Key Takeaways
- Steady H1 despite weather, H2 catch-up expected: Revenue grew 13% YoY in H1 FY26 even as prolonged monsoons slowed site execution; management expects the traditional H2 weighting (60% of annual target) to hold as weather normalizes.
- Order book at INR2,800 crores, but FY26 inflow target needs a sprint: The backlog covers 2.8x FY25 EPC revenue, yet the company must book roughly INR1,100 crores in the next five months to hit the lower end of its INR1,500–2,000 crore FY26 order inflow target.
- Adani MOU is a potential structural shift, not near-term revenue: The five-year early-engagement partnership covers ~1.3 crore sq ft in Mumbai, but projects are at design stage and no revenue is expected this fiscal year.
- Real Estate profitability is a story for FY28, not FY27: The segment should be profitable next year, but management says sustained INR200–300+ crore annual revenue will only materialise from the year after next.
- What to watch next quarter: Whether the INR1,100 crore order inflow gap closes before year-end, the pace of Santacruz residential sales once the project comes above ground, and any Adani contract terms that get firmed up.
EPC: Growth, Margins & the Order Inflow Gap
- H1 delivery held back by rain: EPC revenue grew 14% YoY in Q2 to INR227 crores and 10% YoY in H1 to INR431 crores, with early Q1 rainfall and heavy Q2 monsoons hampering on-ground activity across multiple sites.
- H2 rebound assumed: Management notes H2 is traditionally more conducive for execution, with H1 historically covering only 35–40% of the annual target and the balance 60% coming in H2. Site activity has already begun to pick up as weather normalises.
- FY26 EPC revenue target of INR1,200 crores: This implies 20% YoY growth; internal reviews show jobs scaling up and progressing at a good pace, and management calls it achievable barring something unforeseen.
- FY27 EPC target of INR1,400+ crores: Another 20% growth step, with the margin math resting on fixed-cost absorption at higher scale rather than on project-level margin improvement.
- Margin trajectory is a scale story: When EPC revenue was stuck at INR300–400 crores (2017–2019 plus COVID), fixed costs barely got covered. Once revenue crossed INR500 crores and now INR1,000–1,400 crores, margins reached 8–9% and are inching toward 10%.
- FY26 margin depends on old projects, not new wins: This year's margin is purely from projects already under execution; new projects bagged at lower margins will only translate next year.
- FY27 margin risk is modest and offsettable: New lower-margin orders may cause a 0.5–0.75 bps EBITDA drop, but if INR1,400+ crores revenue is achieved, fixed cost divided over higher revenue should compensate, so EBITDA could remain the same.
- Order inflow target needs a big H2: The FY26 target is INR1,500–2,000 crores of new EPC orders; with INR161 crores from MSEB and INR225 crores from Royal Rides already in hand, a minimum INR1,100 crore shortfall must be covered in the next five months.
- No guarantee, just aggressive bidding: Management acknowledges there is no guarantee on order inflow, but says the company has bid on projects where it is confident and has bid aggressively; bids should open in the short term. Survival of the company depends on booking decent orders in the next few months.
- Working capital now enables aggression: The company has ample working capital limits available in the form of bank guarantees, enabling more aggressive bidding compared to earlier when BG scarcity forced selectivity. Unutilised working capital can support up to INR3,000 crores of additional EPC orders.
Sundararajan: "more than confidence or -- I mean, it is just a need we have to book. So the survival of the company depends on us booking some decent orders in the next few months."
The Adani Partnership
- A five-year early-engagement MOU: Vascon signed a strategic MOU with Adani Limited under which Vascon will be involved from the design stage through execution on select projects totalling about 1.3 crore square feet in Mumbai. The collaboration envisages Vascon's ongoing projects equivalent to about 30% of annual turnover.
- Selection followed a competitive process: Management stated Adani went through three rounds of shortlisting before choosing Vascon, with Adani making clear it needs a few good contractor-partners to execute its large construction pipeline.
- Contract structure is bilateral, not government-linked: The agreement is entirely between Vascon and Adani; Vascon's contract will be only with Adani, and Adani will be the paymaster. Payment terms will be construction-linked as project execution happens.
- No revenue this fiscal year: Projects are at the design stage and will only reach construction at least 6–8 months down the road. Management does not expect even INR1 crore in orders from Adani until March–April. The order pipeline from Adani may start from next year onwards.
- Terms still open: Management declined to disclose specific project details citing an NDA, and said the mode of contract and how cost escalations will be handled would be decided as they go along; terms of contract are still a bit open.
- 30% aspiration is conditional: Management looks to get about 30% of the order book or execution from Adani, but this will depend on terms and how happy Vascon is with those terms.
Sundararajan: "They have made it amply clear that they have a huge pipeline of construction, which they believe cannot be executed unless they partner a few good contractors and treat them as partners along with them. And we went through 3 rounds of shortlisting and we've been chosen."
Real Estate: Slow Sales, Long Payoff
- H1 FY26 saw steady progress but modest bookings: New sales booking of 64,541 sq ft with a booking value of INR74 crores and collections of INR88 crores; these numbers will reflect in financials upon revenue recognition.
- Santacruz project sales are slow: Sales are going slow; the company is about 2–3 months away from coming above ground and seeing residential flats. Management has consciously stayed away from dropping prices to sell, and needs a few crores more to reach the level where construction goes at full pace.
- Near-term pipeline is substantial: The real estate pipeline includes a JV residential project in Powai, a 4-acre development in Kharadi, the Tower of Future commercial project in Baner, Pashan, and Prakash Housing Society in Santacruz. Together these offer 0.08 crore sq ft of saleable area with INR1,110 crores of sales potential attributable to Vascon.
- Profitability is a two-step story: Real Estate is taking longer than EPC did; approvals are taking longer and sales are more sluggish than hoped. Next year should still be profitable, but sustained revenue of INR200–300+ crores year-on-year should happen only from the year after next. Gross profits in real estate are double that of EPC.
- Segment margins dipped on marketing spend: Real Estate EBITDA margins declined in H1 due to high marketing costs incurred for the first half year ending September.
Sundararajan: "next year should still be profitable, but the real sustained revenue of more than INR200 crores, INR300 crores coming from real estate year-on-year should happen from the year after next."
Financial Position & Profitability
- Q2 PAT grew 44% YoY to INR11 crores: Supported by strengthened cost efficiency measures.
- EPC EBITDA margin consistent at 9–10%: Management targets taking this to 10–12% this year.
- Working capital position improved materially: The company now has ample working capital limits available in terms of bank guarantees, enabling more aggressive bidding. Unutilised working capital can support up to INR3,000 crores of additional EPC orders.
- KMP share sales explained as ESOP-related: Key managerial personnel have been selling shares because ESOPs are due next month; they need cash flow to buy ESOPs and pay heavy taxes.
- Thane land status unchanged: No movement; acquisition is pending from the government for a corridor passing through the land (about 40 acres). Elections in December may bring stabilisation.
Order Book Composition
- Order book at INR2,800 crores as of September 30, 2025: This represents 2.8x FY25 EPC revenue. The breakup is INR2,411 crores in external EPC contracts and INR389 crores in internal real estate projects. About 74% comes from government-backed projects.
- Key recent wins: A INR225 crore order from Royal Rides Private Limited (April 2025, to be executed over three years) and a INR161 crore order from MSEB for the redevelopment of Saudamini building at Haji Ali (secured during Q2).
Guidance & Commitments
| Commitment | Specifics | Timeline |
|---|---|---|
| EPC revenue growth | 20% YoY growth to INR1,200 crores | FY26 |
| New EPC order inflow | INR1,500–2,000 crores of new orders | FY26 |
| EPC revenue growth | 20% growth over FY26 to ~INR1,400+ crores | FY27 |
| EBITDA margin | Improve from ~10% to 10–12% | FY26 |
| EBITDA margin stability | EBITDA could remain same as current year despite lower-margin orders, if INR1,400+ crores revenue achieved | FY27 |
| Adani revenue contribution | No revenue expected this fiscal year; order pipeline may start | From FY27 onwards |
| Real Estate sustained revenue | INR200–300+ crores year-on-year | From FY28 (year after next) |
Key Metrics
| Metric | Q2 FY26 |
|---|---|
| Consolidated income | ₹229 cr, +14% YoY over ₹202 cr in Q2 FY25 |
| EPC revenue | ₹227 cr, +14% YoY |
| H1 FY26 consolidated total income | ₹471 cr, +18% YoY over ₹400 cr in H1 FY25, includes profit from sale of Ascent Hotels |
| H1 FY26 EPC revenue | ₹431 cr, +10% YoY |
| EBITDA | ₹20 cr, compared to ₹17 cr in Q2 FY25 |
| H1 EBITDA (excl. Ascent sale profit) | ₹36 cr, compared to ₹34 cr in H1 FY25 |
| EPC EBITDA margin | 9% to 10%, consistent |
| Profit after tax (continued ops) | ₹11 cr, +44% YoY over ₹8 cr in Q2 FY25 |
| H1 profit after tax (continued ops) | ₹34 cr, compared to ₹17 cr in H1 FY25 |
| Order book | ₹2,800 cr, 2.8x FY25 EPC revenue, as of Sep 30, 2025 |
| Order book – external EPC contracts | ₹2,411 cr |
| Order book – internal real estate projects | ₹389 cr |
| Government-backed orders share | 74% of total order book |
| New EPC orders secured in Q2 | ₹161 cr from MSEB for Saudamini building redevelopment |
| FY26 EPC order inflow target | ₹1,500 cr, with ~₹400 cr bagged so far and ~₹1,100 cr minimum target for remaining months |
| FY26 EPC revenue target | ₹1,200 cr, +20% YoY |
| Real estate – H1 new sales booking | 64,541 sq ft, booking value ₹74 cr, collections ~₹88 cr |
| Real estate – total sales to date | 0.05 cr sq ft sold, sales worth ₹291 cr, ₹221 cr collected |
| Real estate – revenue recognized to date | ₹116 cr from Tulips and GoodLife |
| Near-term real estate pipeline sales potential | ₹1,110 cr attributable to Vascon, 0.08 cr sq ft saleable area |
| Working capital – total sanction limits | ₹645 cr, with ₹271 cr unutilized and ₹150 cr under appraisal |
| Adani MOU – project pipeline | 1.3 cr sq ft in Mumbai, 5-year early engagement model, ~30% of annual turnover equivalent |