Star Cement Ltd Q1 FY2027 Concall Summary

Source transcript PDF: https://www.stockscans.in/document/rvwoogw6aarcqwgmsc6h26ub.pdf

Key Takeaways


Quarterly Performance: The Subsidy Cliff, Absorbed

Tushar Bhajanka: "If we actually exclude that hit of INR40 crores, then I think we were positive EBITDA in terms of percentage in absolute terms, which shows that there was resilience."

Volume Trajectory: Floods, Elections, and a Back-Half Bet

Tushar Bhajanka: "I think we expect to probably revise the numbers. A bit from 11% to 12% to about 8% to 9%."

Rajasthan Expansion: From Paper to Ground

Tushar Bhajanka: "It would be about 18 to 20 months from November onwards, I guess. So it means about quarter 1 of FY29 or quarter 4 of FY28."

Cost & Logistics Initiatives: The Next 3-6 Months

Tushar Bhajanka: "Only for quarter 2 because the shutdown cost also gets added in the cost in quarter 2 and also because in Northeast, the rain is more so of course, the fixed costs are getting absorbed by a lower volume. So it may be about INR1,400 for quarter 2, but I think we'll catch up in quarter 3 and 4."

Capital Allocation: West Bengal vs Bihar, and the QIP Question

Tushar Bhajanka: "I don't think it makes sense to put 0.1 crore in West Bengal and 0.1 crore in Bihar because the overall capex of a grinding unit along with the railway siding in a greenfield project sometimes may not -- may need economies, which may not come with the 0.1 crore ton grinding unit."

Subsidy Mechanics & Non-Cement Businesses

Tushar Bhajanka: "The hit that the books are facing because of the subsidy will stop being felt after September onwards, and you'll start seeing a growth thereafter."

Guidance & Commitments

CommitmentSpecificsTimeline
Full-year FY27 volume growth8-9% (revised from 11-12%)FY27
Q2 volumeNo significant stride expected; Assam floodedQ2 FY27
Q3/Q4 volumeDouble-digit growth on pent-up demandH2 FY27
Full-year clinker saleStagnant or degrow 5-10% vs FY26FY27
Fuel costFall to ₹1.45Q2 FY27
Full-year EBITDA per ton₹1,500-₹1,600FY27
Q2 EBITDA per tonAbout ₹1,400Q2 FY27
Rajasthan ECExpected by September end or first week of OctoberSep-Oct '25
Rajasthan construction startMid-October to NovemberOct-Nov '25
Rajasthan plant completion18-20 months from November startQ4 FY28 to Q1 FY29
Silchar railway sidingOperationalOctober-November '25
EV introductionOn some typical routesNext 5-6 months
Siliguri wagon tipplerSave ₹150/ton on Siliguri salesNext 3-6 months
Non-cement revenueReach ₹150 crores ARRQ4 FY27
West Bengal vs Bihar grinding unit decisionAfter West Bengal industrial policy (expected Aug 15)Next investor call
Grinding unit commissioningOne unit if demand continuesNext 2-3 years
FY27 capex₹500 croresFY27
FY28 capex₹1,500-odd croresFY28
Assam subsidy receivablesClear everything up to June '25Undated

Key Metrics

MetricQ1 FY27
Revenue₹902 crores, vs ₹847 crores same period last year
EBITDA₹203 crores, vs ₹230 crores last year
Profit after tax₹74 crores, vs ₹98 crores last year
EBITDA per ton₹1,497, vs ₹1,774 per ton same quarter last year
Cement sales volume13.02 lakh tons, vs 12.22 lakh tons same quarter last year
Clinker sales volume0.52 lakh tons, vs 0.74 lakh tons same quarter last year
Northeast cement sales8.71 lakh tons, vs 8.67 lakh tons same quarter last year
Outside Northeast cement sales4.31 lakh tons, vs 3.55 lakh tons same quarter last year
Cement production13.08 lakh tons, vs 12.31 lakh tons same quarter last year
Clinker production9.10 lakh tons, vs 8.90 lakh tons same quarter last year
Trade share~80% of overall sales
Premium sales share15.9% of overall sales
Clinker factor66.5%
Lead distance~210 km
Fuel cost1.55, up from ₹1.33 in Q4 FY26; Q2 expected at ₹1.45
Green share (incl. WHRS)~3%
Fuel mix, FSA~45%
Fuel mix, spot coal~30%
Q1 capex spent₹93-odd crores
FY27 planned capex₹500 crores, unchanged
FY28 planned capex₹1,500-odd crores
North expansion capex₹2,600–2,700 crores, excluding GST; ~₹2,900 crores with GST
FY27 incentive expectation~₹115 crores, revised down from ~₹145 crores due to Assam subsidy spreading
Assam incentive outstanding₹130 crores
Total Assam incentive book₹794 crores
Q1 GST subsidy hit₹40 crores, due to GST reduction from 28% to 18%
July volume degrowth~12% YoY
Northeast volume growth, Star~0.4% YoY in Q1
Northeast industry growth, Q1~1% to 1.5%
FY27 Northeast industry growth expectation~7%
FY27 Star Northeast growth hope8% to 9%
FY27 cement volume growth guidance8% to 9%, revised down from 11% to 12%
FY27 clinker sale outlookStagnant to degrowth of 5% to 10% vs FY26
Q2 FY27 EBITDA per ton estimate~₹1,400
Full-year FY27 EBITDA per ton estimate₹1,500–₹1,600
Non-cement revenue guidance₹150 crores revenue, expected on ARR basis by Q4
Northeast clinker capacity, FY26 end1.55–1.6 crore tons
Northeast grinding capacity, FY26 end2.3–2.4 crore tons
Expected capacity addition, next 3 years0.1 crore tons each from 2 players
Siliguri wagon tippler expected savings~₹150 per ton on Siliguri sales
One-off donation and incentive reduction next quarter₹60–70 crore saving vs Q1
Rajasthan plant timeline18 to 20 months from November 2026, i.e. Q4 FY28 or Q1 FY29
Rajasthan planned capacity0.3 crore tons grinding, 0.33 crore tons clinker, plus 0.2 crore tons in Jhajjar
Debt-to-EBITDA expectation1.5x–1.6x if approvals are healthy