The Quarter That Was: Why Q3 Was Subdued

Nemlekar: "See, I tell you because real estate is not like FMCG business, where every quarter whenever we launch, the quarter goes up and when we complete some project, revenue gets recognized. So, normally, there can be a bulgy effect in quarters that way."

Project Pipeline & New Wins


Balance Sheet & Capital Position


Revenue Recognition Mechanics

Nemlekar: "So, revenue is recognized as per that percentage completion method. So, once the project is launched and we sell and we take the booking from the customers, 10% is received as per RERA we register their agreement of that unit. ICAI Institute rule, 25% of the work has to be completed to start recognizing the revenue in a project."

Execution Risks & Constraints

Nemlekar: "The challenge is having skilled manpower in the sustainable development. So, the biggest challenge for execution will be having the skilled labor going forward. Having the skilled carpenter, skilled mason, skilled fitters, skilled plumbers, so that is going to be a challenge, and a lot of skill development will have to be done at that level to get the project execution."

Competitive Positioning & Strategy


Guidance & Commitments

CommitmentSpecificsTimeline
Revenue recognitionOC for Param and Gurukrishna projects, unlocking revenue from already-achieved salesBy March (Q4 FY25)
Project launchesOver ₹1,000 crores of projects to be launched, subject to approvals and RERANext 2-3 quarters
Prabhadevi project launchLaunch of ~₹500 crore redevelopment project, subject to approval and RERAQ2 or Q3 of next financial year (FY26)
Pipeline execution₹2,500 crores of existing project pipeline executedOver next 3-5 years
Growth targetCompany should grow at least 20%No specific year stated
EBITDA margin improvementIncremental improvement from debt reduction and better-located projects; reflection expectedQ4 FY25 or next Q1/Q2
Skilled labor capacityWill need to get more skilled labor into the workforceOver next 3-5 years

Key Metrics

MetricQ3 FY25
Standalone revenue₹26.62 cr
Standalone EBITDA₹3.94 cr, EBITDA margin of 14.80%
Standalone net profit₹1 cr, net profit margin of 3.76%
Consolidated revenue₹30.90 cr
Consolidated EBITDA₹5.80 cr, EBITDA margin of 18.77%
Consolidated net profit₹2.03 cr, net profit margin of 6.56%
9M FY25 standalone revenue₹67.74 cr
9M FY25 standalone EBITDA margin21.67%
9M FY25 standalone net profit₹6.03 cr, net profit margin of 8.9%
9M FY25 consolidated revenue₹110 cr
9M FY25 consolidated EBITDA margin15.47%
9M FY25 consolidated net profit₹6.49 cr, net profit margin of 5.70%
Consolidated debt₹55 cr as of end December, reduced by ₹25 cr in the quarter
Standalone debt₹35 cr as of end December
Capital raised₹86 cr via equity shares and convertible warrants
Credit ratingAcute BBB+ with stable outlook, upgraded during the quarter
Total acquired project pipeline₹2,500 cr of projects shared on the Exchange
Projects in execution pipeline₹700 cr (Param Project-1 and Hedavkar Wadi at Prabhadevi), execution over 3-5 years
New redevelopment projects (Malad East and Prabhadevi) combined revenue potential₹730 cr
Prabhadevi project expected topline₹500 cr
Sumit Param project topline₹400 cr, launched in August
Projects expected to launch in next 2-3 quarters₹1,000 cr plus, subject to approvals and RERA
Revenue growth targetAt least 20%
Minimum project size going forward₹200 cr plus
Space under constructionMore than 15 lakh sq ft
Completed projects legacy64 plus projects, 45 lakh sq ft developed, 7,000 plus apartments delivered