Star Cement Ltd Q1 FY2026 Concall Summary

Source transcript PDF: https://www.stockscans.in/document/tfhst1qgcfs450z6905p6h95.pdf

Key Takeaways


Quarterly Performance

Tushar Bhajanka: "The Quarter 1, because of the early monsoon, the volume has taken a bit of a hit. I think in Quarter 2, because now we do not have as much monsoon in northeast, I think the subsequent months are picking up well. So, I think it will take another full quarter to actually see whether volumes will end up. But I do think that it may be realistic to get that kind of a growth."

Expansion Pipeline

Tushar Bhajanka: "Right now, we are trying to just secure a mine. But if you are able to secure a mine, then we plan to do a CAPEX of, we plan to put up about 3-million-ton clinker plant along with 0.4 crore ton grinding in Rajasthan, which would basically be about Rs. 2,400-Rs. 2,500 crores CAPEX overall."

Market & Competitive Position


Balance Sheet & Capital Allocation

Tushar Bhajanka: "the subsidy does not remain an amount which is just showing in the books and never received by the company. So, in our case, it has"

Energy Strategy

Tushar Bhajanka: "if you put up your own plants, then your base cost is only the cost of the O&M of the plant, solar or wind. So, your variable cost falls to 0.6-0.7. So, I think in the long run, it makes much more sense for them and companies if they want to be competitive to kind of put up their own plants"

Guidance & Commitments

CommitmentSpecificsTimeline
Volume guidance0.54-0.55 crore tons for FY26FY26 full year
Silchar grinding unit commissioningConstruction started, all permissions obtainedJan/Feb FY26 (Q4)
Jorhat grinding unit commissioningEC application in one month, clearance in 3-4 monthsJan/Feb FY27 (Q4)
Rajasthan mine auction outcomeParticipating in Jaisalmer auctionNews expected in one week
Rajasthan plant (if mine secured)0.3 crore ton clinker + 0.4 crore ton grinding, ₹2,400-₹2,500 Cr CAPEX~3 years from mine acquisition
Bihar plant evaluation0.2 crore ton grinding unit under assessmentDecision in a quarter or two
Subsidy backlog collection~₹150 Cr outstandingBefore Q2 end
Ongoing subsidy receiptEach quarter's subsidy received by end of next quarterFrom FY26 onward
Premium cement shareTarget 18% of salesBy FY26 year-end
AAC block revenue₹70-₹80 Cr this year, 20-30% higher next yearFY26 and FY27
Green energy roadmapEY engagement delivering comprehensive planClear roadmap in one month
EBITDA outlook₹850-₹900 Cr from this year onwardFY26 and beyond
Debt comfort ceilingComfortable up to ~₹1,500 Cr in worst caseOngoing

Key Metrics

MetricQ1 FY26
Revenue₹847 cr, vs ₹736 cr same quarter last year
EBITDA₹230 cr, vs ₹118 cr same quarter last year
EBITDA per ton₹1,774, vs ₹1,018 same quarter last year
Profit after tax₹98 cr, vs ₹31 cr same quarter last year
Incentive booked₹62 cr, vs ₹75-₹76 cr in Q4 FY25
Full-year incentive guidance₹220-₹250 cr
Cement sales volume12.22 lakh ton, vs 11.54 lakh ton same quarter last year
Northeast cement sales8.97 lakh ton, vs 8.50 lakh ton same quarter last year
Outside Northeast cement sales3.25 lakh ton, vs 3.04 lakh ton same quarter last year
Clinker production8.90 lakh ton, vs 6.86 lakh ton same quarter last year
Cement production12.31 lakh ton, vs 11.80 lakh ton same quarter last year
Trade sales share81%
Premium cement share12.2%, improved from 6%-7% a year back; target 18% by year-end
Fuel cost (Kcal)1.35, vs 1.54 last quarter
Alternative fuel substitution18% of fuel mix
Net debt₹320 cr, vs ~₹300 cr in March quarter
CAPEX incurred₹62 cr
Northeast market share27%-28%
Northeast market size~1.4 crore ton, expected ~10% CAGR