Thermax Ltd Q3 FY2025 Concall Summary

Source transcript PDF: https://assets.stockscans.in/docs/varuy2zasaf4lg10c3axnm4e.pdf

Key Takeaways


The Q3 Miss and Q4 Rebound

Bhandari: "It was a difficult quarter, and the results were below our expectations. There were times in the quarter where we knew it was going to be tough. But the end result was -- had some things that were surprising to me as well from a miss point of view. That said, I expect a strong quarter 4, potentially even a very strong quarter 4 and request that you look at our performance and you evaluate it as the second half of the year overall."

The Project Business Base Cost Challenge

Bhandari: "To say no to something like that when you are working with a INR 100 crores cost challenge on the project side, the amount that it took for the company to say no to something like that. So if you're asking for, are we taking some of those as tough calls? We are taking those as very, very tough calls and taking it on the chin."

Bio-CNG: A Strategic Bet Under Stress

Bhandari: "We haven't reached this. Nobody in the industry has reached, where the economics are on the industry, in my firm belief, it is not sustainable. Yes, something has got to change. I believe strongly that something will change because the industry makes a lot of sense for the country."

Industrial Products: The Steady Compounder


Chemicals and FEPL: Two Turnaround Stories


Supercritical, Heat Pumps, and Coal Gasification: Optionality Bets


Guidance & Commitments

CommitmentSpecificsTimeline
Q4 FY25 revenue and ordersNorth of ₹3,000 crores eachQ4 FY25
Q4 FY25 profitabilityNorth of 10%Q4 FY25
Chemicals PBIT recovery16–18% on an aggregate basisQ4 FY25
Project side profitabilityCross 5% (from 1–2% this year so far)Next year
FEPL lossesCome down substantially, still loss-makingNext year
FEPL breakevenBreakevenYear after next
Bio-CNG new ordersResume taking ordersSecond half of next year
FEPL investment to 1 GW~₹500 crores over a two-year periodTwo years (stretched from 12–18 months)
Industrial Products marginsCross 10%When reasonable revenue threshold is crossed

Key Metrics

MetricQ3 FY25
Revenue miss~₹500 cr of revenue and ₹60+ cr of profitability not recognised in Q3, cleared in January
Q4 revenue guidanceNorth of ₹3,000 cr expected, with orders also north of ₹3,000 cr
Q4 profitability guidanceNorth of 10% expected at the company level
Industrial Products order book growth~40% YoY, backlog grew nearly 30%
Industrial Infra – FGD impact₹16 cr loss in Q3, primarily from Maithon project
Industrial Infra – large projects profitabilityNegative ₹30+ cr in Q3, driven by government projects and FGD
TBWES profitability8% in Q3, despite ₹14 cr loss on HRRL project (on top of negative ₹12 cr in Q2)
Bio-CNG loss₹12 cr negative in Q3; cumulative investment exceeds ₹100 cr beyond original plan
Bio-CNG conversion rate achieved0.5x to 0.75x of originally expected yield, on a consistent basis
Chemicals PBIT expectation16% to 18% expected on an aggregate basis in Q4
Project business profitability YTD1% to 2% so far this year; management expects to cross 5% in FY26
Export revenue expectation FY26Above ₹3,000 cr, in a range of ₹2,000–3,500 cr
Large projects base cost₹80–100 cr of base cost sitting in the project business; need ~₹1,000 cr of project orders to cover it
TOESL Q4 order pipeline₹1,000 cr pipeline, with ₹50–100 cr of orders expected to close in Q4
FEPL investment plan~₹500 cr to reach 1 GW; timeline stretched to a two-year period