Viceroy Hotels Ltd Q3 FY2025 Concall Summary

Source transcript PDF: https://assets.stockscans.in/docs/dsxitcq0no99lktu7r5s1wu9.pdf

Key Takeaways


Renovation Program & Capacity Expansion

Kodali: "the flow-through profit in this additional ADR jump is almost about 95%."

ADR & Pricing Power

Kodali: "this sort of gap between supply and demand only leads to one thing, that is increase in ADRs."

Demand Environment


Portfolio Expansion


Guidance & Commitments

CommitmentSpecificsTimeline
Courtyard expansion operationalAll new floors (6th–9th) with 56 rooms, gym/spa, rooftop bar and poolEnd of June 2025
Marriott convention center renovationConvention center taken out April 1, expected back operationalSeptember 2025
Select Marriott guest rooms renovatedRooms attached to convention center renovated and liveWithin 2025
Overall renovation completionPhase-wise renovation of both hotelsBy 2027
Post-renovation ADR target₹9,500 to ₹10,500First full year post-renovation
Post-renovation revenue target~₹170 cr revenue, EBITDA north of ₹60 crFirst full year post-renovation
Portfolio expansionThird hotel in Hyderabad"Very, very soon"; definitive agreement pending

Key Metrics

MetricQ3 FY25
Revenue from operations₹37.75 cr, up 16% QoQ
EBITDA₹11.35 cr, up 43% QoQ
EBITDA margin30.1% (per an analyst's math)
ADR₹7,423, significantly higher than Q2 ADR of ₹6,063
Occupancy~70%, above the comp set range of 65% to 70%
Post-renovation ADR target₹9,500 to ₹10,500
Post-renovation first full year revenue target~₹170 cr
Post-renovation first full year EBITDA targetnorth of ₹60 cr
Flow-through profit on additional ADR jump~95%
Rights issue subscriptionclose to 112%
Hyderabad market supply growth~3% to 4% per year
Hyderabad market demand growth~10% to 12% per year
Renovation completion timelineby 2027, phased over three years
Courtyard by Marriott new rooms addition56 guest rooms expected by end of June 2025