Key Takeaways
- Revenue upgraded, execution gated: 9M revenue grew 49% YoY, and FY26 guidance was raised to 26–27% growth, but management flagged that ROW and forest clearance issues are the binding constraint on hitting the stretch number.
- Order book closing above ₹16,000 crores: FY26 order intake is tracking to ₹9,500–10,000 crores, and the closing order book is expected to exceed ₹16,000 crores, providing strong revenue visibility into FY27.
- Margins steady, not expanding yet: EBITDA margin held at 12.7% in Q3 and 12.2% for 9M; management is comfortable maintaining the 11.5–12% profile but cannot quantify the margin lift from CAPEX completion.
- Balance sheet transformed: Net debt halved to ₹463 crores (D/E 0.39x), interest cost fell to 3.3%, and CFO-to-EBITDA conversion ran substantially ahead of the 25–30% range an analyst suggested.
- What to watch next quarter: Whether ROW clearances unlock the stretch revenue target, the pace of order intake against the ₹1 lakh crore 12-month pipeline, and the ramp-up of the greenfield facility now being inaugurated.
Revenue Growth & Guidance
- 9M momentum: Revenue reached ₹5,017 crores, up 49% YoY, driven by scaling of operations and a balanced domestic/international mix. Q3 alone grew 32% YoY to ₹1,796 crores.
- FY26 guidance raised: Management upgraded the full-year growth outlook from 23–25% to 26–27%, with a clear caveat: the stretch depends on ROW and forest clearances materializing.
- International execution stable: Management pushed back on the idea of an international slowdown, pointing to 30% growth over last year on a 9-month basis. The Q3-on-Q3 dip (₹800 cr vs ₹723 cr) was attributed to monsoon delays in July–August, not a demand issue.
- Bangladesh tailwind: The Bangladesh project is executing ahead of plan, with completion targeted by June/July next year and approximately ₹600–700 crores of revenue left for FY27. Receivables of ₹488 crores are being collected on time, described as a project of national importance.
Narang: "I would be looking at stretching and improving the Q4 numbers. But if you see on a 9-month basis, leading to 12 months, we will have a very healthy growth for the year."
Order Book & Pipeline
- Closing order book: Expected to reach ₹16,000+ crores by year-end, providing a strong launchpad for FY27. The order book is described as profitable and in line with current margin performance.
- FY26 intake: Order intake is tracking to ₹9,500–10,000 crores, beating last year. Management expects to add another ₹1,500–2,000 crores before year-end.
- FY27 pipeline: A 12-month bid pipeline of ₹1 lakh crore, split roughly 60% domestic and 40% international, supports the 10–14% order intake growth target for next year.
- Order book composition: Management provided general regional guidelines: India ~₹8,000+ crores, Africa ~₹4,000 crores, SAARC ~₹1,200 crores, MENA ~₹750–800 crores, but declined to give a detailed breakup when asked.
- Quality bidding discipline: The company prioritizes right margins, right clients, and right geographies over growth at any cost, a stance management reiterated as central to the order book's profitability.
Narang: "Our focus remains on securing high-quality, margin-assertive projects that align well with our execution strengths. And we continue to follow the quality bidding approach, which is selective yet giving us enough opportunities to improve the bidding pipeline, prioritizing on the right margins, the right clients and geographies, rather than pursuing growth at any cost, which is a key area of focus for us."
Margins & Profitability
- Stable margin profile: EBITDA margin printed at 12.7% in Q3 and 12.2% for 9M, supported by cost discipline, tighter cash flow control, and a healthy project mix. Operating PAT grew 36% in Q3 and 62% in 9M.
- Comfortable outlook: Management is comfortable maintaining the 11.5–12% EBITDA profile and sees no near-term pressure on that range.
- CAPEX margin lift unquantified: Brownfield expansion (70% production commenced, full completion by February) and the greenfield facility (inauguration this quarter) will help save on cost outlay through faster execution, but management declined to put a number on the margin improvement.
- Subcontracting costs elevated: Higher subcontracting expenses reflect the ramp-up in execution and the stage of projects; these are expected to sustain through Q4 and then normalize to last year's levels as high-priority projects complete.
- Steel price benign: Steel has been softening over the last six months and is in line with projections. The company builds contingency into bids based on global trends. Copper price moves are irrelevant as the company does not use copper in its business.
Narang: "There will not be areas where you can quantify it directly in terms of margin change, but project execution on time will definitely help us to improve the cost outlay and the impact of margins is very difficult to say, ma'am."
Balance Sheet & Cash Flow
- Net debt halved: Net debt fell to ₹463 crores from ₹703 crores in H1, with a debt-equity ratio of 0.39x. Interest cost improved from 4.1% to 3.3%, aided by a credit rating upgrade, low leverage, and improving cash flows.
- Cash generation strong: Cash equivalents rose by ₹293 crores over H1 to ₹380 crores. Cash flow from operations pre-tax increased from ₹300 crores to ₹440 crores in the 9-month period, exceeding profit before tax of ₹430 crores.
- CFO conversion debate: When an analyst suggested CFO-to-EBITDA conversion was only 25–30%, management countered that conversion is "substantially higher than that," pointing to absolute cash flow figures, but did not directly address the peer-comparison metric.
- Working capital steady: Net working capital days improved to 83 from 84 in H1 and 91 in FY25. Management noted retention money will increase as the order book builds but expects internal accruals to support the process. A request for normalized days excluding IPO funds went unanswered.
- CAPEX funding: All CAPEX (brownfield and greenfield) will be completed by end of Q4 FY26, funded by internal accruals and IPO money, with debt only marginally increasing and well covered.
Capacity Expansion & Strategic Moves
- Brownfield ramp-up: 70% of Phase 1 brownfield production has commenced; full 100% completion expected by February end. The expansion effectively doubles capacity across towers and conductors.
- Greenfield facility: The new tower factory is progressing well and will be inaugurated shortly this quarter, with production expected by March–April.
- New geography: The company entered the GCC region for EPC works, with a presence now in Abu Dhabi, Oman, and Jordan. Management is hopeful of maintaining its T&D margin profile in these new countries and stated it avoids geographies where margins could erode over time.
- Project milestones: Successfully commissioned three lines in the 765 kV double-circuit Khetri-Narela transmission line, completed the 765 kV double-circuit Ahmedabad-Lakadia line, and finished overhead electrification projects for RVNL. An 800 kV HVDC Nagpur project for Power Grid is already under execution.
- ERP transformation: Initiated an upgrade from SAP HANA to SAP RISE as a strategic initiative for cost discipline, compliance, and real-time data-driven decision-making.
- BESS evaluation: The company is evaluating the Battery Energy Storage Systems opportunity given India's projections and budget but is not yet ready to start bidding.
Narang: "We do not go to geographies and countries where we feel that the overall potential and the margin profile will get eroded over the years."
India Transmission Outlook
- Structural demand: India's transmission capacity is expected to grow from 5 lakh circuit kilometers to 648,000 circuit kilometers over the next 3–4 years. Management sees the India infrastructure story continuing for the next 3–5 years "without a problem."
- Power Grid opportunity: The company expects more contracts and bids from Power Grid as its CAPEX increases, and already has an 800 kV HVDC project under execution for them.
- GIS substation demand: Demand for GIS substations in the Northeast is emerging but will take approximately six months to fructify into a visible bid pipeline; visibility is not yet at the level management desires.
- Civil business focus: The company is only pursuing heavy engineering-led jobs (bridges, cooling towers, elevated roads) and has no intention of entering residential buildings or roads.
Narang: "The India story and infrastructure is really good and what we see is it is going to continue for the next three to five years without a problem."
Guidance & Commitments
| Commitment | Specifics | Timeline |
|---|---|---|
| FY26 revenue growth | 26–27% over last year, with potential to stretch higher if ROW clearances materialize | FY26 full year |
| FY26 order intake | ₹9,500–10,000 crores, beating last year | FY26 full year |
| Closing order book | ₹16,000+ crores | FY26 year-end |
| FY27 order intake growth | 10–14% growth off a ₹1 lakh crore pipeline | FY27 |
| Bangladesh project completion | Finish execution; ~₹600–700 crores revenue left | June/July next year |
| EBITDA margin | Maintain 11.5–12% profile | Ongoing |
| Brownfield CAPEX completion | 100% production commenced | February end |
| Greenfield facility | Inauguration and production start | Q4 FY26 (March–April) |
| All CAPEX completion | Fully completed | End of Q4 FY26 |
| Related party loan (Burberry Infra) | Part payment in Q4, balance next financial year | As per contract |
Key Metrics
| Metric | Q3 FY26 |
|---|---|
| Revenue from operations | ₹1,796 cr, +32% YoY |
| 9M revenue from operations | ₹5,017 cr, +49% YoY |
| EBITDA | ₹228 cr, +27% YoY; margin 12.7% |
| 9M EBITDA | ₹614 cr, +40% YoY; margin 12.2% |
| Operating PBT | ₹169 cr, +34% YoY |
| 9M operating PBT | ₹441 cr, +52% YoY |
| Operating PAT | ₹127 cr, +36% YoY; margin 7% |
| 9M operating PAT | ₹324 cr, +62% YoY; margin 6.4% |
| One-time exceptional item (new Labor Codes) | ₹17 cr provided in 9M |
| Revenue growth guidance for FY26 | 27%+, upgraded from 23%–25% |
| Order inflows (quarter) | ₹1,396 cr |
| 9M order inflows | ₹5,135 cr, +9% to 10% YoY; 55% domestic, 45% international |
| L1 position | ₹3,483 cr |
| Unexecuted order book | ₹14,733 cr; including L1: ₹18,216 cr; 57% domestic, 43% international; T&D 90% |
| Book-to-bill (with L1) | 2.5x |
| Net debt | ₹463 cr, down from ₹703 cr in H1 FY26; debt-equity 0.39x |
| Debt-to-EBITDA | 0.57x |
| Working capital days | 83 days, improved from 84 days in H1 FY26 and 91 days in FY25 |
| ROCE (9M) | 25.25%, consistently above 24% over past 3 years |
| Cash flow from operations (9M, pre-tax) | ₹440 cr, up from ~₹300 cr in 9M last year |
| Contract assets | ₹2,643 cr as of Dec 31, vs ₹2,522 cr as of Mar 31 |
| Addressable market visibility (next 12 months) | >₹1 lakh cr, ~60% domestic, ~40% international |
| Bangladesh project receivables | ₹488 cr |