Key Takeaways
- Losses narrowed but debt rose: Net loss shrank to INR 99 crores from INR 299 crores QoQ, yet net debt climbed to INR 1,374 crores as legacy projects in Australia and the US demanded fresh funding to reach closure.
- Legacy drag is nearly done: The remaining international order book of INR 450 crores should be completed mostly by Q4, with gross margins on new non-legacy projects expected to normalize at 10–11% by Q1 FY24.
- A Reliance-shaped future is assumed but undefined: Management operates on the assumption it will be the preferred EPC subcontractor for Reliance projects, yet cannot yet answer questions on advance percentages, working capital structure or year-wise rollout.
- Nigeria mega-order inches forward: A framework agreement worth up to $10 billion with US EXIM backing is under negotiation; phase 1 at roughly $2 billion is expected to be signed soon, though the timeline remains open-ended.
- What to watch next quarter: Whether the Nigeria contract actually gets signed, the pace of debt reduction as legacy projects close, and any concrete detail on the Reliance relationship that moves it from assumption to order book.
Legacy Project Wind-Down
- Revenue collapse: 9M FY23 revenue fell 51% YoY because of lower contribution from ongoing EPC projects, though Q3 revenue inched up 1.7% QoQ on higher O&M contribution.
- Margin suppression: Gross margins remained suppressed primarily on account of international EPC projects; all modules for old contracts were already supplied by Q1 FY23, so the recent decline in module prices to $0.20–$0.21 does not create positive margin on legacy work.
- What remains: The balance legacy international order book of INR 450-odd crores is expected to be completed mostly by Q4, with possible slight overflow into the first or second half of FY24. Remaining work on these projects is subcontractor and commissioning costs only.
- O&M margin drag: O&M margins improved sequentially to 6.7% in Q3 from negative 13% in Q2, but were still impacted by projects where O&M costs are being incurred without revenue recognition because clients are delaying final handover. Normalization is expected in coming quarters.
- Q4 FY23 outlook: Balance legacy projects carry very little margin; with roughly INR 90 crores of overheads and INR 30 crores of interest, positive EBITDA is not likely. Gross margin at the operating level should be positive because all losses have been accounted for.
Bahadur Dastoor: "The company has accounted for the losses on its ongoing projects. It today has a UOV of about INR 2,700 crores and if one were to look at projects, which are going to be on a no profit, no loss situation, the gross margins there would be between 10% to 11% on all of those. We expect that gross margins will normalize by first quarter of FY '24 and there is nothing much that one has to do now for the ongoing projects."
Debt & Liquidity
- Debt build-up: Net debt rose to INR 1,374 crores because legacy projects in Australia and the US required funding to bring them to closure; a reduction in payables of roughly INR 300 crores and overheads of almost INR 90 crores also had to be paid, plus borrowings to close off payments coming up in January, February and March.
- Q4 debt increase expected: Management anticipates a further INR 200–300 crores increase in Q4 to close existing projects and meet overheads, with debt expected to come down significantly only by Q4 FY24.
- Promoter indemnity inflow: The INR 66 crores received from promoters was against money the company had already paid out, so it was not a free inflow; the company also had to make payments of roughly INR 35–40 crores against those indemnity assets in the quarter.
- Customer refunds: Approximately INR 350 crores was refunded by customers for two of the four projects where advances or performance bank guarantees totaling INR 588 crores were encashed.
- Receivables improvement: Receivables due more than one year declined to INR 325 crores from INR 362 crores as of September 30, 2022.
- No equity fundraising: Management stated there is nothing to disclose on equity fundraising; any such discussion would have already been disclosed to the stock exchanges. Only borrowings of INR 250–300 crores are planned to meet project closure obligations.
Bahadur Dastoor: "Under no circumstances, can any loan assistance be given to the promoter group because our articles prevent it from happening."
Order Book & Pipeline
- Q3 wins: Awarded a 242 MW project from Amplus Solar (PETRONAS Group) in Bikaner, Rajasthan and a 60 MW project from AMPYR Energy in Koppal, Karnataka; total new orders approximately INR 364 crores. Both are without modules, all in India, so commodity price risk is lower.
- NTPC contract signed: The contract agreement for the 1,570 MW DC BOS package at Khavda RE Power Park was signed in October 2022; bid value INR 2,212 crores inclusive of taxes and 3-year O&M. A mobilization advance of roughly INR 220 crores has been received and project mobilization is in process. Revenue will start reflecting from Q1 FY24.
- Nigeria MOU: A US step-down subsidiary signed an MOU with the Government of the Federal Republic of Nigeria along with consortium partners Sun Africa for 916 MWp solar plus 455 MWh BESS. Financing is under negotiation between US EXIM, ING and the Government of Nigeria; the company is in the process of finalizing the D and EPC agreement. Phase 1 at roughly $2 billion is expected to be signed soon, within a total framework agreement for $10 billion. Nigeria orders require modules complying with US specifications from US manufacturers, so the decline in global module prices does not change the order value.
- FY24 order inflow target: $1 billion on a steady-state basis, excluding the Reliance portfolio and one-off large projects like Nigeria, with 10–15% year-on-year growth.
- India tilt: Approximately 55% of the current and foreseeable future bidding pipeline is India, excluding the Reliance mega project. The Indian order book is expected to grow significantly this year.
- Order selectivity emerging: In 2–3 quarters, management sees a situation where EPCs can pick and choose orders based on margin, with margins and order book both improving in the coming few quarters.
Amit Jain: "Certainly, the margins and the order book both will improve in the coming few quarters. And that trend will go for further few years going down the line."
The Reliance Relationship
- Preferred EPC assumption: Management assumes the company will be the preferred EPC subcontractor for Reliance projects as and when they are announced, with scope on the BOS side because Reliance will supply modules. No formal order exists yet.
- Unanswered questions: Management could not answer what percentage of advance would be received from the Reliance project, whether working capital would remain negative, or what the year-wise rollout plan looks like, stating these will be decided between the two parties once the order is received.
- Funding constraint: The company cannot afford to fund a project of Reliance's sheer scale; management will try to keep things as lean as possible, aiming for breakeven or negative working capital if all things remain the same and the agreement is at arm's length.
Bahadur Dastoor: "Obviously, with the infusion that Reliance has done into this company, we would assume and our assumption continues to remain strong, that we will be the preferred EPC subcontractor for the projects as and when they are announced."
Market Environment & Risk Management
- US market: Ordering activity is expected to pick up significantly in 2023 so that projects can be operational by 2025, with tax credits due to expire in 2025.
- India market: Ordering activity is likely to further gather pace, with private IPPs and PSU pipeline continuing to grow and a resolution of GIB issue, which had held up some projects in Rajasthan. Management foresees lumpiness in order inflow, with stronger companies expected to take a larger portion of the market in future and lower level players moving out.
- Risk guardrails: A risk register has been developed, discussed by the Risk Committee of the Board, and measures put in place to avoid repetition of past mistakes. For international orders, price variation clauses and methodologies are being built into contracts to ensure all the price fluctuation does not land on the EPC subcontractor.
- Steel prices: Steel prices were at their lowest points when new jobs were taken; any further reduction could provide small benefits but will not reflect in gross margin even in Q4 FY23 because most of these new projects commence either towards the fag end of FY23 or in the first quarter of FY24.
Amit Jain: "So effectively, by being there in the space and one of the largest players in the world, we are definitely going to ride that phase and cash it out on it totally."
Guidance & Commitments
| Commitment | Specifics | Timeline |
|---|---|---|
| Gross margin normalization | 10–11% on new non-legacy projects | Q1 FY24 |
| Legacy international order book completion | INR 450-odd crores balance to be completed | Mostly by Q4 FY23, slight overflow into H1 FY24 |
| Net debt reduction | Significant decrease from peak | By Q4 FY24 |
| FY24 order inflow | $1 billion steady-state, 10–15% YoY growth (ex-Reliance, ex-Nigeria one-offs) | FY24 |
| Nigeria phase 1 signing | ~$2 billion D and EPC agreement | "Soon" (no date given) |
| O&M margin normalization | New site additions to contribute to top line | FY24 |
Key Metrics
| Metric | Q3 FY23 |
|---|---|
| Revenue growth | +1.7% QoQ, aided by higher O&M contribution; -51% YoY for 9MFY23 |
| Net loss | ₹99 cr, vs ₹299 cr in Q2 FY23 and ₹429 cr in Q3 FY22 |
| Gross margin outlook | 10–11% expected on new non-legacy projects; legacy projects in no-profit-no-loss situation |
| O&M gross margin | 6.7%, vs -13% in Q2 FY23 |
| O&M revenue share | 7.3% of 9MFY23 revenue, totaling ₹141 cr |
| Net worth | ₹218 cr as on Dec 31, 2022 |
| Cash and cash equivalents | ~₹181 cr as on Dec 31, 2022 |
| Net debt | ₹1,374 cr as on Dec 31, 2022; expected to rise by ₹200–300 cr in Q4 FY23 |
| Average borrowing cost | 9.5–9.7% |
| Negative working capital | ₹140 cr as on Dec 31, 2022, vs ₹272 cr as on Sep 30, 2022 |
| Receivables due >1 year | ₹325 cr as on Dec 31, 2022, down from ₹362 cr as on Sep 30, 2022 |
| Unexecuted order book | ₹2,703 cr as on Jan 18, 2023, 84% domestic EPC, executable over 18 months |
| New orders in Q3 FY23 | ~₹364 cr, two domestic solar EPC contracts (242 MW + 60 MW) |
| Order inflow target (steady-state) | $1 bn per year, with 10–15% YoY growth, excluding Reliance and one-off large projects |
| Solar O&M portfolio | ~7 GW, with ~1/3 third-party O&M |