Vardhman Special Steels Ltd Q4 FY2026 Concall Summary

Source transcript PDF: https://assets.stockscans.in/docs/7bfc15uclely6w9x46fz3ctb.pdf

Key Takeaways


The Capex Super-Cycle: Three Plants, One Decade

Sachit Jain: "The advantage in the new plant will be that our costs are going to be much lower than the existing plant. And therefore, some of the commodity -- within the alloy steel, the commodity end of the business like tractors and trucks, which we normally stay out of, because of lower cost of steelmaking in the new plant, we may be able to access those markets."

Product Mix & the "Supermarket" Vision

Sachit Jain: "We will try to be a supermarket of special steels. But we are very clear, we will remain only in the areas of special steels."

FY26 Performance & FY27 Outlook

Sachit Jain: "When you go trekking and you cross a mountain, it seems at a height. As you reach that top, then you suddenly see newer vistas, which were not visible earlier."

Competitive Moat & Customer Access

Sachit Jain: "As of now, as per their study, there really is no viable competition for this process of gear making as per Aichi's knowledge."

What Management Would Not Disclose


Guidance & Commitments

CommitmentSpecificsTimeline
EBITDA per ton rangeINR8,000 to INR11,000 per tonFY27
EBITDA per ton range (medium-term)INR9,000 to INR12,000 per tonTwo years from now (FY28–29)
VolumeCross 250,000 tons; keep 250,000 in mindFY27
Forging plant commissioningPlant operationalQ4 FY28 (Jan–Mar 2028)
New steel plant commissioningPlant operationalJuly 2029
New steel plant volumes beginFirst outputH2 FY30
Brownfield melt-shop expansionCapacity to 360,000 tons, subject to environmental clearanceLater part of calendar year 2027, if clearance obtained
Environmental clearance applicationSubmit applicationWithin two months (by June)
Land acquisition for greenfield plantClose transactionWithin May
Capex disclosurePost year-wise capex on company websiteAfter ~3 months, once machine negotiations conclude
Equity infusionPossibly via QIP for outside investorsLater part of next year
Non-automotive steel mix target30% non-automotive, 70% automotiveOver next 10 years
ROCE thresholdEBITDA on capital employed above 20%Once plants are established and running toward full capacity

Key Metrics

MetricQ4 FY26
RevenueNot stated as a standalone Q4 figure; FY26 sales were lower than FY25 despite higher volume due to lower average selling price
EBITDA per ton₹8,500+ (FY26 average), up from previous range of ₹7,000–₹10,000
Net profit₹122-odd crores (FY26), record profit
Volume225,000 tons (FY26), highest ever and in line with budget
Rolling capacity2,70,000 tons of finished product, post reheating furnace commissioning in March
EBITDA per ton guidance₹8,000–₹11,000 (FY27), raised from ₹7,000–₹10,000; further increase to ₹9,000–₹12,000 expected in 2 years
Volume guidance250,000–255,000 tons (FY27), with 250,000 as the base assumption
Dividend₹3.50 per share, recommended by the Board
Aichi shareholding24.9%, increased during the year
Solar power generation9 crore units per year, from newly commissioned solar plant
Government subsidies₹24 crores (FY26); expected to decline to ₹12–13 crores in FY27 as GST refund ends August 2026
Forging plant capex₹475 crores budgeted (total project cost), with ₹50–80 crores spent so far; commissioning expected Q3 FY28
New steel plant capex~₹2,000 crores planned; commissioning targeted July 2029
Total committed capex~₹2,600 crores (new steel plant + forging project + internal capex)
Peak debt-equity targetBelow 0.75 total debt to equity; comfortable at 0.5