Key Takeaways
- Record order book, execution lagging: The order book crossed 5.1 GW after the landmark 1.166 GW NTPC Green win, but Q2 deliveries were just 256 MW as monsoon disruptions and project-site readiness held back offtake.
- Margins dipped on deliberate investment: EBITDA margin softened as the company layered in IT, ESOP and ramp-up costs to support a much higher future delivery run-rate; management insists the same cost base can handle far larger volumes.
- The supply-vs-commissioning gap is real and industry-wide: Out of 770 MW commissioned in Q1, ~600 MW were turbines supplied in FY21–22 that had been stuck; Q3 onwards, COD is expected to improve quarter-on-quarter as these legacy projects unlock.
- Renom opens the multi-brand O&M door: The acquisition, consolidated for ~25 days in Q2, marks Suzlon's entry into servicing third-party turbines, a segment management sees as adjacent and accretive.
- What to watch next quarter: Whether the promised H2 delivery ramp materialises as project sites dry out, the pace of order book conversion from the 5.1 GW backlog, and any quantification of the return on the cost investments now weighing on margins.
Order Book & the NTPC Win
- Landmark single order: The 1.166 GW NTPC Green order is the largest single order in the Indian wind industry's history, structured as a plug-and-play deal where land and power evacuation sit within NTPC's scope.
- Order book trajectory: The 5.1 GW backlog consists entirely of firm orders backed by financial commitments and advance payments; management is "pretty confident" that each of the next two quarters will be announced as the highest closing order book ever, citing a significant active pipeline.
- Execution timeline: The entire 5.1 GW order book is expected to be completed in the next 18 to 24 months, with all projects carrying confirmed schedules. NTPC supplies should commence by end of Q3 and ramp significantly from Q4.
- No order inflow guidance: Management declined to put a number on tentative FY25 order inflows, stating they only announce when contracts are signed and down-payment received.
JP Chalasani: "I am pretty confident we will continue to do that at least for next two quarters we need to say that this is the highest closing order. It's not that it's going to stop at 5.1."
Execution: Deliveries, Constraints & the H2 Bet
- Q2 deliveries held back by site readiness, not manufacturing: Suzlon could have supplied close to 600 MW in Q2 but was constrained by projects not being ready to offtake; cyclone damage, transportation and logistics disruptions, and inundated sites were the binding constraints.
- Revenue tracks deliveries, not commissioning: Revenue is generated from turbine deliveries (256 MW in Q2 vs. ~270 MW in Q1), not from the industry commissioning numbers, so the commissioning pickup does not immediately translate to revenue.
- The stuck-turbine overhang is clearing: In Q1, ~600 MW of the 770 MW commissioned were turbines supplied in FY21 and FY22 that had been stuck due to temperature issues and connectivity problems; these are now getting unlocked, and COD is expected to improve quarter-on-quarter from Q3.
- H1/H2 skew persists: The normal pattern of one-third deliveries in H1 and two-thirds in H2 is expected to hold this year; management wanted to change it but could not do so meaningfully, and now targets a pattern shift next year.
- No penalty clause for client delays: When asked whether liquidated damages apply when clients delay project readiness, management stated that "in impracticality, it doesn't happen that way" and confirmed the company does not operate in that manner.
JP Chalasani: "Logically, you are right, sir, but in impracticality, it doesn't happen to that way. Let me not say that we will get there. We can put a claim, but at least we are not operating in that manner."
Margins & the Cost Investment Story
- EBITDA margin dipped on deliberate spend: The small decline in EBITDA margin percentage reflects investments in organizational buildup, technology (including an SAP S/4 HANA implementation), and a substantial ramp-up in capacity for future deliveries.
- Cost base is sized for much higher volumes: Employee costs rose on ESOP provisions (~₹32 crores, non-cash, continuing till FY26), annual increments, and administrative costs for future ramp-up; management states explicitly that the same cost base can support far higher deliveries than the current 256 MW quarterly run-rate.
- WTG margins have room to rise: WTG business EBITDA margins, currently around 7%, are expected to increase northwards as volumes rise; OMS EBITDA margins at ~40% are expected to maintain their trajectory. Management committed that margins at the EBITDA level for both businesses will "definitely not get compromised."
- Consolidated margin mix headwind: As the WTG business grows faster than OMS, consolidated margins will continue to be lower due to the mix effect.
- One Earth lease charge: The sale-and-leaseback of the corporate office creates a ~₹4 crore per month P&L charge; subleasing efforts have started and the expense will reduce as third-party rental income comes in.
Himanshu Mody: "Is the cost representative of the organization delivering 256 MW RR, the answer is no. With the same cost the organization can and is gearing up to deliver much higher RR in the future."
Manufacturing Capacity & Supply Chain
- 4.5 GW capacity by March 2025: Expansion across blades, towers and nacelles is committed and on track; the Pondicherry nacelle facility has already started production and is ramping up, Daman plant capacity is increasing significantly, and additional blade lines are being commissioned with cycle times improving on the 3 MW platform.
- Further expansion is conditional: Whether capacity goes beyond 4.5 GW will be evaluated based on the order book position at March 2025 and the 2–3 year outlook.
- SE Forge diversifying beyond wind: SE Forge is pursuing exports and entering non-wind segments including bearings for various industries, defence, railways, and castings for smaller gearboxes; a few orders have already been received and revenue is expected in the next four to five months.
Renom & the Multi-Brand O&M Entry
- Strategic entry into multi-brand services: The Renom acquisition gives Suzlon a foothold in the multi-brand O&M sector, leveraging Renom's strong independent service provider position alongside Suzlon's own expertise.
- Consolidation impact: Renom was consolidated on a line-by-line basis for a proportionate ~25-day period, as the acquisition was consummated in the first week of September.
- Services revenue lag: For Suzlon's own turbines, services revenue typically kicks in after the third anniversary of commissioning, a three-year lag; the NTPC order is an exception where services revenue begins from day one.
Competition, Diversification & Unanswered Questions
- Solar is off the table: Management flatly denied ever speaking about entering solar, reiterating the company remains in its core wind business and anything connected to it; they are willing to take a full project including solar if a client wants a single supplier, but no such request has been received.
- Energy storage: a soft no: When asked about acquiring an energy storage domain company, management said "at this stage... no" but added "I am not saying outrightly no," leaving the door slightly ajar for future exploration.
- Chinese competition not addressed: An analyst asked specifically about competitive intensity from Chinese players; management discussed competition generally and stated they will not compromise on margins, but did not address the specific question about Chinese players' impact on pricing or market share.
- NTPC pricing contradiction: Management initially answered "No" when asked if NTPC would have different terms and lower realisation per MW, then immediately clarified that competitive bidding with a PSU means different pricing compared to normal commercial terms.
- No 5 MW turbine confirmation: Asked about R&D for a 5 MW model, management deflected, saying the right turbine size will be launched when necessary, with no confirmation or denial.
- No share consolidation planned: Management declined the suggestion of share capital consolidation to improve EPS, stating there are "no impending such thoughts."
JP Chalasani: "I have no idea about what was written in the Moneycontrol because we never spoke about getting into solar and We've been on record always saying that we would remain in our core business, and anything connected with that is what we will keep doing it."
Guidance & Commitments
| Commitment | Specifics | Timeline |
|---|---|---|
| Order book execution | Entire 5.1 GW firm order book completed | 18–24 months |
| NTPC supply commencement | Supplies begin end of Q3, ramp significantly from Q4 | Q3 FY25 onwards |
| Manufacturing capacity | Reach 4.5 GW per annum across blades, towers, nacelles | By March 2025 |
| H2 delivery skew | One-third H1, two-thirds H2 pattern to hold this year | FY25 |
| WTG EBITDA margin direction | Increase northwards from current ~7% as volumes rise | Volume-dependent |
| OMS EBITDA margin trajectory | Maintain current growth trajectory at ~40% | Ongoing |
| SE Forge non-wind revenue | Orders received to materialise into revenue | Next 4–5 months |
| Balance sheet cleanup | Clean up legacy reserves and negative items | 6–7 months |
| One Earth lease cost reduction | ₹4 crore/month expense to reduce as subleasing income comes in | As third-party rental materialises |
Key Metrics
| Metric | Q2 FY25 |
|---|---|
| Revenue | ₹2,093 cr, +48% YoY |
| EBITDA | ₹294 cr, +31% YoY |
| EBITDA margin | 14.1%, down from 15.9% in Q2 FY24; investments in organizational buildup and capacity ramp |
| PAT | ₹201 cr, +96% YoY |
| Net worth | ₹4,495 cr as of September 2024 |
| Net cash position | ₹1,277 cr as of September 2024 |
| Deliveries | 256 MW, up from 132 MW in Q2 FY24 |
| Order book | 5.1 GW, executable over 18 to 24 months |
| Manufacturing capacity | 3.1 GW currently, ramping up to 4.5 GW by March 2025 |
| WTG business gross margin | ~22% |
| OMS business gross margin | ~67% |
| OMS fleet under service | 15 GW in India, machine availability above 96% |
| Industry installations H1 FY25 | 1,476 MW, below expectations due to monsoon disruptions |
| Renom consolidation period | ~25 days in Q2, following acquisition consummated in first week of September |
| One Earth lease charge | ~₹4 cr per month P&L impact from sale-and-leaseback |