Torrent Power Ltd Q1 FY2027 Concall Summary

Source transcript PDF: https://assets.stockscans.in/docs/as-0604d6ecf1c75acfbc2bf0b2.pdf

Key Takeaways


Profit Bridge: What Moved the Quarter


Nabha Power Acquisition

Mashruwala: "So on a steady state basis, around ₹1,000 crores of EBITDA should be a good enough number."

Renewables: Pipeline, Delays & Discipline

Shah: "What we have said is after factoring in all those issues, our expectation is that we should achieve this target, what we have given. Now, if something unfortunate happens, we'll update you on a quarterly basis."

Thermal & Gas Strategy

Mashruwala: "I cannot hedge my gas-based prices, gas prices on a long-term basis. So if I do a PPA for a long tenure with a fixed price, there is an inherent risk which I'm taking by locking in my tariff."

Distribution & Demand Trends


LNG Procurement & Merchant Operations

Mashruwala: "It's very challenging, $20 to sell power at a $20 MMBtu is quite challenging, I would say."

Guidance & Commitments

CommitmentSpecificsTimeline
RE commissioning~1.2 GW in FY27 (~400 MW in Q2, ~800 MW in H2)FY27
RE commissioning1.4–1.6 GWFY28
RE commissioningBalance capacityFY29
FY27 RE capexApproximately ₹10,000 croresFY27
Nabha Power steady-state EBITDAAround ₹1,000 crores per annum on cash-flow/adjusted basisSteady-state
Anuppur thermal project commissioningProject to commissionNext 6–7 years
Pumped Storage Hydro Project commissioningProject to commissionNext 3–4 years
Solapur transmission project commissioningProject to commissionFY27
AMGEN replacement plantSet up ~800 MW unit to replace AMGEN (362 MW), subject to central government coal allocationOnce coal allocation approved
Gas-plant upgradesImprove margin realization going forwardProgressively rolled out

Key Metrics

MetricQ1 FY27
Reported PBT₹925 cr, down from ₹985 cr in Q1 FY26, a reduction of ₹60 cr
Adjusted PBT₹925 cr, down from ₹1,044 cr in comparable Q1 FY26, a reduction of ₹119 cr on an adjusted basis
Tax rate28%, up from 25% in Q1 FY26, mainly due to completion of tax holiday under section 80-IA for some units
Thermal generation business performanceLower by ₹123 cr YoY, adjusted for non-recurring items
Gains from merchant sales and LNG tradingLower by ₹87 cr YoY
O&M expenses increase (gas plant upgrades)Higher by ₹51 cr YoY
Nabha Power contribution₹15 cr profit, acquired 25th June 2026, five days of operations consolidated
Distribution and transmission segment profit contribution71% additional profit YoY
Regulatory carrying cost approved₹41 cr favorable order received
Distribution franchisee volume growth4% YoY
Renewable operations contribution₹19 cr positive contribution YoY; prior year Q1 included ₹47 cr LPS income not repeated
Aggregate installed generation capacity6.6 GW as on 30th June 2026, comprising 2.7 GW gas, 1.8 GW coal, 2.1 GW renewable
Renewable energy capacity under implementation4.6 GW as on 30th June 2026
RE commissioning guidance FY27~1.2 GW expected, with ~400 MW in Q2 and balance ~800 MW in H2
RE commissioning guidance FY281.4–1.6 GW expected
Capex incurred in Q1 FY27 (RE projects)₹1,550 cr, vs ₹1,200 cr in Q4 FY26 and ₹335 cr in Q1 FY26
Total capex expected for all RE projects in FY27~₹10,000 cr
Total Q1 FY27 capex (all segments)₹2,300 cr, comprising RE ₹1,550 cr, thermal ₹125 cr, transmission ₹120 cr, distribution ₹500 cr
Cumulative RE capex incurred up to 30th June 2026₹8,800 cr out of total ₹29,600 cr
Anuppur thermal project cumulative capex₹450 cr incurred as on 30th June 2026
Pumped Storage Hydro Project cumulative expense₹1,130 cr incurred as on 30th June 2026
Solapur transmission project cumulative capex₹330 cr incurred as on 30th June 2026
Nabha Power gross debt added~₹6,500 cr, comprising ~₹3,000 cr in Nabha Power books and ~₹3,800 cr in Torrent Power books
Nabha Power steady-state EBITDA expectation~₹1,000 cr per annum on a cash flow/adjusted basis, per management
Merchant sales volume445 MUs in Q1 FY27
Nabha Power PLF (five days of operations)~85% during the five days consolidated
Spot LNG price~$20/MMBtu
Management long-term gas price expectation$6–$8/MMBtu