Tata Power Company Ltd Q2 FY2024 Concall Summary

Source transcript PDF: https://assets.stockscans.in/docs/4tt6r59oyzfkri68z08o3x0d.pdf

Key Takeaways


Profitability Engine: Core Business Offsets Coal Decline

Praveer Sinha: "Our stand has been consistent. Those places where we will get better margin, we will execute those projects."

Clean Energy Build-Out: Capacity, Manufacturing, and Storage

Sanjeev Churiwala: "The approach to hydro feasibility is very simple. That will enable us to kind of deliver the RTC ambitions that India has. Because pure solar or pure wind will have its own limitations on a large-scale deployment and very clearly given that we are putting up this on our own reservoir our CAPEX cost and our per unit cost should be very, very competitive."

Thermal & Merchant: Mundra’s Limbo and a Two-Year Demand Window

Praveer Sinha: "Mundra right now is till June '24 and as you rightly mentioned that there is a huge demand of power, and this is expected to continue next year also. So, I think for next 2 years it looks like there will be a shortage of power and there will be huge demand and we expect that if we have to meet 100% requirement some of the imported coal plants have to operate under Section 11."

Odisha Turnaround: Cleaning the Books, Billing What Is Real


Project Pipeline & Capital Allocation


Guidance & Commitments

CommitmentSpecificsTimeline
Clean energy capacity3,760 MW under implementation to be completed, reaching 9,300 MW (~50% of total)Next 2 years
2030 clean energy mix70% of installed capacity from clean sourcesBy 2030
Cell production startBegin production at the 4.3 GW plantJanuary 2024, stabilize by March-April
Module production stabilizationStabilize trial production at the new plantNext 2–3 months
Pumped hydro approvalsAll regulatory approvals in placeMarch-April 2024
Pumped hydro construction startWork to begin on the 2,800 MW Maharashtra PSPMid-2024
Pumped hydro commissioning2,800 MW operationalMid-2027 (36 months from start)
Renewable commissioning pace~1 GW this year, 1.5–2 GW average per year thereafterCurrent year and ongoing
Odisha DISCOM platform completionAll four platforms finished, delivering consistent billing and collectionNext 2 quarters
Mundra Section 11Plant operates under cost-plus directive; management expects extension given power shortageThrough June 2024, with expectation of extension
EPC margin targetDeliver 4–5% margin on the EPC businessOngoing
PSP minimum returnAt least 15% ROE on the ₹13,000 crore investmentProject lifetime

Key Metrics

MetricQ2 FY24
Consolidated PAT₹1,017 cr, +9% YoY
Revenue growth+9% YoY
EBITDA growth+51% YoY
Half-year revenue>₹30,000 cr
Half-year EBITDA₹6,092 cr
Half-year PAT₹1,924 cr, +6% YoY
Net debt₹36,609 cr, declined by ₹1,140 cr in Q2
Net debt to underlying EBITDA2.65x
Net debt to equity1.02x
Clean energy portfolio5,500 MW, 38% of installed capacity
Renewable capacity under implementation3,760 MW, to be completed in next 2 years
Commissioned renewable capacity4.2 GW, with 3.6 GW pipeline for total ~8 GW
EV public chargers~4,900
EV home chargers~62,000
Orissa DISCOMS PAT~₹90 cr in Q2, ₹154 cr in H1
EPC business margin~4% in Q2
EPC projects cancelled₹1,158 cr, mutually terminated due to client land and clearance issues
Regulated equity~₹11,850 cr as of Sep 30, up ~₹1,900 cr YoY
Mundra debt~₹11,000–12,000 cr
H1 CAPEX spent~₹4,500 cr
Full year CAPEX estimate~₹11,000 cr (+/-10%)
Pumped storage project capital outlay~₹13,000 cr for 2.8 GW PSP
Coal price (current)~$80/tonne, down from $135–$140/tonne in same period last year
Peak power demand241 GW, >10% of previous year
Power demand growth (last quarter)~13% YoY
Cumulative power demand growth (last 2 years)~22%
Other income from Trombay Unit 6 equipment sale₹52 cr
Arutmin sales proceeds received₹230 cr, cash flow only, no P&L impact
Zambia hydropower payment receivedUSD 5.1 cr, 50% share of USD 10.2 cr
Meters replaced in Odisha (last 3 years)25 lakh