Key Takeaways
- Strong revenue, margin timing hit: Revenue grew 29.4% YoY on healthy volumes and inventory liquidation, but EBITDA margin fell 387 bps YoY to 24.5% as input cost pass-throughs lagged and the company absorbed new product development and pre-hiring costs.
- FY27 growth guidance raised to ~30%: Management lifted its full-year revenue outlook from 25%, citing improved volume visibility for Q3 and Q4.
- Capacity expansion deepened: The board approved an additional 3,250 tons and ₹31 crores, taking the total expansion to 11,750 tons and ₹151 crores, with the new foundry targeted for April 2028 commissioning.
- Margins face a Q3 squeeze before Q4 relief: Input costs fell in July–August (benefit passed on in Q3) but rose again from September (absorbed in Q2, recovery expected in Q4), so Q3 carries both the give-back and the temporary absorption.
- What to watch next quarter: Whether the Q4 pass-through recovery materializes as input costs stay elevated, the pace of new-part commercialization from the 32 developed, and any tariff normalization back to pre-April 2025 levels.
Revenue Growth & Volume Drivers
- Q2 dispatch surge drew down inventory: Revenue growth was amplified by liquidation of inventory built during Q1, so dispatch volumes exceeded production volumes, pushing capacity utilization down to 57% from approximately 66% QoQ.
- H2 seasonality supports the raised guide: Management noted H2 is historically stronger than H1, and with improved Q3 and Q4 volume visibility, raised FY27 revenue growth guidance to approximately 30%.
- End-market demand anchored in commodities: Customers expect commodity prices to stay elevated, driving investments in mining, earthmoving, construction and railroad, while the China Plus One strategy adds tailwinds.
- Customer wallet share expanding: Existing customers are willing to develop more parts with Steelcast versus competition, and 15 of 32 new parts developed in H1 have already been commercialized.
- Export-domestic mix normalizing: Export share fell to 52% from 64% YoY, but management expects exports to be slightly above domestic in H2 and sees a long-term band of 50% ±5% for each.
Tamboli: "What we have been hearing from our customers is that the commodity prices are likely to be staying at elevated levels. ... So the higher commodity prices are leading to an increase in demand in these 4 industries. Second, there are also some tailwinds of China Plus One strategy, which is also helping us."
Margin Walk & the Pass-Through Timing Mismatch
- Three factors compressed Q2 margins: Approximately ₹1 crore in new product development spend (trials, rework), increased employee expenses from recruiting and training ahead of the foundry expansion, and a timing mismatch on input cost pass-throughs.
- The pass-through mechanics hurt twice: Raw material costs rose ₹2 crores QoQ, driven by increases from the first week of September, and natural gas prices spiked nearly 100% versus February levels, both absorbed in September with customer price corrections expected only in Q4.
- Q3 gets squeezed from both sides: The benefit of lower input costs during July–August must be passed on to customers in Q3, while the September cost increase remains unrecovered until Q4, so Q3 margins carry both the give-back and the temporary absorption.
- Operating leverage is present but diluted: Higher volumes will help, but the benefit is partly offset by input cost increases not yet passed on, additional people costs for the new facility, and ongoing development expenditure.
- Full-year margin view held at 25–26%: Management acknowledged Q3 pressure but expects Q4 recovery through pass-through and higher volumes, keeping the full-year EBITDA margin in the 25–26% range.
Tamboli: "Input costs declined during July and August. The benefit of that reduction will need to be passed on to customers in Q3. However, input prices began increasing again from the first week of September. We absorbed the impact of this increase during September, while the corresponding customer price revision is expected to be reflected in Q4."
Capacity Expansion & Capex
- Expansion deepened to 11,750 tons: The board approved an additional 3,250 tons (₹31 crores) with an electric arc furnace, extending product weight capability to castings up to approximately 3.5 tons from the current 2.5 tons.
- Total capex now ₹151 crores: The incremental investment phases alongside the original ₹120 crore project across FY27 and FY28, with approximately ₹60 crores expected by March 2027 and the balance in FY28.
- New foundry targeted for April 2028: Management is targeting commissioning around 1 April 2028 while making efforts to complete earlier if feasible; CNC machine orders worth ~₹35 crores placed in September, with deliveries staggered from January 2027 to January 2028.
- Renewable energy build-out underway: A 2.4 MW hybrid plant and 1.4 MW solar plant are under commissioning, targeted by 31 December 2026, expected to save ~₹4.5 crores annually in power costs. An additional 6 MW of solar is needed for the existing facility (target March 2028) and 15 MW for the new facility, with land acquisition in progress.
- Long-range plan assumes ~90% utilization by FY29: Management has factored in adequate manpower to support that level, with the FY29 volume mix targeting mining at 35%, earthmoving at 36%, and newer segments like GETs at 6% and railways at 5%.
Tamboli: "So with all these factors in mind, we expect good growth over the next 3- to 4-year period. And the additional capacity will further increase volumes of the company."
End-Market Mix & Diversification
- Mining and earthmoving dominate, but the base is broadening: These two sectors remain the core, but management is building railways, GETs (ground-engaging tools), and construction into material contributors, targeting a shift from ~90% concentration to 60–65% over 3–5 years.
- Railways and GETs have explicit FY29 targets: Railways expected to reach 5% of sales and GETs ~6% by FY29, with the remaining mix split across mining (35%), earthmoving (36%), construction (12%), locomotive (5%), transportation (1.5%), and cement/steel/defense (~1% each).
- European certification opens a new export door: A recently received certification should strengthen eligibility and customer development opportunities in Europe, with business contribution expected to increase gradually as customer approvals and qualification cycles progress.
- Defense deprioritized: Indian defense is no longer a focus area; export defense prototypes have been made and may materialize over 3–6 months, but management has no ambitious plans for the segment.
- Tariffs absorbed so far, normalization expected: Tariffs came in during April 2025 and have gone through 2–3 revisions; customers have been absorbing the increase, and management expects rates to eventually return to pre-April 2025 levels.
Balance Sheet & Cost Structure
- Debt-free with strong returns: The company remained debt-free for a third consecutive year, with free reserves of ~₹120 crores, ROCE of 28.8% and ROE of 21.9% in H1 FY27.
- Logistics risk sits with customers: All sales have been on an ex-works basis for the last five years, so logistics cost volatility does not affect the company.
- Order book visibility is short but supplemented by forecasts: Physical purchase orders generally represent 3–4 months of sales, with the balance based on customer forecasts and rolling production plans.
- Power cost savings are structural, not cyclical: The renewable energy push targets ~80% captive power generation, with the 2.4 MW hybrid and 1.4 MW solar plants alone expected to save ~₹4.5 crores annually once commissioned by December 2026.
Guidance & Commitments
| Commitment | Specifics | Timeline |
|---|---|---|
| FY27 revenue growth | Approximately 30% (raised from 25%) | FY27 full year |
| FY27 EBITDA margin | Broad range of 25–26% | FY27 full year |
| Existing facility utilization | Broadly around 60% | FY27 full year |
| Renewable plants (2.4 MW hybrid + 1.4 MW solar) | Commissioned, saving ~₹4.5 crores annually | By 31 December 2026 |
| Additional 6 MW solar for existing facility | Commissioned to meet 80% captive target | By 31 March 2028 |
| New foundry (11,750 tons total expansion) | Commissioned, capex of ₹151 crores | Around 1 April 2028 (efforts to complete earlier) |
| FY27 capex | Approximately ₹60 crores | By 31 March 2027 |
| Long-term sustainable EBITDA margin | Around 25% | 2- to 3-year horizon |
| FY29 capacity utilization | Around 90% | FY29 |
| GETs revenue share | ~6% of total sales | FY29 |
| Railways revenue share | ~5% of total sales | FY29 |
| Mining/earthmoving/construction concentration | ~60–65% of business (down from ~90%) | 3- to 5-year horizon |
Key Metrics
| Metric | Q2 FY27 |
|---|---|
| Revenue from operations | ₹138.0 cr, +29.4% YoY and +10.6% QoQ |
| EBITDA (excl. other income) | ₹33.8 cr, +11.8% YoY |
| EBITDA margin | 24.5%, vs 28.3% in Q2 FY26 and 25.6% in Q1 FY27 |
| Profit after tax | ₹23.4 cr, +0.6% YoY |
| PAT margin | 16.9%, vs 21.8% in Q2 FY26 and 19% in Q1 FY27 |
| H1 FY27 revenue | ₹262.8 cr, +23.2% YoY |
| H1 FY27 EBITDA margin | 25%, vs 27% in H1 FY26 |
| H1 FY27 PAT | ₹47.4 cr, +10.1% YoY |
| FY27 revenue growth guidance | ~30%, raised from earlier 25% guidance |
| FY27 EBITDA margin outlook | 26–27% broad full-year range; Q3 expected under pressure from pass-through timing |
| Sales volume | 4,370 tons, +28% YoY and +8% QoQ |
| Capacity utilization (existing 29,000 tons p.a.) | 57%, vs ~66% in Q1 FY27; FY27 expected around 60% |
| Export revenue share | 52%, vs 64% in Q2 FY26 |
| Executable order book | ~₹145 cr, equivalent to ~3 months of sales |
| New parts commercialized during FY27 | 15 (out of 32 developed, from a 111-part 3-year pipeline) |
| Return on capital employed (H1 FY27) | 28.8%, vs 28.6% in FY26 |
| Return on equity (H1 FY27) | 21.9%, vs 22.0% in FY26 |
| Free reserves | ~₹120 cr, invested across FDs, mutual funds and secured bonds |
| Total capacity expansion approved | 11,750 tons (to 40,750 tons), investment of ₹151 cr, commissioning targeted by March 2028 |
| Renewable energy portfolio | 13.3 MW planned; 9.5 MW commissioned, 2.4 MW hybrid and 1.4 MW solar under commissioning by 31 Dec '26, expected annual savings of ~₹4.5 cr |
| Additional product development spend in Q2 | ~₹1 cr over Q1 |
| Raw material cost increase in Q2 | ₹2 cr higher than Q1, from first week of September |
| GET revenue share | ~1.5% of sales currently; target ~6% by FY29 |