ₹60–70 crores will be spent by the October 2022 commissioning date.
- SGST benefits secured: Both Assam grinding units are eligible for SGST benefits under current state policies, valid for ~15 years and ranging from 100% to 150% of fixed investment depending on project size.
- No captive power plant for new clinker line: The existing ~50 MW in Meghalaya is deemed sufficient, with WHRS coming for both the current plant and the new clinker line.
Management: "The debt will be in a 2-3-year horizon we may have some debt so we'll pay it off as soon as possible. I don't think that debt situation would be something of a concern going forward."
Guidance & Commitments
| Commitment | Specifics | Timeline |
|---|---|---|
| Clinker plant construction start | 0.3 crore-ton plant construction begins | June 2022 |
| Clinker plant commissioning | New clinker line operational | December 2023 |
| Guwahati grinding unit commissioning | 0.2 crore-ton unit operational | December 2023 |
| Third grinding unit (South Assam) commissioning | ~1.5–2 lakh tons operational | 2–3 months after Dec 2023 |
| Environmental clearance for Meghalaya expansion | Final clearance received | End of May 2022 |
| Existing WHRS commissioning | ~₹150 crore project operational | October 2022 |
| AFR system in kiln | 5% substitution contributing | Q3 FY23 onward |
| Total green energy substitution | Reach 15–17% of energy needs | Next 6–7 months |
| FY23 volume target | ~0.4 crore tons (~17% YoY growth) | FY23 |
| Branding expenditure cap | Not to exceed ₹32–33 crores annually | Going forward |
| Peak debt during expansion | ₹500–650 crores, repaid in first year of commissioning | Over 2–3 year horizon |
Key Metrics
| Metric | Q4 FY22 |
|---|---|
| Revenue | ₹2,218.74 cr (full year FY22), vs ₹1,718.61 cr in FY21 |
| EBITDA | ₹122.55 cr, vs ₹112.70 cr in Q4 FY21 |
| EBITDA per ton | ₹1,063, vs ₹1,242 in Q4 FY21 |
| PAT | ₹88.42 cr, vs ₹85.29 cr in Q4 FY21 |
| Full-year FY22 EBITDA | ₹379 cr, vs ₹361 cr in FY21 |
| Full-year FY22 PAT | ₹247 cr, vs ₹187 cr in FY21 (FY21 included extraordinary item of ₹64 cr) |
| Full-year FY22 EBITDA per ton | ₹1,112, vs ₹1,337 in FY21 |
| Volume | 11.52 lakh tons, vs 9.01 lakh tons in Q4 FY21 |
| Volume growth target (FY23) | ~17%, targeting ~0.4 crore tons for FY23 vs ~0.34 crore tons in FY22 |
| Siliguri plant utilization | ~65% in Q4 FY22, up from ~30% earlier; FY22 full-year utilization ~42% |
| Trade vs non-trade mix | 84% trade, 16% non-trade, same as last quarter |
| Lead distance | 219 km for FY22; Q4 FY22 ~218 or 217 km |
| Post-March price increase (West Bengal, Bihar) | ₹20–32 per ton |
| Post-March price increase (Northeast) | ₹10–15 per ton |
| Fuel cost (long-term agreement) | ₹1.35 per GCV landed, SFA contracts fixed for 5 years |
| Biomass substitution | ~10% of total energy requirements |
| Cash reserves | ~₹750 cr as of April-end; ~₹670 cr as on March 31 |
| Total CAPEX plan (next 2 years) | ~₹2,000 cr, approx ₹1,000 cr each year |
| Peak debt during expansion | ₹500–650 cr, expected to be repaid in 2–3 years |
| Branding expenditure (FY22) | ₹43–45 cr; expected to drop to ₹32–33 cr going ahead |
| Freight subsidy outstanding | ~₹12 cr; ₹25 cr received in April out of ₹37 cr total outstanding |