Key Takeaways
- Volume doubled, margins normalized: Sales volume rose to 796 MW (vs 590 MW YoY) while EBITDA margin reached 18.5% (vs 8% YoY), though Q3 margin dipped as expected because ~30% of execution came from older government contracts.
- Capacity build-out on track: The 5 GW Vallam facility was commissioned, taking module capacity to 9.5 GW, and the Gangaikondan cell plant is targeting first cell-out by December 2026, a milestone that will shift the cost structure and reduce China dependence.
- Input costs are rising, but the model protects: Chinese polysilicon controls, silver price surges, and the removal of a 9% VAT export rebate from April 2026 are tightening the input environment; management says cost-plus contracts pass through the impact for 88% of the order book.
- Export ambition meets tariff reality: Indian cells are unviable for exports due to reciprocal tariffs, so the export supply chain must run through Southeast Asia with UFLPA/FEOC compliance, a workaround that is still being built.
- What to watch next quarter: Whether the Gangaikondan module plant commissions on schedule in Q1 FY27, progress on the BESS technology partnership announcement, and any movement on the lapsed anti-dumping duty recommendation on Chinese cells.
Volume, Margins & the Q3 Mix Effect
- Volume scale-up: 796 MW sold in Q3 FY26 versus 590 MW in Q3 FY25, supported by a stronger execution base built over the prior year. Effective capacity utilization ran at 90% for the quarter and 88% for the nine-month period.
- Margin normalization, not decline: EBITDA margin of 18.5% in Q3 FY26 compares to 8% in Q3 FY25; the 9M FY26 margin of ~20% compares to 12% in 9M FY25. The Q3 dip was anticipated because roughly 30% of the quarter's execution came from government contracts taken about a year back, which is normal course of business.
- Realization drop explained: Q3 FY26 had 100% non-DCR execution, while Q3 FY25 included a DCR utility-scale contract that lifted blended realization. Non-DCR modules saw a 30% to 40% drop in realization, and management noted that a few basis points of margin swing is not a decline but a function of the specific execution mix committed to.
- Cost efficiency levers: Higher throughput, greater shop-floor automation, and tighter indirect cost control drove the improvement. Newer capacity additions feature advanced automation that reduces manual touch points and labor cost while improving manufacturing yields.
- Finance cost tailwind: Weighted average finance cost declined to 6.5% in 9M FY26 from 7% in H1 FY26, supported by disciplined cash flow management, improved credit profiles, and timely interest rate resets in a declining rate environment.
- Non-DCR margin expectation: Management expects non-DCR business to deliver 18% to 20% EBITDA on a sustained basis, with non-DCR realization at INR14 to INR14.5 per watt peak given the current increase in cell costs. DCR module prices are expected to remain at INR23-24.
Ranjan Jindal: "It is, however, pertinent to mention that the Module Supply Contracts signed by the company are designed to pass through the impact of such rising input costs to the consumers since we operate in a cost-plus business model."
Capacity Expansion & the Backward-Integration Bet
- Vallam commissioned: A 5 GW advanced module manufacturing facility at Vallam, Tamil Nadu, was commissioned during the quarter, taking total installed module capacity to 9.5 GW. The plant is designed as a highly automated, future-ready facility built on advanced N-type technology with flexibility for next-generation upgrades.
- Gangaikondan progress: All statutory approvals are in place; core site infrastructure including access roads, construction power, and site offices is complete. Civil works for module and cell facilities are ongoing: module plant structural works and roofing are in progress, while cell plant foundation and sub-structure works are underway with critical long-lead items under finalization.
- Cell plant timeline: The 12 GW cell plant's clean room is expected to be ready by September-October 2026, with commissioning and first cell-out by December 2026. The shifting exercise starts April-May 2026. Both upcoming cell plants will be capable of manufacturing both M10R and G12R cells.
- Capacity goal revised: Total module capacity goal updated to 15.5 GW (from 17.5 GW) to ensure 75% backward integration with 12 GW of planned cell capacity. The 2 GW Falta expansion has not been cancelled but is retained; a decision will be revisited based on whether ALMM-II cells become mandatory.
- Leased 5 GW line: The Vallam facility was taken on lease for approximately INR400 crores at 8.5% over 5 years, with an annual lease payment of roughly INR108 crores. Management cited speed (conceived February 2025, commissioned October 2025) and income tax deductibility of the full lease payment as rationale.
- Capex envelope: Total capex of INR10,000 crores is to be spent over the next 24 to 30 months.
- Product transition complete: The company has successfully transitioned to a complete portfolio of high-efficiency N-type modules, including the Hypersol Pro launched at REI Expo 2025 with efficiencies up to 23.7% and power outputs up to 640 watt-peak. The existing 9.5 GW module portfolio is shifting to G12R.
Gyanesh Chaudhary: "As the industry transitions through ALMM LIST-II for cells and the roadmap which has been given by the government for ALMM List III for wafers, we believe depth in domestic manufacturing and supply chain resilience will become increasingly important."
Input Costs, Sourcing & the China Question
- Tightening input environment: Chinese supply chain shifts including polysilicon production controls and the removal of a 9% VAT export rebate from April 2026 are pressuring input costs. Surging silver prices are also pushing up N-type cell input costs, though the company has no direct silver exposure because cells are imported.
- Cost-pass-through protection: Module Supply Contracts are designed as cost-plus, passing rising input costs through to consumers. For the 12% of the order book not covered, management is reaching out to customers to revisit pricing.
- Cell sourcing skew: Current cell procurement is heavily skewed towards China due to cost advantage, but a critical mass of supply is now available in other Southeast Asian countries with cost parity emerging as Chinese state-supported subsidizing moves away. The shift is not entirely commercial: it is also good to have diversified sources from a volume point of view. Chinese cells attract a 27.5% levy while non-Chinese South Asian cells land at almost the same pricing point.
- Only a one-year runway: The company has only about a one-year runway for cell sourcing from external partners before its own cell capacity comes online. Conversations with partners in other Southeast Asian countries are being activated.
- Silver reduction innovation: Management flagged new process innovations in cell manufacturing such as LECO and rear-side usage of silver-coated copper pastes as being explored to reduce silver consumption per watt, calling it a huge catalyst for the industry to innovate towards better conductive polymers.
Ranjan Jindal: "And the whole purpose of making a shift from China to Southeast Asia is not entirely commercial. It's always good to have diversified sources from the volume point of view also."
Export Strategy & the Tariff Hurdle
- Indian cells are unviable for exports: Reciprocal tariffs imposed on India make Indian-manufactured cells uncompetitive for export markets. The export supply chain must therefore run through Southeast Asian countries with UFLPA-compliant and FEOC-compliant sourcing, plus CBP pre-approval.
- Competitive landscape shifting: Larger CMVT countries faced similar duties earlier in calendar year 2025. Capacity is coming up in North African regions and other Asian countries, and Vikram is actively working with these sources.
- Structural opportunity, tariff headwind: Management views the export opportunity as structural rather than cyclical, believing India has achieved critical mass where manufacturers with 10-15 GW capacity can compete with China globally. Markets like Europe and MENA are accessible if India remains competitive, though the current tariff regime is creating a challenge.
- Export order book: Exports represent 16% of the current order book, not 20% as an analyst had assumed.
Gyanesh Chaudhary: "So, we don't see a challenge there. Trying to bid and win large orders and accessing markets like Europe, MENA, you're right, current tariff regime is creating a bit of a challenge. But ultimately, the market is still very strong."
Demand, Order Book & Competitive Position
- Domestic demand visibility: The domestic order book is adequate to carry through the next 4-5 quarters until cell capacity comes online. About 30-35 GW+ of utility-scale DCR demand is expected in Fiscal 2028, with a healthy pipeline of more RFSs expected in coming quarters.
- No deferment risk: No developer has asked for a shift in supply; production and sales have been at the same level, maintaining the same stock. Customer-wise dispatches and payments/LCs are in place, and management foresees no deferment.
- Installation runway: Management sees no risk of a slowdown in the next two fiscals. Beyond Fiscal 2028, DCR RFSs and rooftop/C&I adoption will sustain momentum for the next 5 to 10 years.
- Tender pipeline math: Per an analyst's math, adjusting the 108 GW of tenders for roughly 42 GW without a PPA leaves approximately 70 GW of non-DCR AC as the addressable market. Management confirmed this figure, noting that the 42 GW has no official cancellation communication.
- Order inflow target: On a rolling basis, the target is 1.2x to 1.3x scheduled deliveries for the next four quarters, and that will be the target walking into Fiscal 2027. Focus segments will shift more towards non-government (C&I and distribution) in FY27.
- Competitive moat: Among the top 10 customers, 7 out of 10 are repeat and grant patronage to Vikram Solar. Management does not see a fight in that customer circle; overcrowding exists in lesser-efficient legacy systems (Mono PERC supply) among the 95 smaller manufacturers controlling 45 GW.
- TOPCon dominance: In the non-DCR market, the market has completely pivoted to TOPCon; there is hardly any expectation from the market of Mono PERC. In the DCR market, not enough TOPCon product is available, so PERC DCR remains valid for the immediate term. All additions going forward, including the 6 GW, will be TOPCon.
Rinal Shah: "We do not see that fight. And most of your overcrowding exists in the lesser efficient legacy systems."
BESS, Policy & Ratings
- BESS build-out: A 5 GWh battery pack facility is to be commissioned in Fiscal 2027, with parallel work underway for a 7.5 GWh integrated cell and battery pack facility. A technology partnership for lithium-ion battery cells is in advanced stages and will be announced soon; management stated that getting cell supply for the battery pack unit is not a challenge.
- ALMM III draft roadmap: MNRE issued a draft roadmap to extend the ALMM framework upstream to ingots and wafers, proposed effective June 1, 2028, subject to a minimum 15 GW capacity by three uncontrolled players. The company is evaluating commercial viability and demand outlook for FY28 and beyond; any capital deployment towards wafers will be undertaken in a disciplined, phased, and technology-driven manner.
- Anti-dumping duty lapse: The 90-day period for the Ministry of Finance to act on DGTR's anti-dumping duty recommendation on cells from China lapsed on December 29, 2025, with no development.
- MNRE lending clarification: MNRE issued a clarification that there is no freeze on solar lending, just a nudge to incentivize vertical integration.
- Credit rating upgrade: India Ratings upgraded long-term bank facilities from Ind A to Ind A+ with stable outlook, and short-term rating from Ind A1 to Ind A1+. The company was also recognized as a Tier 1 solar module manufacturer for the eighth consecutive quarter in the BloombergNEF Bankability Rating.
Guidance & Commitments
| Commitment | Specifics | Timeline |
|---|---|---|
| Gangaikondan module plant commissioning | On track | Q1 FY27 |
| Gangaikondan cell plant first cell-out | Phased commissioning; clean room ready Sep-Oct 2026 | December 2026 |
| Non-DCR EBITDA margin | 18% to 20% on a sustained basis | Ongoing |
| Non-DCR realization | INR14 to INR14.5 per watt peak (with current cell cost increase) | Current |
| DCR module price | INR23-24 | Current |
| Order inflow target | 1.2x to 1.3x scheduled deliveries for next four quarters | Walking into Fiscal 2027 |
| Total capex spend | INR10,000 crores | Next 24 to 30 months |
| BESS battery pack commissioning | 5 GWh | Fiscal 2027 |
| BESS integrated cell and battery pack | 7.5 GWh, parallel work underway | No date given |
| BESS technology partnership announcement | In advanced stages | "Soon" |
| Falta 2 GW expansion decision | Revisited based on ALMM-II cell mandate becoming mandatory | Undated |
| Wafer manufacturing capital deployment | Subject to commercial viability assessment; disciplined, phased, technology-driven | FY28 and beyond |
Key Metrics
| Metric | Q3 FY26 |
|---|---|
| Revenue from operations | ₹1,106 cr, up from ₹1,026 cr in Q3 FY25 |
| EBITDA | ₹205 cr, 18.5% margin vs ₹85 cr, 8% margin in Q3 FY25 |
| Profit after tax | ₹98 cr vs ₹19 cr in Q3 FY25 |
| 9M FY26 revenue from operations | ₹3,349 cr, up from ₹2,230 cr in 9M FY25 |
| 9M FY26 EBITDA | ₹682 cr, ~20% margin vs ₹268 cr, 12% margin in 9M FY25 |
| 9M FY26 profit after tax | ₹360 cr vs ₹49 cr in 9M FY25 |
| Sales volume | 796 MW vs 590 MW in Q3 FY25 |
| 9M FY26 sales volume | 2.3 GW, surpassing full year FY25 sales volume by 23% |
| Effective capacity utilization | 90% for Q3 FY26, 88% for 9M FY26 |
| Order book | 10.58 GW as of 9M FY26, up 28% YoY from 8.2 GW |
| Order book pass-through coverage | 88% of order book has cell price pass-through as of 31st December |
| Non-DCR business sustained EBITDA guidance | 18% to 20% on a sustained basis |
| Weighted average finance cost of debt | 6.5% during 9M FY26, down from 7% in H1 FY26 |
| Total installed module capacity | 9.5 GW, entirely TOPCon, after commissioning of 5 GW Vallam facility |
| Headcount | 2,413 employees as of December 2025, up from 1,587 in December 2024 |