Key Takeaways
- Highest-ever quarterly PAT, up 33% YoY: performance was broad-based across all businesses, with traditional generation EBITDA rising 37% YoY on a combination of efficiency and DSM.
- RE capacity addition missed H1 targets as evacuation lines were delayed, but management expects to meet the full-year 2.5 GW target once lines are ready by December/January.
- Mundra resolution advancing: SPPA signed with Gujarat and filed at CERC, two more states expected to conclude before December, and the majority-decision clause means it will then bind all five DISCOMs.
- Pumped storage bet is scaling fast: the Board approved a second 1,800 MW project (Shirwata, ₹11,871 crore) on top of the 1,000 MW already under construction, with management signalling more proposals may follow.
- What to watch next quarter: whether evacuation lines actually come in by December/January to unlock the RE pipeline, the CERC order on the Mundra SPPA, and the Singapore Court of Appeal hearing on 19 January.
Mundra Resolution & Regulatory Assets
- SPPA progress: the SPPA with Gujarat has been filed at CERC and is now reserved for order; two other states are in very advanced discussion and expected to conclude before December. Under the PPA condition, once a majority of states decide, the SPPA becomes applicable to all five DISCOMs.
- Financial impact already booked: billing to all five DISCOMs is being done under the SPPA, and the impact is already considered in the quarterly accounts.
- Regulatory assets rose mainly due to Delhi and Odisha. In Delhi, the absence of a full quorum at the regulatory commission delayed true-up orders and tariff revisions; a full quorum is now in place.
- Amortisation path: in Delhi, the Supreme Court has advised amortising the regulatory asset over six years, i.e. till 2031; the commission is expected to come up with tariff revisions. In Odisha, a true-up is expected once the full commission is in place. Management expects the amortisation process to pick up pace in FY2028.
Praveer Sinha: "In Delhi, now already the Supreme Court has advised them that this regulatory asset needs to be amortized in six years period, that is till 2031."
Renewable Energy: Delays, Curtailment & the Full-Year Bet
- H1 capacity addition missed targets because evacuation lines were delayed; many projects are now ready and evacuation lines are expected by December or January. Management expects to meet the full-year target of 2.5 GW.
- RE curtailment worsened from 8.8% in Q1 to 11% in Q2, attributed to industry-wide transmission constraints. A connectivity pipeline and BESS installation are expected to ease this, with good line of sight on improvement in subsequent quarters.
- RE Genco EBITDA run-rate: management expects the full-year run-rate to be more than double H1, i.e. at least 60–70% higher than H1 (over ₹4,500 crore), because many plants came up in the last 3–6 months and their full impact will flow through in subsequent quarters.
- Rooftop solar subsidy is in place till March; management's information is that a new avatar of the subsidy will come beyond March, though it will be a little different from the existing one.
- Solar cell/module technology: no decision yet to shift the existing plant to TOPCon; a call will be taken later when market demand increases, as there is still huge demand for the existing product.
Traditional Generation & Coal JV
- Traditional generation EBITDA rose 37% YoY driven by a combination of efficiency improvements and DSM (Deviation Settlement Mechanism) gains. DSM gains were higher during summer but are not a very material amount; management did not provide the specific figure on the call.
- Sustainability aim: management aims to sustain the improved performance by finding means of improving efficiencies going forward.
- Coal JV profitability improved sharply driven by prevailing coal prices and geopolitical conditions. Momentum is expected to continue for the next 5–6 months, with profit in the ~₹400 crore range per quarter for the next two quarters; beyond that, management says it is very difficult to predict due to geopolitical conditions.
Praveer Sinha: "The coal prices are governed by geopolitical conditions. At least for next five to six months, I expect this will continue. Beyond that, it is very difficult to comprehend how things will change."
Pumped Storage & Capex
- Second pumped storage project approved: the Board approved an 1,800 MW pumped hydro project in Shirwata near Lonavala, with investment of ₹11,871 crore. This is in addition to the first 1,000 MW already under construction.
- Strategy: management is going big into pumped storage, looking at projects with one existing reservoir plus one new settling reservoir, evaluated over a 40+ year life. More proposals in other reservoirs may follow; long-term storage is seen as a very attractive solution.
- Timelines: the Bhivpuri PSP (first project) is expected operational in the first half of calendar year 2029; Shirwata PSP is expected commissioned in calendar year 2031.
- Full-year capex: the company is on track to complete nearly ₹25,000 crore for the year.
- Shirwata cost question: when an analyst asked what drove the large jump in Shirwata PSP capex from earlier estimates, management disputed that an earlier estimate existed and did not provide Greenfield cost guidance for a project requiring both reservoirs.
Power Demand & the Hydro Challenge
- Q2 power demand grew ~10–11% driven by a weak monsoon (higher agricultural demand) and cooling demand from heat waves and humidity; October continued at ~12% YoY growth.
- Hydro headwind: many hydro plants had low rains this year, so their generation capability next year will also be a challenge. Management expects huge power demand going forward, with many plants having to work at full capacity even during winter months.
- H2 seasonality: H2 is typically better than H1 because many projects and actions delayed by the monsoon in H1 get completed in H2; benefits from projects under implementation will start accruing in H2.
Praveer Sinha: "Since many of the hydro plants this year did not have enough rains, their capability to generate next year also will be a challenge. There will be huge demand of power going forward, and many of our plants will have to work at full capacity even during winter months."
Contingent Liabilities & Strategic Updates
- Singapore arbitration: the appeal in the Singapore International Commercial Court was rejected; the company has approached the Court of Appeal (Supreme Court of Singapore), with the matter listed for 19 January. Management strongly believes it has a good case on merit and law and expects to succeed.
- Kleros enforcement: Kleros has approached for enforcement, seeking to attach company shares in TPIPL and Bhira investments. Tata Power will formally respond within 14 days; the shares are pledged so banks will also be approached. The whole enforcement process is expected to take 3–6 months, within which finality in the Supreme Court of Singapore is expected.
- No provision taken: when asked whether the full ~$650 million would be provided if the Court of Appeal rules against Tata Power, management declined to engage with the hypothetical, stating the case is strong and there is no need to think about losing. The question was asked by an analyst, not stated by management.
- Ingot and wafer plant: all approvals received to start work, expected to begin this month (November 2026), with the plant fully operational by March 2028. The order has not yet been placed; management is examining implications of Chinese export controls, noting the Chinese government is reportedly having a rethink, with more clarity expected by end of November.
- Distribution privatisation: management awaits clarity from state and central governments on Electricity Act amendments, new electricity rules, and tariff rules; regulators are awaiting government notifications before deciding on applications.
- Georgia asset impairment: a ₹96 crore impairment was taken as the leftover amount from a prior impairment; attempts to revive operations failed, and a business trigger from a cash flow perspective led to the provision.
Sanjeev Churiwala: "No, I think we have a very strong case, right? That is why this has not been provided for. So, there's no need for us to think that we will lose the case."
Guidance & Commitments
| Commitment | Specifics | Timeline |
|---|---|---|
| Full-year capex | Complete nearly ₹25,000 crore | FY27 |
| RE capacity addition | Meet full-year target of 2.5 GW | FY27 |
| RE Genco EBITDA | Full-year run-rate more than double H1 (at least 60–70% higher than H1, i.e. over ₹4,500 crore) | FY27 |
| Mundra SPPA | Conclude with majority of states; expect CERC approval | By 31 December 2026 |
| Coal JV profitability | Profit in ~₹400 crore range per quarter | Next 5–6 months (next two quarters) |
| Bhivpuri PSP | Operational | First half of calendar year 2029 |
| Shirwata PSP | Commissioned | Calendar year 2031 |
| Ingot and wafer plant | Fully operational | March 2028 |
| Singapore arbitration (Kleros) | Finality expected in Supreme Court of Singapore | Within 3–6 months |
| Regulatory asset amortisation | Process expected to pick up pace | FY2028 |
Key Metrics
| Metric | Q2 FY27 |
|---|---|
| Revenue | ₹19,886 cr, +26% YoY to ₹19,886 cr from ₹15,769 cr |
| EBITDA | +5% YoY |
| PAT | ₹1,652 cr, highest-ever quarterly, +33% YoY from ₹1,245 cr |
| H1 FY27 Revenue | ₹38,784 cr, +17% YoY from ₹33,233 cr |
| H1 FY27 EBITDA | ₹8,494 cr, +7% YoY from ₹7,961 cr |
| H1 FY27 PAT | ₹3,053 cr, +22% YoY |
| H1 FY27 capex | ₹10,000 cr completed, full-year target ₹25,000 cr |
| RE Genco YTD EBITDA | ₹2,231 cr, annualized run rate ~₹4,500 cr |
| RE capacity addition target | 2.5 GW for FY27 |
| RE curtailment | ~11% in Q2, up from ~8.8% in Q1 |
| Regulatory assets (distribution) | ₹8,310 cr, +28% YoY |
| Traditional generation EBITDA | ₹351 cr, +37% YoY from ₹255 cr |
| Coal JV profit outlook | ~₹400 cr per quarter expected for next two quarters, conditional on geopolitical conditions |
| New pumped hydro project (Shirwata) | 1,800 MW, investment ₹11,871 cr, 75% debt / 25% equity |
| Georgia asset impairment | ₹96 cr, leftover from prior impairment |