Key Takeaways
- Strong quarter, demand-led beat: Robust automotive and non-automotive demand, amplified by a competitor's unscheduled shutdowns, drove price increases and pushed EBITDA per ton to the top of the guided range.
- Operational levers are now delivering: The Kocks Block and reheating furnace capex is yielding higher capacity, better yields, lower rework, and in-sourced job work, all of which lifted margins.
- The greenfield project is getting bigger and costlier: Management confirmed the new steel plant cost will exceed the original ₹2,000 crores estimate due to land, rupee depreciation, freight, and scope changes, with final numbers only by March–April.
- Capital allocation is pivoting: A rights issue is planned for H2 next calendar year, dividends may be suspended for 3–4 years, and the debt-equity mix for the new plant is shifting toward 1:1.
- What to watch next quarter: Whether Q3 price increases materialize as expected, the pace of the 360,000-ton environmental approval, and any further detail on the revised project scope and cost.
Quarterly Performance: What Drove the Beat
- Demand was broad and strong: GST cuts on two-wheelers and smaller vehicles, good SUV sales, and increased non-automotive demand tightened material supply for the automotive segment.
- Supply shock added a tailwind: Unscheduled shutdowns at a large competitor created a slight market shortage, increasing the pull for Vardhman's material.
- Pricing power followed the imbalance: The demand-supply mismatch led to good price increases over the last two quarters, with most Q2 prices settled and Q3 settlements ongoing.
- Volume spike is seasonal: Q2 is always the best quarter due to festive season inventory buildup; finished goods and billet inventories have been consumed, and this volume level is unlikely to repeat.
- Realizations are contract-driven, not spot: Revenue growth outpacing volume growth is driven primarily by market price resets in contracts, not spot sales, with commodity price increases flowing through over the last two quarters.
- Inventory gains are present but unquantified: Management acknowledged an element of inventory gain in EBITDA per ton, stated it is not sustainable, and does not separate it out.
- Accounting change to SAP S/4 HANA: From 1 July 2025, inventory is valued on batch-wise costing, eliminating the earlier revaluation based on a three-month average.
- Receivables jump is mechanical: The large increase in accounts receivable is directly proportional to the incremental 11,000 tons of sales in August and September, plus a 4–5 day increase in receivables days from sales to customers with longer credit periods.
- Borrowings reclassification, not a real increase: The rise in borrowings to ₹162.93 crores and trade receivables to ₹410 crores reflects an Ind AS change: creditors against discounting of LCs previously under trade payables are now reclassified to borrowings; combined borrowing and creditors show a decrease.
Sachit Jain: "I will not expect — I will request you not to treat that for now as a standard kind of a thing. We still believe the EBITDA range will be between INR9,000 to INR12,000 EBITDA per ton."
Operational Improvements: The Margin Story
- Capex benefits are compounding: The Kocks Block and reheating furnace commissioned last year began delivering cost savings in Q2, with benefits expected to increase going forward; the power plant is also yielding benefit.
- Job work brought in-house: A significant portion of job-work expenditure was eliminated as work previously sent outside came back in-house, directly lifting margins.
- Yield improvement from longer billets: Billet size increased from 4.2 meters to 5.2 meters; since wastage occurs at each end, a longer billet means proportionally less wastage and better yields.
- Quality gains are structural: Rework and rejections have come down due to the combination of the Kocks Block and the reheating furnace.
- Capacity unlocked to 300,000 tons: The Kocks Block and reheating furnace combination enabled capacity to increase to 300,000 tons, with potential to reach 330,000 tons.
- Production stabilization underway: Production has been stabilized at one billet size; full implementation over the next six months will give better flexibility to service customers using the combination of billet size and the Kocks Block.
The Greenfield Project: Scope, Cost, and Timeline
- Project cost is rising above ₹2,000 crores: Drivers include more expensive land, rupee depreciation after the Iran war, higher sea freight, higher metals and commodities, and certain second-phase equipment preponed into the first phase.
- Scope is being reconfigured: Product mix is being re-examined to better service non-automotive parts, and the plant will have capacity for higher-diameter blooms serving automotive, railways, and windmill sectors.
- Final numbers by March–April: Revised capex figures for both the new steel plant and the forging plant are still being revised and will be finalized by March–April next year; management declined to share any interim estimates.
- Timeline holds for now: The project remains on track for completion by September 2029 and stabilization by March 2030; environmental approval filing is expected by December 2026.
- Land progress: Land acquisition for the melting part is completed; rolling-part land acquisition is ongoing and should be completed by January of next year.
- Equipment and SMS: Equipment for the plant part is finalized, and land for the SMS is finalized.
- Non-automotive seeding begins now: Near-term, very limited non-automotive volume is possible because the plant is running at full capacity and focused on automotive; trials are underway in tool and die steels, and real volume expansion will come only with the new plant.
Sachit Jain: "The project cost will be higher than the INR2,000 crores that we had envisaged. But we will also have the ability to have a higher production than 500,000 tons eventually."
Capital Allocation: Rights Issue, Dividend Suspension, and Leverage
- Rights issue planned: Equity raising via a rights issue is planned for the second half of the next calendar year.
- Dividend suspension under review: Management is examining suspending the dividend for 3–4 years; a decision will be taken by the Board in the April Board meeting.
- Debt-equity mix shifting higher: Management may look at a 1:1 debt-equity ratio for the new plant, versus the earlier 0.5:1 to 0.75:1, implying a higher debt component and lower equity raising.
- Forging plant capex coming in lower: The forging plant capex will be lower than the ₹475 crores originally budgeted.
- Existing plant capex: Approximately ₹150 crores is planned over the next three years for the existing plant.
Sachit Jain: "It does not make sense to give dividend, pay tax on that, and then ask rights issue for these same investors to put in money and rights issue."
New Business Lines: Forging, Ring Gears, and Import Substitution
- Forging plant foundation laid: The foundation stone was laid by the Honorable Chief Minister of Punjab in end-July 2026; full stabilization and commissioning is expected by March 2028, and it will take time to fill the 15,000-ton capacity because it is a new business.
- Aichi driving the forging business: The Japanese partner has dispatched a senior-level person appointed as President of the forging business; Aichi will be driving this business.
- Ring gear section taking shape: Approval and orders have already been received from one of the big global Tier 1s, but it is a slow process because it is a new business and no certain plans or commitments are being made yet.
- Import substitution win: Approval received and mass manufacturing started for a major import substitution product (large quantity, very high-end quality) for a domestic major; sales to start from January.
- European OE approval secured: Approval received from the European OE and mass manufacturing has started; management is flexible on pricing mechanism, open to either the Indian quarterly negotiation system or the European alloy system.
- Ingot casting starts November: The ingot casting route to make specialized steels for non-automotive segments will start at the end of November.
- NDT and peeling lines near commissioning: A new NDT line is to be commissioned by December, and a new peeling line by early November.
Guidance & Commitments
| Commitment | Specifics | Timeline |
|---|---|---|
| FY27 volume | Sales of about 260,000 tons, a little higher than initial forecast | FY27 |
| EBITDA per ton | ₹9,000 to ₹12,000 range; current high end not to be treated as standard | Foreseeable future; reviewed annually |
| Q3 pricing | Expecting some price increase; average realization to continue at same pace or a little higher | Q3 FY27 |
| Brownfield expansion to 360,000 tons | If and when environmental approval comes, capacity increase takes about a year or December next year, whichever is later | Conditional on approval |
| New steel plant completion | Project completion by September 2029, stabilization by March 2030 | September 2029 / March 2030 |
| Forging plant commissioning | Full stabilization and commissioning | March 2028 |
| Rights issue | Equity raising via rights issue | H2 next calendar year |
| Dividend suspension decision | Board to decide on suspending dividend for 3–4 years | April Board meeting |
| Revised project capex finalization | New steel plant and forging plant capex figures finalized | March–April next year |
| Environmental approval filing for new plant | Filing expected | December 2026 |
| Ingot casting start | Start of specialized steel production for non-automotive segments | End of November 2026 |
| NDT line commissioning | New NDT line | December 2026 |
| Peeling line commissioning | New peeling line | Early November 2026 |
Key Metrics
| Metric | Q2 FY27 |
|---|---|
| Revenue from operations | Up 39% YoY |
| Total sales volume | More than 70,000 tons, up from 59,000 tons in Q1 FY27 |
| EBITDA and PAT | Up about 50% YoY |
| EBITDA per ton | At the highest part of the range; management guidance remains ₹9,000 to ₹12,000 per ton |
| FY27 full-year sales volume guidance | About 260,000 tons |
| Borrowings (as of 30 Sep 2026) | ₹162.93 crores, up from ₹92 crores at end of Q4 FY26; increase driven by Ind AS reclassification of LC discounting from trade payables |
| Trade receivables | ₹410 crores, up from ₹277 crores at end of Q4 FY26; days increased 4 to 5 days QoQ due to some high-credit-period customer sales |
| Direct exports | 6% to 7% of sales; indirect exports through ASC another 6% to 7%, same ratio as last year |
| Price increase letters from other companies | ₹3,500 to ₹4,000 per ton; no settlements finalized yet for Q3 |
| Price increase over last 2 quarters for some OEMs | Around ₹8,000 per ton; some OEMs settled with a lag at a lower amount, Q2 not yet fully settled for some |
| GST benefit status | 7-year period ended August 2026; electricity duty benefit continues for 10 years, valid up to August 2029 |
| New steel plant project cost | Will be higher than the ₹2,000 crores previously envisaged; final figures by March-April 2027 |
| New plant capacity scope | Building to increase beyond 500,000 tons to at least 700,000 tons in second phase |
| Forging plant Phase 1 capacity | 15,000 tons annually at full capacity; commissioning by March 2028 |
| Brownfield expansion capex (300 to 360 KTPA) | Approximately ₹100–115 crores; timeline about a year or December next year after environmental approval |