Vardhman Special Steels Ltd Q2 FY2027 Concall Summary

Source transcript PDF: https://assets.stockscans.in/docs/gruoe6wayufknh1luoh3f61s.pdf

Key Takeaways


Quarterly Performance: What Drove the Beat

Sachit Jain: "I will not expect — I will request you not to treat that for now as a standard kind of a thing. We still believe the EBITDA range will be between INR9,000 to INR12,000 EBITDA per ton."

Operational Improvements: The Margin Story


The Greenfield Project: Scope, Cost, and Timeline

Sachit Jain: "The project cost will be higher than the INR2,000 crores that we had envisaged. But we will also have the ability to have a higher production than 500,000 tons eventually."

Capital Allocation: Rights Issue, Dividend Suspension, and Leverage

Sachit Jain: "It does not make sense to give dividend, pay tax on that, and then ask rights issue for these same investors to put in money and rights issue."

New Business Lines: Forging, Ring Gears, and Import Substitution


Guidance & Commitments

CommitmentSpecificsTimeline
FY27 volumeSales of about 260,000 tons, a little higher than initial forecastFY27
EBITDA per ton₹9,000 to ₹12,000 range; current high end not to be treated as standardForeseeable future; reviewed annually
Q3 pricingExpecting some price increase; average realization to continue at same pace or a little higherQ3 FY27
Brownfield expansion to 360,000 tonsIf and when environmental approval comes, capacity increase takes about a year or December next year, whichever is laterConditional on approval
New steel plant completionProject completion by September 2029, stabilization by March 2030September 2029 / March 2030
Forging plant commissioningFull stabilization and commissioningMarch 2028
Rights issueEquity raising via rights issueH2 next calendar year
Dividend suspension decisionBoard to decide on suspending dividend for 3–4 yearsApril Board meeting
Revised project capex finalizationNew steel plant and forging plant capex figures finalizedMarch–April next year
Environmental approval filing for new plantFiling expectedDecember 2026
Ingot casting startStart of specialized steel production for non-automotive segmentsEnd of November 2026
NDT line commissioningNew NDT lineDecember 2026
Peeling line commissioningNew peeling lineEarly November 2026

Key Metrics

MetricQ2 FY27
Revenue from operationsUp 39% YoY
Total sales volumeMore than 70,000 tons, up from 59,000 tons in Q1 FY27
EBITDA and PATUp about 50% YoY
EBITDA per tonAt the highest part of the range; management guidance remains ₹9,000 to ₹12,000 per ton
FY27 full-year sales volume guidanceAbout 260,000 tons
Borrowings (as of 30 Sep 2026)₹162.93 crores, up from ₹92 crores at end of Q4 FY26; increase driven by Ind AS reclassification of LC discounting from trade payables
Trade receivables₹410 crores, up from ₹277 crores at end of Q4 FY26; days increased 4 to 5 days QoQ due to some high-credit-period customer sales
Direct exports6% to 7% of sales; indirect exports through ASC another 6% to 7%, same ratio as last year
Price increase letters from other companies₹3,500 to ₹4,000 per ton; no settlements finalized yet for Q3
Price increase over last 2 quarters for some OEMsAround ₹8,000 per ton; some OEMs settled with a lag at a lower amount, Q2 not yet fully settled for some
GST benefit status7-year period ended August 2026; electricity duty benefit continues for 10 years, valid up to August 2029
New steel plant project costWill be higher than the ₹2,000 crores previously envisaged; final figures by March-April 2027
New plant capacity scopeBuilding to increase beyond 500,000 tons to at least 700,000 tons in second phase
Forging plant Phase 1 capacity15,000 tons annually at full capacity; commissioning by March 2028
Brownfield expansion capex (300 to 360 KTPA)Approximately ₹100–115 crores; timeline about a year or December next year after environmental approval