Key Takeaways
- H1 execution strong, Q2 paused by monsoon: Revenue grew ~48-50% YoY in H1, but Q2 execution was mildly lower than Q1 after two and a half months of heavy monsoon and flooding delayed most projects. Catch-up is expected in Q3 and Q4.
- Margins held at the top of the peer set: H1 EBITDA margin of 11.98% sits within the guided 11.5%-12% band and management claims a 4%-5% lead over competitors, even as steel price declines did not flow through to gross margins because other input costs rose.
- Working capital swelled on deliberate inventory build: The company accumulated inventory to lock in lower steel prices, driving the increase in working capital days; contract assets also rose on retention money that management expects to collect as projects close in H2.
- Order inflow guidance raised to INR 9,000-10,000 crore: Backed by a H2 bid pipeline of INR 55,000 crore and three new country entries (Ethiopia, Djibouti, Botswana), the company targets ~40%-45% of fresh orders from international markets.
- What to watch next quarter: Whether the promised Q3/Q4 execution catch-up materializes after the monsoon-led Q2 softness, the pace of contract asset and retention money conversion into cash, and any movement on the INR 67 crore contingent liability claim that management declined to detail.
Revenue Growth & Execution
- H1 growth rate amplified by a weak base: The ~48-50% YoY H1 revenue jump reflects a slow start last year when engineering design approvals delayed execution; the company is now in full execution phase across most projects.
- Monsoon hit Q2, not the full-year plan: Extensive rainfall and flooding for two and a half months affected most project sites, making Q2 execution mildly lower than Q1. Management expects the shortfall to reverse automatically in Q3 and Q4 as sites become workable.
- Full-year 25% growth guidance reaffirmed: Management is comfortable meeting the 25% revenue growth target for FY26 and flagged that any upside would materialize by March.
- Next-year growth guided at 23%-25%: Early guidance for FY27 calls for 23%-25% revenue growth over whatever base FY26 closes at, signaling confidence in the order book and execution pipeline.
- Bangladesh project nearing completion: Another INR 900 odd crore will be finished by end of this year, with the residual completed by June-July.
Narang: "Everybody is expecting that we do better than our guidance, which we want to also do. And it's a good problem to have because our speed of execution is genuinely good versus our business plan."
Margin Performance & Cost Structure
- H1 EBITDA margin at 11.98%, top of the peer set: Management describes this as the best in the industry, 4%-5% ahead of competitors, and within the guided 11.5%-12% band for the full year.
- Steel price drop did not lift gross margins: Steel prices fell by INR 3,000-4,000 per metric ton, but steel is only one item (30% of execution involves towers). Copper and zinc prices have risen, and certain construction costs increased on demand-supply dynamics, offsetting the steel benefit.
- Project cost ratio elevated on finishing-stage mix: Project cost (raw material plus subcontractor) ran at ~68% in H1 because some projects are at the finishing stage with higher subcontractor cost and lower material cost. Management expects normalization to 65%-66%, hopefully by March, as those projects close and get billed.
- Full-year margin guidance maintained: The company intends to hold EBITDA margin at 11.5% to 12% for the full financial year, with the mix of product, project, and geography determining where within that band it lands.
Narang: "I think this is the best in the industry. We are ahead of our competitors by 3%-5% and therefore the margin profile is good."
Order Book & Bid Pipeline
- Fresh order inflow guided at INR 9,000-10,000 crore for FY26: The company expects to book INR 3,000-5,000 crore of that in H2 alone, with ~40%-45% coming from international markets.
- H2 bid pipeline stands at INR 55,000 crore: The total bid pipeline is ~INR 95,000 crore, giving visibility into the order intake target. Bidding activity is active in Oman, Qatar, Jordan, and Abu Dhabi.
- Three new country entries in Q2: Ethiopia, Djibouti, and Botswana added to the geographic footprint, expanding the addressable international market.
- Domestic tilt expected next year: Management targets a 55% domestic, 45% international revenue mix going forward, a shift from the current balance.
- Order book execution timeline: Domestic orders run up to 24 months, international orders 24 to 30 months, providing multi-quarter revenue visibility.
Working Capital, Cash Flow & Balance Sheet
- Inventory build drove working capital expansion: The company deliberately accumulated inventory to take advantage of low steel prices, which is the major reason for the increase in working capital days.
- Contract assets rose on retention money: The INR 156 crore increase in contract assets mainly comprises TOC retention and final retention (around INR 250 crore increase), partially offset by a INR 100 crore reduction in unbilled revenue assets. Management expects retention money, typically 5%-10% of project value accumulated across ~20 projects, to convert in Q3 and Q4 as projects close.
- Trade payables reflect LC-backed procurement: Procurement is taken through letter of credit instruments matched to the receivable cycle, typically six months. Vendors are secured because they discount against the LC. The increase in trade payables over the last six months is only ~INR 100 crore.
- Cash inflow position expected to improve by March: NWC outstanding has reduced and recovered substantially in November. Management has a clear agenda to expedite collections and expects a comfortable cash inflow position by March, with December and March as focus milestones.
- Related-party loan collection timeline: The loan matures in September 2026; collection is expected by that date, with a possible split into two parts (partly 2026, partly 2027). The next tranche will happen by Q4.
- Burberry Infra loan recovery: Part of the INR 80 crore loan will be received in Q4 this financial year, with the balance thereafter in 2026-2027.
Capacity Expansion & Strategic Moves
- Brownfield tower expansion nearing completion: Phase 1 of the brownfield expansion has started execution; ~10%-15% residual work remains after a month's delay from heavy monsoons and flooding, to be completed in Q3.
- Greenfield project on track for year-end commissioning: The new facility remains on schedule, while the conductor plant will enter expansion mode by Q1 of next year. Phase two brownfield expansions are also underway.
- Capex progress: 88% of orders for Phase 1 have been placed, around 60% paid off, with work in progress.
- Solar EPC strategy focused outside India: The company picked up one solar EPC job but principally does not want to work in India for solar EPC, preferring international opportunities in Africa and the Caribbean.
- Small bets on civil and railways: The company acquired CEDEC Engineering Private Limited (an SPV) for INR 50 lakhs to build pre-qualifications in bridges and hydro, and intends to build railway pre-qualifications selectively. Both are future-readiness moves; the focus remains 90% T&D.
Narang: "Principally, we don't want to work in India, because we are still looking at opportunities in international, particularly Africa and Caribbean."
Guidance & Commitments
| Commitment | Specifics | Timeline |
|---|---|---|
| Revenue growth FY26 | ~25% growth over FY25 | Full year FY26 |
| Revenue growth FY27 | 23%-25% growth over FY26 closing base | Full year FY27 |
| EBITDA margin | Maintain 11.5% to 12% | Full year FY26 |
| Fresh order intake | INR 9,000 crore to INR 10,000 crore | Full year FY26 |
| H2 order intake | INR 3,000 crore to INR 5,000 crore | H2 FY26 |
| Bangladesh project | Complete INR 900 odd crore; residual by June-July | End of CY2024 / mid-2025 |
| Project cost ratio normalization | Normalize to 65%-66% | Hopefully by March 2025 |
| Cash flow position | Comfortable cash inflow position | By March 2025 |
| Related-party loan collection | Full collection by September 2026; next tranche by Q4 FY26 | September 2026 / Q4 FY26 |
| Burberry Infra loan recovery | Part recovery in Q4 FY26; balance in 2026-2027 | Q4 FY26 and beyond |
| Brownfield plant completion | Residual 10%-15% work completed | Q3 FY26 |
| Greenfield facility commissioning | Commissioned by end of year | End of CY2024 |
| Conductor plant expansion | Enter expansion mode | Q1 FY27 |
Key Metrics
| Metric | Q2 FY26 |
|---|---|
| Revenue | ₹1,561 cr, 53% international and 47% domestic |
| H1 FY26 revenue | ₹3,221 cr, +61% YoY |
| EBITDA margin | 11.93%, +34% YoY growth in EBITDA |
| H1 EBITDA margin | 11.98% |
| Profit After Tax | ₹90.98 cr, +65% YoY |
| H1 PAT | ₹197 cr, +84% YoY |
| H1 PBT margin | 8.4% |
| H1 PAT margin | 6.1%, +78 bps YoY |
| Order inflow (Q2) | ₹1,992 cr, including entry into three new countries |
| H1 order inflow | ₹3,740 cr |
| L1 position | ₹2,682 cr, led mainly by T&D |
| Unexecuted order book | ₹17,799 cr, including L1 of ₹2,682 cr |
| Total order book in hand | ₹15,116 cr, 93% T&D, 61% domestic and 39% international |
| Net debt | ₹703 cr, debt-equity ratio of 0.38 times |
| Working capital days | 84 days, 77 days ex-IPO funds |
| Full-year revenue growth guidance | ~25% over FY25 |
| Full-year order inflow guidance | ₹9,000 cr to ₹10,000 cr |
| Full-year EBITDA margin guidance | 11.5% to 12% |
| Bangladesh exposure | ~₹1,500 cr total, with ~₹400 cr receivables as of Q2; ₹300+ cr collected in October |
| Capex (Phase 1) | ₹325 cr sanctioned, 88% orders placed, ~60% utilized |
| Bid pipeline (H2) | ~₹55,000 cr to be bid, total ~₹95,000 cr for FY26 |
| Strike rate | 8% to 10% |
| International fresh order intake target | ~40% to 45% of total, ~₹4,000 cr |
| Power T&D revenue share | ~90% |
| Railways SBU revenue share | 4% to 5% |
| Project cost (raw material + subcontractor) | ~68% of revenue in H1, expected to normalize to 65%-66% |
| Contract asset increase vs March 2025 | ₹156 cr, driven by ₹250 cr increase in TOC and final retention |
| Trade receivables split | ~60% international, 100% secured by LC or multilateral funding |
| Trade payables | ~₹2,500 cr, increase of ~₹100 cr over six months |
| Related-party loan recovery | ₹30 cr received last March, balance expected by FY27; interest at 12% |