Key Takeaways
- EPC revenue missed, driven by election and client delays: EPC revenue fell sharply YoY as Bihar elections froze payments on the Supaul project and Capgemini slowed its Chennai site, together costing roughly ₹130–150 cr in lost revenue.
- Order booking fell well short of the ₹1,500 cr target: The company booked only ~₹650 cr against its FY26 goal, with management acknowledging it "failed in a big way" on this count while pointing to a cumulative ₹3,000 cr-plus target by April 2027.
- Real estate contributed zero revenue this quarter: No projects reached completion in Q3, versus the year-ago quarter that booked the GoodLife project; debt in the segment rose to ₹150–160 cr after the planned QIP was dropped.
- Adani partnership is the medium-term thesis, but revenue is distant: Technical discussions are frozen, four to five projects are in design, yet management sees concrete orders and revenue as "at least six months away," with no contribution in the next two quarters.
- What to watch next quarter: Whether the ₹1,300–1,500 cr of L1 positions convert to booked orders, any resolution on the stalled Vedanta (~₹30 cr remaining) and Supaul payments, and the pace of Orchids sales conversion around Gudi Padwa.
EPC Execution: What Broke This Quarter
- Supaul project halted by Bihar elections: Payments were stuck due to the election cycle, forcing the company to stop or slow site work and reduce labor; this was the single largest drag on quarterly and full-year EPC revenue.
- Capgemini Chennai slowed on client-side CapEx review: The client relooked at internal processes and capital spending decisions, delaying the project and removing an estimated ₹30–50 cr from FY26 revenue.
- Vedanta project still not closed: Roughly ₹30 cr of work remains, but top-management decisions at Vedanta are pending; management is hopeful of completion by Q2 of this financial year.
- Royal Rides, Goa has not started at site: The ropeway project is dependent on client-side government approvals that have not come through; no revenue is expected in the next three months.
- Revenue recognition policy amplifies lumpiness: Real estate revenue is booked only on full project completion, not percentage-of-completion, so any delay in finishing a project wipes out the entire quarter's contribution.
Santosh Sundararajan: "between the devil and the deep sea, we had no choice but to choose the devil and stop or slow down site."
Order Book & the Bidding Environment
- FY26 order booking target missed by a wide margin: Against a ₹1,500 cr target, only ~₹650 cr was booked; management stated the cumulative target of ₹3,000 cr-plus by April 2027 is not being reduced, implying a steep catch-up in FY27.
- Competitive intensity in UP is extreme: Tenders in the state are being awarded at minus 25% to minus 30%, while the company is unwilling to bid beyond minus 10%; management described the bidding horizon as "crazy."
- Margin expectations lowered to stay in the game: The company has brought down its margin expectations and is now ready to bid in the 13% range rather than 15%, a deliberate trade-off to secure volume.
- L1 positions offer a near-term pipeline: The company is currently L1 for orders totaling ₹1,300–1,500 cr across Tamil Nadu, Karnataka, and the private sector; conversion of these positions is the most concrete near-term order book catalyst.
- Municipal elections froze tenders in key states: In UP, Bihar, and Maharashtra, a large number of tenders were put on hold due to municipal elections; Bihar has only now stabilized.
- Project selection is deliberately conservative: The sweet spot is ₹300–800 cr projects; the company evaluates which government department is funding and stays away from politically sensitive buildings that could be jeopardized by a change in government.
Santosh Sundararajan: "I will make it amply clear that on that count, it does look like we have failed in a big way. But we are not unduly perturbed."
Real Estate: Zero Revenue, Rising Debt, and a Pivot
- No real estate revenue in Q3: No projects reached completion during the quarter; the year-ago quarter had benefited from the GoodLife project completion, creating a tough base effect.
- Real estate debt rose to ₹150–160 cr: Borrowing increased from ~₹80 cr in FY24 because the planned ₹125 cr QIP was dropped due to market conditions and a desire not to dilute equity drastically; projects could not be stopped, so funding was arranged through other means.
- GoodLife Phase-2 shelved, land to be monetized differently: Management has no plan to launch Phase-2 in the affordable segment, citing challenges in that space; the land will be monetized through other options such as hotels or commercial development.
- GoodLife Phase-1 inventory held strategically: A large amount of completed inventory has been rented out, generating rental demand, and the same inventory is serving as collateral for the EPC segment's bank guarantee limits.
- Orchids sales velocity is slow but expected to improve: As the first redevelopment project in Bombay, sales velocity is typically low until the project reaches ground level; it is now at G+1 and inquiry velocity has increased substantially, with ~10–12 additional bookings in documentation.
- Prakash Housing Society redevelopment is the next launch: All approvals have been received and construction is expected to commence in Q1 FY27.
Santosh Sundararajan: "Once we are about 25% sold, we do not even want to be slashing prices. Since it's a small project and our inventory is small, we are not unduly worried about the slower velocity."
The Adani Partnership: Promise and Patience
- Engagement has deepened beyond the original three parcels: Discussions now cover four to five projects at the design stage, including sites in Ghatkopar and other cities, plus airport site developments, beyond the three large Mumbai parcels initially discussed.
- A new contracting methodology is being worked out: Technical discussions on responsibilities have been frozen, and both parties are working on a medium- to long-term partnership structure.
- Revenue is at least six months away: Management was explicit that receiving a concrete order and starting revenue is still at least six months out; no revenue will translate in the next two quarters.
- Once it starts, the effect is expected to be sustained: Management anticipates a quarter-on-quarter incremental effect for two to three years once revenue begins.
- Original parcel timelines are unknowable: Management declined to provide any timeline for the originally discussed three Mumbai parcels, noting each is at a different stage of approval, some very nascent, and the approval timeline is outside the company's control.
Santosh Sundararajan: "it does look to me that finally in terms of receiving a concrete order for a particular project and starting revenue, it still looks at least six months away."
Balance Sheet & Funding
- SBI working capital terms improved: Collateral coverage was reduced from 35% to 27%, bank guarantee margins for guarantees exceeding three years were cut to 15% from 25%, and BG commission rates were improved.
- CRISIL long-term rating reaffirmed at A-minus: The rating was reaffirmed for the current year.
- QIP dropped, debt used as bridge: The ₹125 cr QIP program (with ₹100 cr earmarked for real estate) was dropped due to market conditions; project funding for Powai, Baner, and Prakash, which required FSI purchases and approval costs, was done through borrowing.
- Real estate debt optimization, not elimination: Management clarified that optimizing debt does not mean eliminating borrowing on the real estate side.
- Order inflow slowdown is not a banking-constraint issue: The company has been filling a large number of tenders and the slowdown is not attributable to a lack of banking relationships or bank guarantee availability.
Somnath Biswas: "But due to certain market conditions, all these things, we do not want to dilute our equity drastically, we dropped the QIP program. But obviously, the project cannot be stopped."
Guidance & Commitments
| Commitment | Specifics | Timeline |
|---|---|---|
| Cumulative order booking | ₹3,000 cr-plus from EPC orders | By April 2027 |
| Vedanta project completion | Remaining ~₹30 cr of work completed | Hopeful by Q2 of this financial year |
| Adani revenue start | Concrete order received and revenue begins | At least six months away |
| Prakash Housing construction start | Construction commences on redevelopment project | Q1 FY27 |
| EPC margin posture | Ready to bid in the 13% range (down from 15%) | Current |
| FY26 EPC revenue | Will not achieve the projected ₹1,200 cr-plus; one top project and Capgemini together cost ~₹130–150 cr in lost revenue | FY26 |
Key Metrics
| Metric | Q3 FY26 |
|---|---|
| Consolidated total income | ₹254 cr, decline of ~15% YoY vs ₹298 cr in Q3 FY25 |
| EBITDA | ₹17 cr vs ₹24 cr in Q3 FY25 |
| EPC EBITDA margin | ~10%, stable YoY |
| Profit after tax | ₹9 cr vs ₹76 cr in Q3 FY25, decline of 88% on absolute basis; Q3 FY25 included exceptional gain of ₹75 cr from sale of GMP |
| Consolidated total income (9M FY26) | ₹725 cr vs ₹698 cr in 9M FY25 |
| EBITDA (9M FY26, excl. profit from sale of Ascent Hotels) | ₹53 cr vs ₹58 cr in 9M FY25 |
| EPC EBITDA margin (9M FY26) | 9% |
| Profit after tax (9M FY26) | ₹43 cr vs ₹93 cr in 9M FY25, decline of 55% |
| EPC revenue | ₹248 cr, moderation of ~9% YoY |
| EPC revenue (9M FY26) | ₹676 cr, ~4% growth YoY |
| New EPC orders secured (FY26 to date) | ₹646 cr |
| Total order book | ₹2,825 cr as of Dec 31, 2025, ~2.8x FY25 EPC revenue; external EPC contracts ~₹2,470 cr, internal real estate projects ₹355 cr |
| Government-backed projects share of order book | ~77% |
| Real estate new sales booking (9M FY26) | 77,315 sq ft, total booking value ₹86 cr, collection ~₹105 cr |
| Real estate cumulative booked sales | ₹303 cr, cumulative collected ₹238 cr, revenue recognized ₹117 cr |
| Near-term real estate pipeline gross sales value | ₹2,360 cr total developmental potential, ₹1,110 cr attributable to Vascon |
| Total working capital sanction limit | ₹745 cr, ~₹370 cr unutilized, additional ₹60 cr under appraisal |
| Real estate debt | ~₹150 cr to ₹160 cr range |
| CRISIL long-term credit rating | A-minus, reaffirmed for current year |