Technocraft Ventures Ltd Guidance Report - SOIC x StockScans Report

as of Nov 2026

  1. IPO listing within three working days of bid closing Delivered - In the DRHP, the company committed to complete all formalities for listing and commencement of trading of Equity Shares within three Working Days of the Bid/Offer Closing Date. The IPO completed with listing on BSE and NSE on 14 August 2026.
  2. Outstanding order book of ₹685.83 cr (June 2025) completed within 3-4 years On track - In the DRHP, the outstanding order book of ₹685.83 crore as of 30 June 2025 was expected to be completed within the next 3 to 4 years. As of 30 September 2026, the total order book stood at \~₹1,393 crores; no disclosed read on completion of the June 2025 order book specifically.
  3. Working capital requirement rising to ₹246.85 cr by FY27 On track - In the DRHP, working capital requirement was projected to rise by ₹36.97 crore (26.40%) from ₹140.01 crore in FY25 to ₹176.98 crore in FY26, and by ₹69.88 crore (39.48%) to ₹246.85 crore in FY27, on expected revenue growth. FY26 working capital requirement came in at ₹133.82 crore, below the ₹176.98 crore projection; FY27 actuals are not yet due.
  4. CETP and STP capacity targets - 50 MLD CETP, 200 MLD STP in coming years Pending - In the DRHP, the company targeted entering the CETP sector with a target of reaching 50 MLD for CETPs and 200 MLD for STPs "in the coming years". Executed and upgraded STPs range from 3 MLD to 56 MLD, including Ghaziabad 56 MLD, Pilkhuwa 3 MLD and Shahjahanpur 40 MLD; no disclosed read on current total STP capacity against the 200 MLD target or on CETP entry progress.
  5. IPO fresh-issue proceeds used for disclosed objects including working capital On track - At the Q2 FY27 call, management committed to using the IPO fresh-issue proceeds for the purposes disclosed in the offer documents, including working capital for executing the large quantum of projects procured; the DRHP specified ₹1,380.00 million towards Working Capital Requirements, with General Corporate Purpose capped at 25% of gross proceeds. A CARE Ratings Monitoring Agency Report on utilisation for the quarter ended 30 September 2026 was reviewed by the Audit Committee and Board on 14 November 2026, and the company committed to a utilisation update from the next reporting period; no utilisation figures are disclosed in our record.
  6. Legacy order book of \~₹300 cr completed within FY27 On track - At the Q2 FY27 call, management stated the balance \~₹300 crores of the order book, older projects towards completion, is expected to be completed within FY27. As of 30 September 2026, the total order book stood at \~₹1,393 crores, of which \~₹1,100 crores was newly awarded and the balance \~₹300 crores was towards completion; no completion disclosure yet for the legacy portion.
  7. Delhi Jal Board project - 60-70% completion by end of FY28 On track - At the Q2 FY27 call, management guided that 60%-70% of the Delhi Jal Board project work will be completed within the balance of FY27 plus FY28. The project was awarded in Q2 FY27 at approximately ₹196.47 crores; our record holds no progress disclosure beyond the award.