Tata Power Company Ltd Q1 FY2025 Concall Summary

Source transcript PDF: https://assets.stockscans.in/docs/8ab1iz0627onustb95phti4a.pdf

Key Takeaways


Execution & Project Pipeline

Sinha: "We don't want to take a project and then get stuck with them, which stuck because of the transmission or the evacuation arrangements not being available."

Solar Rooftop Opportunity

Sinha: "There is a huge uptick. And it is something to the extent of 10x more than what we saw last year. So great opportunity. It's a question of how quickly we can convert them and execute these orders."

Pumped Storage & Hydro

Sinha: "Well, nothing less than what we get in CERC."

Financial Performance & One-Offs


New Business & Regulatory Developments

Sinha: "First of all, thank you. But I really don't know what to tell you very frankly. We are still waiting to hear from the government and also the identified public enterprise who would be working with us. So this is, it's very, very preliminary."

Guidance & Commitments

CommitmentSpecificsTimeline
Capex deploymentINR20,000 crores investmentThis financial year
Cell plant commissioningFirst 2 GW this month, next 2 GW next month, full capacity thereafterQ3 FY25
Project executionMore than 3 GW this year, more than 4 GW next yearFY25 and FY26
Pumped storage construction start1,000 MW projectLater this calendar year
Pumped storage construction start1,800 MW projectMid-next year
Pumped storage equipment orderFinalize orderBy October
Stressed asset transmission Part BComplete implementationThis financial year
TBCB transmission projectsBecome operationalFY26
Tata Steel hybrid projectPart commissioning this year, balance next yearFY25 and FY26
Solar rooftop revenueMeaningful accretionBy Q4 FY25
Working capital collectionBalance of deferred EPC receivablesAugust and September
Section-11Extension or amicable solution expectedBy October 15

Key Metrics

MetricQ1 FY25
RevenueNot stated [1-14]
Consolidated EBITDANot stated [1-14]
Consolidated PATNot stated [1-14]
Net debt₹42,000 cr, increased by ₹4,300 cr during the quarter
Net debt to underlying EBITDALess than 3x
Net debt to equityLess than 1.1x
Capex incurred in Q1₹4,000 cr, nearly 60% in renewable, balance 40% in transmission and distribution
Full-year capex guidance₹20,000 cr, 55-60% renewable, 30% T&D, 10-15% thermal, pumped hydro and Bhutan
Credit ratingUpgraded to AA+ stable from AA+, both ICRA and CARE
Delhi Distribution operating profit₹554 cr, versus ₹321 cr in Q1 FY24; includes onetime tariff order impact of ₹163 cr
Renewable capacity under implementation (own)More than 5 GW of utility scale renewables
Third-party EPC under implementationNearly 3 GW
Total projects under implementationNearly 8 GW
RE commissioning target FY25More than 3 GW, including own and third-party projects
RE commissioning target FY26More than 4 GW, including own and third-party projects
Rooftop solar installationsMore than 1 lakh cumulative
Rooftop solar inquiry growth10x more than last year
Pumped hydro storage pipeline2,800 MW, 1,000 MW to possibly start later this calendar year, 1,800 MW by mid of next year
Bhutan hydro project capacity600 MW, investment of nearly ₹6,900 cr, Tata Power 40% equity
Tata Steel hybrid project agreement966 MW signed, part commissioning this financial year, balance next financial year
Tata Steel projects already executedNearly 100 MW, another 100 MW under finalization
Cell and module plant capacity4 GW module plant at full capacity; cell plant first 2 GW commissioning this month, next 2 GW next month, full capacity from Q3
Power demand growthNearly 11% in the last quarter
Negative working capital impact~₹2,500 cr during the quarter, due to deferred payments from large EPC projects
Section-11 applicabilityIn place until 15th of October