Teerth Gopicon Ltd Q4 FY2025 Concall Summary

Source transcript PDF: https://assets.stockscans.in/docs/ay11lio4ipizxw0hf2slfl4d.pdf

Key Takeaways


The MP Jal Nigam Payment Freeze

Kumbhani: "The main reason we don't show it is that it unnecessarily creates liability in GST. Once the department pays with GST, then only we have a liability."

The Bank Guarantee Investigation

Kumbhani: "Your concern is justified, and this is everybody's concern but this not a matter of concern as on Date."

Order Book: Infra Stalled, Renewables Waiting


FY26 Revenue Ambition vs. Visibility

Kumbhani: "No one can take the guarantee of the Government. Yes, our best efforts will be there and our whole focus is always on planning based on what was announced in the budget."

Margins, Costs & the GST Constraint


Transparency & Disclosure Commitments

Kumbhani: "I assure you that we will rise up to the occasion. To gain faith and the favor of the investors whatever planning we have to do, we will do it internally."

Guidance & Commitments

CommitmentSpecificsTimeline
Revenue targetApproximately ₹600 crore EPC + ₹200 crore renewables = ₹800 crore cumulative for FY26FY26
CBI findingsCourt direction to CBI to complete investigationBy June 30
Fresh BG submissionProcess complete; will proceed upon receiving CBI findingsAfter CBI findings
Infra order book execution₹930 crore order book to be executedOne and a half years
Renewable order execution₹800 crore (220 MW) on PPA modeTwo years
Indore Smart City execution startAfter land possession and prerequisitesMinimum one year from LOA

Key Metrics

MetricQ4 FY25
Total revenue₹118.55 crore, +12.8% YoY; +202.81% from FY23
H2 FY25 revenue decline26% decline vs H1 FY25, due to payment delays from MP JNM
EBITDA₹24.9 crore, margin 21% vs 17% in FY24
PAT₹12.84 crore, +11.07% YoY
PAT margin (H2 FY25)6.61%, impacted by higher finance cost, fixed overheads and provisioning
Net worth₹75.97 crore, vs ₹19.28 crore in FY24
Order book (infra)₹930 crore, ~90% Jal Jeevan Mission; execution timeline 1.5 years
Order book (renewable)220 MW, approximately ₹800 crore; execution timeline 2 years
Combined order book (infra + renewable)~₹2,000 crore
Receivables₹27 crore as on FY25, approved but not yet released by department
Balance BG exposure₹110 crore, out of original ₹180 crore; ~80% recovered
Indore Smart City project₹434 crore allotted, revenue potential ₹1,800 crore over 3–4 years
MOU with MP Government (solar module/cell)₹1,500 crore
FY26 revenue target₹800 crore (₹600 crore EPC + ₹200 crore renewable), per management commitment to analyst's figure