Key Takeaways
- Transformative year, capacity tripled: FY26 marked entry into high-voltage large power transformers (up to 200 MVA, 220 kV) as the new Kannur facility commenced production, expanding annual capacity from 2,500 to 9,000 MVA.
- Revenue guidance of ₹275–300 crores for FY27: The ₹585 crore order book supports the target, with ₹400–420 crores planned for execution this year and 30% of the backlog spilling into FY28.
- Margins held despite raw material inflation: A 1% to 1.5% PAT margin dip versus last year was contained by advance booking of transformer oil and strategic copper procurement; operating margin guidance of 15–16% is maintained.
- New facility ramp-up is the near-term execution risk: 150–200 people deployed in the last 2–3 months, but getting output from newly appointed workers is a challenge; management expects 3–4 months to reach expected output.
- What to watch next quarter: Whether Q1 revenue lands in the planned ₹50–60 crore band, the pace of new-facility output ramp, and progress on the 160 MVA, 220 kV prototype test needed to unlock the higher-voltage market.
Demand Environment
- Structural tailwinds intact: India’s peak power demand touched ~256 GW, and accelerated investment in renewable energy, transmission infrastructure, AI-driven data centers and grid modernization is driving demand for high-capacity, energy-efficient transformers.
- Large power transformer opportunity: Management sees huge demand for transformers above 100 MVA and 160 MVA over the next 5 years, but the company must first complete its 220 kV prototype test to participate fully.
- Order book composition confirms the shift: Power transformers now account for 73% of the ₹585 crore order book, with distribution transformers at 20% and inverter duty transformers at 6–7%.
Vee Rajmohan: "Definitely. The demand is very huge. Huge demand is there; a number of data centers are coming up. And the government is also interested in more -- investing in power sector and in renewable energy also, they are very much interested, both the State government and the Central governmental all put together they are very much interested in renewable energy. So, the demand is there."
Capacity Expansion & Ramp-Up
- New Kannur facility now operational: Commercial production has commenced, expanding annual capacity from 2,500 MVA to 9,000 MVA and adding capability to manufacture power transformers up to 200 MVA and 220 kV voltage class.
- People, not machines, are the bottleneck: All machines are installed and a senior leadership team with 30–35 years of experience is in place, but 150–200 people deployed in the last 2–3 months are still being trained; management expects 3–4 months to get the required output from newly appointed workers.
- Full utilization still 2–3 years away: Peak capacity utilization of ~90% is expected in 3 years, with output ramping gradually through FY27.
- Tank factory expansion planned: A new tank manufacturing facility on a 1-acre plot will be built this financial year at a capex of ₹20–25 crores, operational next financial year; tanks currently bought from outside represent 5–8% of turnover and are increasingly difficult to source.
Vee Rajmohan: "The thing is now by hand working people is a challenge, and we already deployed 200 people on that. Output, we are -- the task is to get the output from the newly appointed people. So it will take 3 to 4 months to ramp up and get required or expected output."
Margins & Cost Management
- Raw material inflation contained: A sudden increase in transformer oil and other key materials caused a 1% to 1.5% PAT margin dip versus last year; the company limited the damage by booking a large quantity of transformer oil in advance and strategically procuring copper.
- Larger transformers carry higher gross margins but higher overheads: Management estimates 1–2% more margin on larger power transformers, but this is eaten away by the cost of more skilled people and human resources, so net margins are expected to be maintained at similar levels.
- Price variation clauses provide partial protection: Deliveries beyond 3–4 months have a price variation clause; for shorter-cycle deliveries, the company places back-to-back purchase orders with vendors upon receiving the customer PO to lock in input costs.
- Tank factory to support margins modestly: The steel/iron portion on a transformer is 6–7%; in-house tank manufacturing will support supply chain reliability and improve margin slightly, though management declined to quantify the benefit.
- Q1 margin visibility: Most raw material for Q1 was booked in March, so H1 EBITDA margins should sustain unless a force majeure event occurs.
Vee Rajmohan: "We believe the same type of margins will be maintained because since there is a 1% or 2% more margin on larger power transformers, and we -- that has been eaten away by the overheads because we deploy more skilled people, more human resource."
Orders & Credential Building
- ₹264.27 crore in orders from Karnataka EPC players: Multiple transformer orders secured, alongside ₹159.94 crore in distribution transformer orders from Tamil Nadu Power Distribution Corporation and a ₹57 crore power transformer order from Kerala State Electricity Board.
- Higher-voltage orders secured as credential-builders: The company received an order for a 160 MVA, 220 kV class transformer and a 112 MVA, 333 kV class transformer, plus a 50 MVA order requiring a prototype test; these will be produced and tested this year to build credentials for larger power transformers.
- 220 kV certification on an accelerated timeline: Management had expected the prototype test cycle to take 1.5–2 years, but the marketing team secured a 160 MVA order immediately, pulling the timeline forward; the prototype test is now planned for December/January, after which the company can continuously supply 220 kV class transformers.
- Higher voltage ambitions are gated: A plan exists to go up to 765 kV, but not in the next 2–3 years; the priority is fully utilizing the new plant first. In Phase 2, with additional testing equipment, the company can reach 300–330 kV.
Vee Rajmohan: "We need to do a prototype test prototype. We have to make one 160 MVA transformer voltage class of 220 kV that we have to design, manufacture and it has to be tested in CPRI... And in our case, generally, it will take 2 years or 1.5 years from this stage. But as Supreme marketing team was done well, they got an order for 160 MVA immediately."
Manufacturing & Execution
- Lead times vary by product: Distribution transformers take 4 weeks from first material arrival; power transformers up to 25 MVA take 6–8 weeks; 50–100 MVA units take 3–4 months; inverter transformers take 6–8 weeks, with variation by size and customer requirement.
- Order book execution cadence: 30% of the current order book (₹173 crores) will be executed in FY28; ₹400–420 crores is planned for execution this year, with ₹270–300 crores expected to convert to revenue depending on customer payment cycles and raw material production cycles.
- Q1 revenue planned at ₹50–60 crores: Revenue will gradually increase in Q2 and Q3 as the new facility ramps up; per an analyst’s math, H1 revenue could reach around ₹120 crores, though management did not confirm the figure, stating only that it will increase gradually.
- Working capital discipline: Receivable days reduced sharply to 94 days, reflecting strong collection discipline and healthy cash flow management.
Guidance & Commitments
| Commitment | Specifics | Timeline |
|---|---|---|
| FY27 revenue | ₹275 crores to ₹300 crores | FY27 full year |
| FY28 revenue | Add another ₹100 crores on top of FY27 | FY28 full year |
| PAT margin | 10% to 12% maintained | FY27 full year |
| Operating margin | 15% to 16% maintained | FY27 full year |
| New facility ramp-up | Reach expected output from newly appointed people | 3–4 months |
| Tank factory | Complete construction; capex ₹20–25 crores | This financial year; operational next financial year |
| 220 kV prototype test | Design, manufacture and test 160 MVA, 220 kV transformer at CPRI | December/January (end of this calendar year) |
| Full capacity utilization | Reach ~90% utilization of 9,000 MVA capacity | 3 years |
| Main board migration | Board on the main board | Plan exists, no date given |
Key Metrics
| Metric | FY26 |
|---|---|
| Total income | ₹182.1 cr, +21.78% YoY |
| EBITDA | ₹33.29 cr, +14.52% YoY |
| PAT | ₹20.44 cr, +9.89% YoY |
| EPS | ₹8.15 |
| H2 FY26 total income | ₹106.75 cr, +41.66% HoH |
| H2 FY26 EBITDA | ₹19.01 cr, +33.18% HoH |
| H2 FY26 PAT | ₹11.03 cr, EPS ₹4.40 |
| H2 FY26 EBITDA margin | 14.6% |
| PAT margin decline | 1.5% drop, raw material cost pressure partially offset by advance procurement |
| FY27 revenue guidance | ₹275 cr to ₹300 cr |
| FY28 revenue guidance | ₹375 cr to ₹400 cr, another ₹100 cr added on FY27 |
| Order book | ₹588.17 cr as of May 27, 2026 |
| Order book split | 72% power transformers, 20% distribution transformers, 8% inverter duty transformers |
| Order book by customer type | 66.37% non-government (₹388.35 cr), 33.63% government (₹196.79 cr) |
| Annual manufacturing capacity | 9,000 MVA, expanded from 2,500 MVA |
| New facility revenue potential | ₹500 cr to ₹550 cr at optimal utilization |
| New facility FY26 contribution | ₹20 cr to ₹25 cr |
| Old facility utilization | 70% to 78% |
| Receivable days | 94 days, reduced sharply |
| Tank manufacturing capex | ₹20 cr to ₹25 cr, expected operational next financial year |
| CRGO procurement cost | ₹180 to ₹250 per kg, varies by grade |
| Q1 FY27 revenue plan | ₹50 cr to ₹60 cr |