Steamhouse India Ltd Guidance Report - SOIC x StockScans Report
as of Nov 2026
- ROE and ROCE to improve as IPO funds are deployed
Pending - At the Q2 FY27 PPT, management noted ROE moderated post-IPO due to fresh capital infusion, with returns expected to improve as funds are deployed into growth projects. H1 FY27 ROE was 4.53% and ROCE 12.97% (not annualized), versus FY26 ROE of 22.36% and ROCE of 16.06%.
- 3.04 MW solar installation at Ankleshwar
Delivered - The Q1 FY27 PPT noted a 3.04 MW (AC) ground-mounted solar project at Ankleshwar with a wheeling agreement signed May 29, 2026, reiterated in the October 2026 announcement. The solar project stands installed and the wheeling agreement was signed May 29, 2026; no operational data has been disclosed.
- Coal purchases converted from credit to cash from May 2026
Delivered - At the Q1 FY27 call, management said coal purchases were converted from credit to cash post May 2026, lowering fuel cost. Coal purchases were converted entirely to cash post May 2026, listed alongside solar installation and inventory optimization as structural changes.
- Sarigam utilization recovery via new customer onboarding
On track - At the Q1 FY27 call, management said Sarigam utilization had dipped after missing a big customer but improved in Q1 FY27 after onboarding two-three new good customers, with discussions ongoing with two-three bigger ones. Q1 FY27 utilization improved after onboarding new customers; no specific Sarigam utilization figure was disclosed for Q2 FY27.
- PM Mitra park discussions with Ministry of Textiles
Pending - At the Q1 FY27 call, management noted PM Mitra park discussions were ongoing, including with the Ministry of Textiles. The Union Minister of Textiles visited Steamhouse India and discussed the Community Boiler System; no formal agreement has been reported.
- Participation in Gujarat Bulk Drug Park tender
Pending - At the Q1 FY27 call, management noted the Gujarat Bulk Drug Park tender is live and the company is participating, reiterated at the Q2 FY27 call. No award or outcome has been reported as of 2 Nov 2026.
- Coal trading discontinued from 1 April 2026
Delivered - The Q1 FY27 PPT stated coal trading was discontinued with effect from 1 April 2026 and the company does not intend to undertake such activities in the future. Coal revenue was nil in Q1 FY27 and Q2 FY27, with the business exited and stopped.
- Additional 750 Nm³/hr PSA nitrogen plant by end CY 2026
On track - The Q2 FY27 PPT stated an additional 750 Nm³/hr PSA nitrogen plant will be installed at the existing Ankleshwar facility, with commissioning expected by end of CY 2026, reiterated in the October 29, 2026 announcement. No commissioning has been reported; the existing 350 NM³/hr plant has been operational since February 1, 2025.
- Dahej Proposed Facility - 30 TPH by October 2027
On track - The DRHP stated the Dahej Proposed Facility will have 30 TPH installed capacity, greenfield using Indonesian coal, commissioning targeted for October 2027 subject to Net Proceeds receipt by February 2026. The IPO listed on September 17, 2026, but nil proceeds had been utilised toward Dahej GIDC Phase 2 as of 30 Sept 2026.
- Pirana (Ahmedabad) 30 TPH green boiler by CY 2027
On track - The DRHP stated the Pirana project, costing ₹695.00 million including ₹347.50 million subsidy, had approvals not yet in place and expected operations start in calendar year 2027; the Q2 FY27 PPT gave commissioning target CY 2027. No commissioning has been reported and approvals were not yet in place as of the DRHP.
- Vapi Phase 3 30 TPH green boiler by CY 2026
On track - The DRHP stated the Vapi Phase 3 project, costing ₹400.00 million with all approvals in place, would start operations in calendar year 2026 with a customer tie-up for 150 to 400 TPD; the Q2 FY27 PPT set commissioning target CY 2026 with 15.2 TPH contracted. No commissioning has been reported; the 15 TPH Vapi WTE ran at 77.6% utilization in FY26.
- Jhagadia 30 TPH coal boiler by November 2026
On track - The DRHP stated the Jhagadia project, costing ₹150.00 million with all approvals in place, would start operations in calendar year 2026 with a customer tie-up for 6 to 22 TPH; the Q2 FY27 PPT set commissioning target November 2026 with 14.80 TPH contracted. No commissioning has been reported; the November 2026 target was imminent as of 2 Nov 2026.
- Nandesari Phase 2 30 TPH green boiler by CY 2026
On track - The DRHP stated the Nandesari Phase 2 project, costing ₹394.26 million with all approvals in place and 30 TPH on refuse-derived fuel and/or agro-waste, would start operations in calendar year 2026; the Q2 FY27 PPT set target CY 2026 with 17.5 TPH contracted. No commissioning has been reported; Nandesari Phase 1 (30 TPH) commenced operations in September 2023.
- IPO - fresh issue of 43,580,246 shares
Delivered - The DRHP stated the IPO comprised 51,111,110 equity shares of face value ₹2 each, with 43,580,246 as fresh issue and 7,530,864 as offer for sale. The IPO completed and shares listed on NSE and BSE on September 17, 2026, aggregating ₹414 crore.
- IPO proceeds for general corporate purposes - ₹231.25 mn, revised to ₹283.79 mn
Delivered - The DRHP listed general corporate purposes at ₹231.25 mn as an IPO object, later revised to ₹283.79 mn due to lower actual issue expenses. As of 30 Sept 2026, ₹270.75 mn of the revised ₹283.79 mn had been utilised, leaving ₹13.04 mn unutilised.
- IPO proceeds - Dahej GIDC Phase 2 capex of ₹381.74 mn
Pending - The DRHP outlined a new manufacturing facility at Dahej SEZ, with IPO objects listing the Dahej GIDC steam manufacturing facility (Phase 2) at ₹381.74 mn. As of 30 Sept 2026, nil had been utilised of the ₹381.74 mn.
- IPO proceeds - Panoli Phase 2 capex of ₹379.76 mn
Pending - The DRHP outlined expansion by installing new boilers at Panoli (Phase 2), with IPO objects listing Panoli Facility Phase 2 capacity expansion at ₹379.76 mn. As of 30 Sept 2026, ₹5.00 mn had been utilised of the ₹379.76 mn.
- IPO proceeds - Ankleshwar Phase 3 capex of ₹379.77 mn
Pending - The DRHP stated Ankleshwar Phase 3 total estimated cost is ₹35.1 crore excluding GST, with ₹35.1 crore of Net Proceeds earmarked; IPO objects listed the expansion at ₹379.77 mn. As of 30 Sept 2026, nil had been utilised of the ₹379.77 mn.
- IPO proceeds - debt repayment of ₹1,800 mn
On track - The DRHP earmarked ₹150 crore of Net Proceeds toward repayment or prepayment of outstanding borrowings, with IPO objects listing ₹1,800.00 mn. As of 30 Sept 2026, ₹1,418.95 mn had been utilised; gross debt fell from ₹2,816.22 mn at FY26 to ₹2,672.42 mn at H1 FY27, and net debt from ₹2,711.11 mn to ₹909.32 mn.
- Hydrogen and oxygen expansion where commercially viable
Pending - At the Q1 FY27 call, the CMD stated intent to gradually scale the nitrogen business and expand into hydrogen and oxygen where commercially viable; the Q2 FY27 PPT said the company is evaluating hydrogen, oxygen and other gases based on customer requirements. No project has been announced; the company is working with several gas players on ASU (cryogenic) options, including self-execution and build-own-operate models.
- Haryana MoU - ₹500 crore industrial infrastructure opportunities
Pending - The Q2 FY27 PPT stated an MoU signed with Haryana Enterprises Promotion Centre, Government of Haryana, exploring ₹500 crore of proposed industrial infrastructure investment, including cluster-level steam generation and pipeline distribution, subject to feasibility, demand, environmental requirements and statutory approvals. The MoU stands signed; no further progress has been reported as of 2 Nov 2026.
- Surat Municipal Corporation 400 TPD Waste-to-Steam EOI
Pending - The Q1 FY27 PPT stated the company submitted an Expression of Interest to Surat Municipal Corporation for a proposed 400 TPD Waste-to-Steam project with a 20-year tenure, extendable up to 10 years after completion, reiterated in D7. The EOI stands submitted; no award or further progress has been reported as of 2 Nov 2026.
- Una revenue-sharing - 9% of revenue to Himachal Pradesh
Pending - At the Q1 FY27 call, the CFO stated Steamhouse will share 9% of revenue with Himachal Pradesh Bulk Drug Park Infrastructure Limited on Una, to be recovered from end consumers with nothing from Steamhouse's pocket, reiterated at the Q2 FY27 call. No agreement signing or revenue-sharing commencement has been reported as of 2 Nov 2026.
- Una EBITDA margin of 8% to 10%
Pending - At the Q1 FY27 call, the CMD said Una EBITDA margin should be around 8% to 10% clear margin on an EBITDA-per-ton basis, while flagging it as "still not finalized" pending agreement signing, reiterated at the Q2 FY27 call. The margin structure remains unfinalized; no agreement signing has been reported as of 2 Nov 2026.
- Una Bulk Drug Park - 300 TPH community boiler, ₹311 crore EPC
On track - At the Q1 FY27 call, management described the Una Bulk Drug Park project: a 300 TPH community boiler facility with an EPC mandate of \~₹311 crores inclusive of GST, asset-light, funded by Himachal Pradesh Bulk Drug Park Infrastructure Limited, including long-term O&M, reiterated at Q2 FY27 and in D7/D8. The tender stands awarded at ₹311 crore inclusive of GST, with the revenue-sharing period envisaged from April 2032 to March 2052.
- Haldia steam purchase agreement - operations in H1 FY28
On track - The Q2 FY27 PPT stated a five-year Steam Purchase Agreement signed April 2026 at Haldia, West Bengal, with operations expected in H1 FY28. The agreement was signed with a food processing industry at Haldia; no operations have been reported as of 2 Nov 2026.
- Dahej SEZ steam purchase agreement - operations in H1 FY28
On track - The Q2 FY27 PPT stated a five-year Steam Purchase Agreement signed April 2026 at Dahej SEZ, with operations expected in H1 FY28. Two steam trading/distribution agreements were signed - one at Dahej SEZ and one at Haldia, West Bengal; no operations have been reported as of 2 Nov 2026.
- Green boiler capacity up 7x from 15 TPH to 105 TPH in FY27
On track - The Q1 FY27 PPT stated green boiler capacity would increase 7x from 15 TPH in FY26 to 105 TPH in FY27, within a FY27 split of coal 360 TPH plus green 105 TPH for 465 TPH total, reiterated in the Q2 FY27 PPT and D5/D7. Installed capacity remained 345 TPH as of Q2 FY27 with green capacity still 15 TPH; Nandesari Phase 2 and Vapi Phase 3 (30 TPH each) target CY 2026 and Pirana (30 TPH) CY 2027.
- FY27 revenue and EBITDA growth similar to Q1 levels
On track - At the Q1 FY27 call, the CMD said full-year revenue and EBITDA growth would be "almost same for both the numbers," adding "we will try to maintain, not saying that we will maintain", reiterated at the Q2 FY27 call. Q1 FY27 revenue grew 13.35% YoY and EBITDA 60.08%; H1 FY27 revenue growth was 7.63% YoY and EBITDA growth 65.72%.
- 30-35% EBITDA CAGR over three years
On track - The Q1 FY27 PPT stated a target of sustained EBITDA growth of 30-35% CAGR over the next three years, supported by capacity expansion, operational excellence and new growth opportunities, reiterated in the Q2 FY27 PPT, with soft reaffirmations of "We will try. Yes, we hope so" at both calls. H1 FY27 EBITDA was ₹556.15 mn, +65.72% YoY, with Q1 +60.08% and Q2 +73.38% YoY against FY26 EBITDA of ₹83.49 crore.
- Sanjoo Dyeing steam purchases to continue for next few quarters
On track - At the Q1 FY27 call, the CMD said related-party steam purchases from Sanjoo Dying and Printing Mills will continue "at least for next few quarters," possibly stopping if new Sachin GIDC-area projects materialize, reiterated at the Q2 FY27 call. Coal trading with Sanjoo Dyeing was discontinued from 1 April 2026, while the steam purchase arrangement in Sachin continued as of the DRHP with no change disclosed in Q2 FY27.
- Margins maintained or better after coal trading exit
Delivered - At the Q1 FY27 call, the CMD said margin levels "can be maintained and can be even better going forward" now that the low-margin coal trading business has been exited, reiterated at the Q2 FY27 call. Q1 FY27 EBITDA margin was 24.05% versus 17.03% in Q1 FY26, Q2 FY27 was 19.28% versus 11.39%, and H1 FY27 was 21.67% versus 14.08%.
- Finance cost moderation during FY27
Missed - At the Q1 FY27 call, the CFO expected finance cost to moderate during FY27 as IPO proceeds repay high-cost borrowings, reiterated at the Q2 FY27 call and the Q1 FY27 PPT. Q2 FY27 finance costs were ₹96.33 mn, +55.00% YoY, and H1 FY27 ₹165.55 mn, +49.91% YoY, despite ₹1,418.95 mn of IPO proceeds utilised toward debt repayment and gross debt down to ₹2,672.42 mn.
- Working capital days of 40-45, revised to 35-40
Pending - At the Q1 FY27 call, the CFO guided to 40 to 45 days positive working capital cycle going forward; at the Q2 FY27 call he revised this to 35 to 40 days. No specific working capital days figure was disclosed for Q1 or Q2 FY27; trade receivables are billed fortnightly with payments typically realized between the 7th and 15th day.
- Operating cash flow at \~1.2x EBITDA maintained
Missed - At the Q1 FY27 call, the CFO stated Q1 operating cash-flow was around 1.2 times EBITDA and that going forward this ratio "should continue... or should be a bit lower", reiterated at the Q2 FY27 call. H1 FY27 net cash flow from operations was negative at -₹576.86 mn, primarily due to payment of trade payables funded through debt and equity capital raised during H1.
- FY27 EBITDA per ton at par with or better than Q1 FY27
On track - At the Q1 FY27 call, the CFO stated on an annual basis FY27 should be at par with or better than Q1 FY27 delivery, barring Q2/monsoon, reiterated at the Q2 FY27 call. Q1 FY27 EBITDA per ton was ₹1,011, Q2 was ₹818.32, and the H1 average was ₹915.54; the full-year outcome is not yet available.
- EBITDA per ton of \~₹1,000 maintained
On track - At the Q1 FY27 call, the CFO said EBITDA per ton of \~₹1,000 "can be safely assumed... will be maintained" for the next few quarters, with new waste-based facilities at ₹1,000 or better and Q2 flagged as a monsoon exception each year, reiterated at the Q2 FY27 call. Q1 FY27 delivered ₹1,011; Q2 fell to ₹818.32, down 19.09% QoQ on monsoon seasonality; H1 averaged ₹915.54, +44.93% YoY.
- Volume growth of 5-10% at current locations; 20-25% company-level
On track - At the Q1 FY27 call, the CMD expected 5% to 10% volume growth at current locations with current installed capacity, and on an analyst's suggestion of 20-25% company-level growth the CFO said "Yes, very comfortably", reiterated at the Q2 FY27 call. Steam sales grew 16.70% YoY in Q1 and 12.06% in Q2, with H1 FY27 steam sold up 14.35% YoY.
- New boilers at \~50% utilization initially
Pending - At the Q1 FY27 call, the CMD stated newer boilers being commissioned are expected to run at \~50% utilization in the very initial months after commissioning, reiterated at the Q2 FY27 call. No new boilers were commissioned during the record period; Panoli, commissioned June 2025, had H1 FY26 utilization of 3.61%.
- Capacity utilization taken to 60% to 65%
On track - At the Q1 FY27 call, the CMD stated intent to take capacity utilization to 60% to 65%, "the optimum utilization that we wish to take it to", reiterated at the Q2 FY27 call. Q1 FY27 utilization was 41.40%, Q2 was 42.41%, and H1 was 41.91% versus 37.03% in H1 FY26, with management noting lower utilization leaves room for incremental demand.
- Additional ₹170 crore capex over 15-18 months for IPO projects and Tarapur
Pending - At the Q1 FY27 call, the CFO stated intent to do another ₹170 crore worth of capex in the next 15 to 18 months for the IPO end-use projects and Tarapur, reiterated at the Q2 FY27 call. As of 30 Sept 2026, ₹5.00 mn of IPO proceeds had gone to Panoli Phase 2 and nil to Ankleshwar Phase 3 and Dahej GIDC Phase 2, with no total capex-vs-plan disclosure.
- \~₹55-60 crore capex to complete four under-construction projects
Pending - At the Q1 FY27 call, the CFO stated another \~₹55-60 crores of capex was needed to take all four under-construction projects live, restated at \~₹60-odd crores at the Q2 FY27 call; the Q2 FY27 PPT put approximately ₹50 crore for the 90 TPH green boiler projects. No capex deployed against the plan has been disclosed; FY26 capex was ₹130 crore with CWIP rising from ₹116 crore to ₹165 crore.
- Tarapur 60 TPH facility go-live Q4 FY28, revised to CY 2027
On track - At the Q1 FY27 call, the CFO stated the 160 tonnes per hour Tarapur capacity should go live in Q4 FY28, restated at the Q2 FY27 call as the 60 TPH Tarapur project in Q4 FY2028; the Q2 FY27 PPT moved the target to CY 2027, matching the DRHP's calendar year 2027 start with approvals not yet in place and cost ₹450.00 million. No commissioning has been reported; project cost is estimated at ₹45 crore with approvals still pending as of the DRHP.
- Steam distribution capacity expansion from 345 TPH to \~705 TPH
On track - At the Q1 FY27 call, management targeted expanding steam distribution capacity from 345 TPH to approximately 705 TPH via four under-construction projects, IPO-proceeds projects and Tarapur; the Q1 FY27 PPT set annual installed capacity rising from 2,185,920 TPA to 4,466,880 TPA, and the Q2 FY27 PPT dated each project from November 2026 (Jhagadia) through CY 2028, with D8 noting a potential \~1,005 TPH platform including Una. Installed capacity remained 345 TPH across 7 boilers as of Q2 FY27, with H1 FY27 utilization at 41.91% and no commissioning yet reported.