Techno Electric & Engineering Company Ltd Q3 FY2026 Concall Summary

Source transcript PDF: https://assets.stockscans.in/docs/xim9bf6wyahu2ikj53x9z7wf.pdf

Key Takeaways


Data Center Build-Out

Gupta: "By '28, '29, data center will -- digital infra will become the face of the company. It will be other way around."

EPC Order Book & Margin Discipline

Gupta: "We will like to limit our order intake and not -- and learn to say no to many orders unless they are juicy and bottom line accretive."

Smart Meter Execution & Strategy

Gupta: "Probably Techno is the best where we have deployed more than 50% of the concessions backed by us, others performance is only ranging from 15% to 25%."

Margin & Profitability Dynamics


Strategic Announcements & New Ventures


Guidance & Commitments

CommitmentSpecificsTimeline
FY26 revenue₹3,300-3,400 croresFY26 full year
FY26 EPS~₹15 (standalone)FY26 full year
FY27 EPS₹75, no execution challenges anticipatedFY27 full year
Q4 FY26 standalone revenue~₹3,400 croresQ4 FY26
Q4 FY26 standalone EPS₹50Q4 FY26
Chennai Phase 1 utilizationFully utilizedH1 FY27
Data center capex FY27₹500-600 croresFY27 (Apr-Mar)
Data center cumulative capexNo less than ₹5,000 croresBy 2030
Edge data center revenue₹100 crores plus top line at 50-60% EBITDA marginsFY27
EPC order intake cap₹3,000-3,500 crores annuallyUntil top line reaches ₹5,000 crores+
Smart meter go-live: IndoreCompletionMarch 2026
Smart meter go-live: RanchiCompletionJune 2026
Smart meter go-live: Kashmir, TripuraCompletionDecember 2026
Noida data center first capacity0.5 MW operationalMarch 2026
Noida data center additional capacity5 MW operationalMarch 2027
Kolkata data center Phase 1CommissioningLate 2027
Chennai full campus36 MW plus possible expansion commissionedWithin 2.5-3 years
Afghanistan paymentReceipt expectedQ1 next fiscal
Bengal Energy arbitrationAward expected "any day"Imminent
Data center top line target~₹300-400 croresWithin 2-3 years
Data center asset exitNo exit plannedNext 2-3 years

Key Metrics

MetricQ3 FY26
Revenue₹857 cr, +26% YoY
Profit after tax₹151 cr, +45% YoY
EPS₹13, up 45% from ₹9 last year
Core EBITDA margin14.14%, marginal decline due to EBS Connect platform deployment costs
9-month revenue₹2,209 cr, +39% YoY
9-month PAT₹373 cr, +49% YoY
9-month EPS₹34.3
Cash and liquid investments~₹1,925 cr
Order book₹10,200 cr as of Dec 31, 2025
New confirmed orders (Apr 2025–Feb 2026)~₹2,500 cr, with L1 in tenders worth another ₹750 cr
Smart meter order book0.22 cr meters, valued at ₹2,612 cr under RDSS; ~50% executed as of December
Smart meters deployed (cumulative)~0.14 cr expected by March 2026
Data center capex planned for FY27₹500–600 cr across Noida, Kolkata, and 3–4 edge data centers
FY26 revenue guidance₹3,300–3,400 cr
FY26 EPS guidance~₹15 (standalone)
FY27 EPS guidance₹75, maintained