Tonbo Imaging India Ltd Guidance Report - SOIC x StockScans Report

as of Nov 2026

  1. Offer for Sale of up to 18,085,246 equity shares - no proceeds to company Delivered - In the DRHP, the Offer for Sale of up to 18,085,246 Equity Shares of face value ₹2 each was stated, with no Offer Proceeds going to the company, all going to Selling Shareholders. The IPO raised ₹852 crore by way of offer for sale and shares listed on NSE and BSE on 23 October 2026, subscribed over 135 times overall with strong QIB demand.
  2. Competitive share in future Indian thermal weapon sight programs "a fairly large percentage" (\~50%) Pending - At the Q2 FY27 call, management guided that competitive share in future Indian thermal weapon sight programs (India growing from \~30,000 to maybe 300,000 sights) may fall from \~65% historical but remain "a fairly large percentage", e.g. maybe 50%. Today \~30,000 tactical thermal sights are deployed in India, \~20,000 Tonbo's - more than 65% share; no new program award yet.
  3. European seeker option - up to €13 million on acceptance of FOPM units Pending - At the Q2 FY27 call, management stated that on acceptance of the FOPM units from the European state-owned company order, the customer has an option to order up to €13 million of systems, with "more than a fair chance" of proceeding if delivered to spec. The \~€65,000 FOPM export order was secured in October 2026; the option sits in the ₹408.3 crore negotiation pipeline, not the ₹250 crore order book - no exercise yet.
  4. Platform systems to account for a larger share of business over time On track - At the Q2 FY27 call, management stated platform systems are expected to take a larger share of business over time, with tactical systems currently \~70-80% of business. H1 FY27 platform revenue was ₹94.1 crore vs ₹33.3 crore in H1 FY26, and platforms are 82% of the order book; platform share of H1 revenue was \~43% in both periods.
  5. Contracts under negotiation (\~₹408 crore) to convert into revenues in FY27, assuming December receipt Pending - At the Q2 FY27 call, management stated contracts under negotiation, assuming they come through by December, should convert into revenues this financial year, with ₹100-200 crore of new orders expected to be executed this year. Contracts under negotiation stood at ₹408.3 crore as of 30 September 2026, with conversion expected in the next 2-3 months - no FY27 conversion actual yet.
  6. FY27 full-year R&D spend of \~₹30 crore excluding HPM, \~₹25 crore capitalized Pending - At the Q2 FY27 call, the CFO expected FY27 full-year R&D spend (excluding HPM) of about ₹30 crore order of magnitude, \~₹25 crore capitalized, with H1 spend of \~₹16 crore and \~₹3 crore expensed to P&L expected to continue in H2. H1 FY27 spend of \~₹16 crore with \~₹3 crore expensed is on that run-rate; no full-year actual yet.
  7. Directed energy system capital cost of \~₹160 crore funded by EXIM loan, iDEX grant and own balance sheet On track - At the Q2 FY27 call, management stated the first directed energy system costs \~₹160 crore, funded by a sanctioned ₹120 crore EXIM loan, a ₹25 crore iDEX Aditi grant and ₹15 crore from own balance sheet - "we already have this". The HPM project's total cost is \~₹160 crore (hard cost \~₹120 crore materials), with \~₹20 crore of capitalized employee expense over the next 2.5 years; the first unit may be used for demonstrations.
  8. First directed energy system production deliveries in 2029-2030 On track - At the Q2 FY27 call, management stated first directed energy system production deliveries will start in 2029-2030 ("will not happen before '29-'30"), with product engineering and testing risk to be mitigated from TRL 4 between now and FY29. The WaveStrike DEW product is at TRL 4, with letters of intent signed for 11 units - 5 for the Indian Navy and 6 for a European customer; no deliveries yet.
  9. FY27 full-year EBITDA margin improvement over H1's 14.2% Pending - At the Q2 FY27 call, management stated EBITDA margins, low in H1 at 14.2% due to fixed employee costs, are "expected to improve for the full year" on higher revenues and higher export-mix gross margins - no quantified range given. Q2 FY27 EBITDA margin was 24.1%; no FY27 full-year actual yet.
  10. H2 FY27 revenue materially better than H1 - no quantified guidance Pending - At the Q2 FY27 call, the CFO gave no revenue guidance but stated H2 FY27 revenues are "likely to be materially better than H1", based on the ₹250 crore order book, contracts under negotiation, and a pipeline expected to convert in the next 2-3 months. H1 FY27 revenue was ₹219.3 crore, with ₹408.3 crore under negotiation as of 30 September 2026; no H2 actual yet.