Vascon Engineers Ltd Q1 FY2027 Concall Summary

Source transcript PDF: https://assets.stockscans.in/docs/n3l0r5b6k494mp8s6c8b7a30.pdf

Key Takeaways


EPC Execution: The Quarter That Broke

Sundararajan: “It has been one of the worst quarters we've had over the last 3 to 4 years, but I think there's nothing structurally wrong that has led to that. It is just a matter of execution.”

Real Estate: Bookings Inflection, Profit Recognition Lagged

Sundararajan: “Achieving the price points embedded in our underwriting rather than pursuing volumes at the expense of value.”

Balance Sheet & Working Capital: The Debt Spike

Biswas: “We are seeing that the net working capital cycle has been increased from 45 days to almost 65 to 70 days... we are quite sure we are seeing the light at the end of the tunnel that things are getting pretty improved.”

Order Book & Pipeline: Rebuilding the EPC Foundation

Sundararajan: “We don't want to call it canceled yet. But at the same time, there is no go ahead from the client. So for this financial year, let's just assume there will be no revenue coming.”

Real Estate Strategy: Geography, Discipline, and the Pipeline

Sundararajan: “...it's a bit easier for us because our base currently is low. So for us to grow from ₹100 crores and double over the next 3, 4 years is a must for us to even see reasonable profits in the real estate business.”

Guidance & Commitments

CommitmentSpecificsTimeline
Consolidated revenue target₹1,200 crores (EPC ≥₹900 crores, hope for ₹1,000 crores; real estate ₹200 crores plus)FY27
EPC revenue phasingQ1 + Q2 = 30% of annual top line; Q3 + Q4 = 70% (vs typical 40/60 split)FY27
EPC PBT marginCloser to 8–9% if EPC executes ₹1,000 croresFY27
EPC order booking₹1,500 crores to ₹2,000 croresFY27
Real estate revenue recognitionBulk recognition only in Q4FY27
Project completions (OC)Coimbatore project and Tower of Ascend (Kharadi)Q3/Q4 FY27 (targeting within this year)
Project completionOrchid SantacruzEnd of FY27 (tight task, target only)
Stalled project restartVashi Hospital mobilizationQ2 FY27
Stalled project restartVedanta project completionFY27
Working capital normalizationNet working capital cycle to align back to ~45 daysOver next 6–8 months
Short-term EPC debt rolloverDebt to roll over as projects kick off and cash flows come6–8 months
New project acquisitionsConversion of some active opportunitiesNext 2–3 quarters
Warrant fund deployment~₹80 crores infused in tranches, ~60–70% to real estateOver 18 months
Adani projectsNo construction start; revenue maybe Q4 or next yearNext 6 months (no start)
Royal Rides projectAssume zero revenueFY27

Key Metrics

MetricQ1 FY27
Consolidated revenue from operations₹152 crores, compared to ₹221 crores in Q1 FY26
Consolidated EBITDA₹10 crores, compared to ₹34 crores in Q1 FY26; Q1 FY26 included a one-time gain of ₹18 crores from sale of an investment
Adjusted EBITDA margin~6%, broadly in line with Q1 FY26 on an adjusted basis (adjusted Q1 FY26 EBITDA was ~₹15 crores)
Profit after tax₹2 crores, compared to ₹22 crores in Q1 FY26
EPC revenue~₹148 crores, compared to ₹203 crores in Q1 FY26
EPC EBITDA margin~9%, compared to 8% in Q1 FY26
Real Estate segment revenue~₹4 crores
Real Estate segment EBITDALoss of ~₹4 crores
Net debt~₹152 crores as of June 30, 2026
Order book₹2,850 crores
Real estate booking value₹66 crores, compared to ₹113 crores in full year FY26
Real estate new sales bookings~30,690 square feet
Real estate total collections~₹20 crores
Net working capital cycle65–70 days, increased from 45 days over the last 6 months or more
FY27 total revenue target₹1,200 crores, management remains confident of achieving this