Key Takeaways
- Demand outstrips capacity, forcing order refusals: The company is completely booked out and turning away business, with volumes growing 7–8% only because the licensed 3-lakh-ton ceiling leaves no headroom.
- EBITDA per ton range set to widen upward: Cost reductions, fixed-cost absorption on higher volumes, and a full quarter of solar savings lifted profitability; management expects the range to shift from ₹8,000–11,000 to ₹8,000–12,000 next year.
- A second growth engine is being built right now: Ingot casting for non-automotive steel (die steels, railways, windmill shafts) will be established by Q3 and stabilized by Q4, seeding demand ahead of the new plant’s FY30 commissioning.
- The new steel plant is being reconfigured mid-flight: Capacity and project cost are both rising as the company redesigns for lower carbon footprint and better energy efficiency; a refined plan goes to the next Board meeting.
- What to watch next quarter: Whether the July 1 price increase sticks and lifts Q2 realizations, the finalization of land and machinery for the new plant by mid-September, and any progress on the environmental clearance that would unlock brownfield expansion to 3.6 lakh tons.
Demand & Capacity: Sold Out, Turning Orders Away
- Demand is very strong, all repeat business: The company is completely booked out and refusing orders; the demand scenario is good and the company is finding it difficult to meet customer requirements.
- Growth capped by license, not market: Volumes can grow only 7–8% because the licensed capacity is 3 lakh tons; management confirmed there is no capacity constraint for the current year, but beyond that, brownfield expansion to 3.6 lakh tons waits on environmental approval.
- Testing bottleneck is creating a pile-up: Material that is ready and meets customer specifications cannot go through due to lack of testing capacity; peeling is being done on job work from outside to clear the backlog.
- Export strategy deliberately deprioritized: Earlier assumptions that exports would take a bigger share were a mistake; the company now cannot meet existing domestic customer requirements, so exports are not high on the agenda. Direct exports are 6–7% of sales, indirect another 5%, though management acknowledged its estimates were off and will try to calculate indirect export content from next quarter.
- Maruti import substitution adds volume from Q4: The next volume increase from commercial production for Maruti import substitution will start in Q4 of FY27.
Sachit Jain: "We are completely booked out and we are refusing orders."
Profitability: Levers Firing, Range Moving Up
- Three levers drove the quarter’s EBITDA improvement: Cost reductions, bigger production spreading fixed costs over a larger volume, and a full quarter of savings from the solar plant, which now supplies 43% of total power consumption.
- Yield gains from the new reheating furnace: The newly stabilized reheating furnace has improved yields, contributing to the cost side of the margin equation.
- Job work and outside processing will reduce from Q3: This is the third lever management flagged for further margin improvement, alongside continued volume growth and operating-cost reductions from modernization.
- A fourth lever, a second solar plant, is a little over a year away: Due to changes in government policy, the company can enhance the solar project and expects to increase capacity by almost 50% in about 1 to 1.5 years, though cost savings will be lower than the first phase because government now requires locally made cells.
- Price revisions are flowing through, with more asked for Q2: Price revisions have taken place because costs have gone up; some have been agreed, some are still in process. The company has asked for a further price increase from July 1, so Q2 realizations will be higher. If Q1 settlements with some OEMs close higher, the Q2 ask will come down, and some Q1 profit may spill into Q2.
- Auto OEM pricing mechanism provides a floor: Prices change based on cost parameters (raw material costs); the company remains protected within a range that gets bumped up or down every few years based on market circumstances.
- Carbon footprint below 0.5 is a structural advantage: This places the company among the best Indian companies in carbon footprint, enabling a strong position for exports to Europe.
The Multi-Engine Growth Strategy
- Today, one engine; tomorrow, three: Management framed the strategy explicitly around building engines of growth beyond automotive steel. The second engine is non-automotive steel (die steels, railways, windmill shafts) via ingot casting; the third is the forging plant. A fourth engine, aerospace and nuclear plant steels, is maybe 1.5 years down the line.
- Ingot casting will be established by Q3, stabilized by Q4: This is the near-term diversification play. Die steel capability will be ready by the end of this year; Aichi, the Japanese partner, makes die steels and has the know-how. Die steels command ₹2.5 lakh a ton (non-ESR) and can cross ₹3.5–4 lakh a ton with ESR, though volumes are small.
- The forging unit is on track and under budget: The forging project is likely to be commissioned by the last quarter of FY28, with revenue starting maybe at the end of FY29 and into FY30. Project cost is lower than the estimated ₹475 crores, with savings of more than 10%; a better grip on total savings is expected by next quarter. A Technical Assistance Agreement has been signed with Aichi Steel, Japan for the forging unit.
- Non-automotive seeding starts now to fill the new plant later: The company is pushing die steel, railways, and windmill shafts now to seed the business so that when the new steel plant comes up, filling capacity becomes easier.
- Aerospace and nuclear JV is a separate, longer-term track: Management is talking to a few potential partners and looking for more; it will be a non-Aichi JV and will take a couple of years to find the right partner. No specific parties or timeline were named.
Sachit Jain: "Today, we have only automotive steel as an engine of growth. Tomorrow, we will have a second engine, which is non-automotive steel. And once the forging plant comes up, there will be a third engine of growth."
The New Steel Plant: Reconfigured, Bigger, Later
- On track for FY30 commissioning, but the project is changing: The new steel plant is expected to start by the end of FY30, with 6–8 months to stabilize and revenues from FY31. However, the company is partly reconfiguring the plant to reduce carbon footprint further and improve energy efficiency, which will increase both project cost and capacity.
- Details go to the next Board meeting: Management said details are still being worked out; by the next Board meeting, a clear picture with a refined project and increased capacity will be presented, with an effort to keep cost per ton similar to the original envisagement, though maybe a little higher because of the Iran war.
- Land and machinery are in the last stage: Land is in the last stage of getting finalized; machinery is also in last stages. By August end or latest mid-September, everything should be finalized. The Punjab government is fully assured in its support for the new plant.
- Capital raising is on the horizon: Sometime next year, depending on when funds are needed, the company will do capital raising. Vardhman Group and Aichi are committed to putting in capital; banks and institutions are also interested.
Sachit Jain: "Details are still being worked out. I think by next Board meeting, we will be able to have a clear picture and we present a refined project with an increased capacity and try to keep cost per ton similar to where we have envisage, maybe a little higher because of Iran war."
Partnerships & Approvals: The Aichi Advantage
- Aichi relationship unlocks multiple doors: The Japanese tie-up has already delivered Toyota global approval and is helping secure Maruti localization for imported steels. European OEM supply samples have gone, with commercial supply expected to start in H2 of this financial year.
- Environmental clearance is the gating item for brownfield expansion: The company has applied to the Environment Ministry for approval to increase melting capacity from 3 lakh to 3.6 lakh tons. Management expects approval in the next 3–4 months, but cautioned: "you haven't got it until you have got it." If approval comes, the FY28 sales target rises to approximately 290,000 tons, and with capex, 330,000–340,000 tons in FY29.
- New NDT line commissioning by September/October: This will help address the testing bottleneck that is currently causing a pile-up of finished material.
- No client concentration risk from the partnership: Management stated the company is well diversified; Maruti is about 10% of business, and there is no concentration risk.
Sachit Jain: "But again, you haven't got it until you have got it. So, fingers crossed till that time..."
Guidance & Commitments
| Commitment | Specifics | Timeline |
|---|---|---|
| EBITDA per ton range | Widen from ₹8,000–11,000 to ₹8,000–12,000 | Next year (FY28) |
| Ingot casting operational | Non-automotive steel capability established and stabilized | Q3 established, Q4 stabilized (FY27) |
| New NDT line | Commissioned to relieve testing bottleneck | September/October FY27 |
| Land and machinery finalization | New steel plant inputs locked | By mid-September FY27 |
| Refined new plant plan presented | Reconfigured project with increased capacity and cost | Next Board meeting |
| Forging unit commissioning | Project commissioned; revenue starts end-FY29/FY30 | Last quarter FY28 |
| New steel plant commissioning | Plant starts; 6–8 months to stabilize; revenues from FY31 | End of FY30 |
| Brownfield expansion (3 to 3.6 lakh tons) | Environmental clearance expected; capex follows; FY28 sales target rises to ~290,000 tons | Approval in 3–4 months; production helpful next year |
| Solar capacity increase | ~50% capacity addition | 1 to 1.5 years |
| Die steel regular production | Regular production of die steels | FY28 |
| Value-added products (forging/machining) | Revenue contribution begins | FY29 |
| EBITDA range floor raised | Remove ₹8,000 floor; confident of ₹9,000–12,000 range | FY29 |
| Aerospace/nuclear JV | Fourth engine of growth; separate non-Aichi JV | ~1.5 years to find partner |
| Capital raising | Equity raise for new plant; Vardhman Group and Aichi committed | Sometime next year |
Key Metrics
| Metric | Q1 FY27 |
|---|---|
| Revenue from operations | ₹486 cr, +12% YoY, driven by higher volumes and sales prices |
| Sales volume | 59,000 tons, +6.5% YoY |
| EBITDA | ₹68 cr |
| EBITDA per ton | ₹10,760, after excluding non-business income from surplus funds deployed in money markets |
| PAT | ₹41 cr, vs ₹34 cr in Q4 FY26 and ₹20 cr in Q1 FY26 |
| EBITDA per ton guidance range (current) | ₹8,000–11,000 |
| EBITDA per ton guidance range (FY28) | ₹8,000–12,000, management expects to raise the range next year |
| Solar power consumption | 43% of total power consumption, 2.3 cr units generated in the quarter |
| Carbon footprint | Below 0.5, among the best in Indian steel companies with approvals |
| Direct exports | 6–7% of total sales; indirect exports via Aichi trading arm: another 5% |
| Maruti share of business | ~10% |
| Volume target FY27 | 255,000 tons |
| Volume target FY28 | Over 270,000 tons; could rise to ~290,000 tons if environmental approval received |
| Forging project cost | ₹475 cr estimated; savings of more than 10% expected |
| Average selling price | ~₹85,000 per ton |