Key Takeaways
- Jharsuguda plant is the quarter's story: All pipe machinery installed and in trial runs, with commercial production waiting only on a permanent electricity connection now expected within a month.
- Highway Guard Rail is running "phenomenally well": Order booking is well above 2,000 tons and the galvanizing plant is at full capacity for this product, exceeding management's own expectations.
- Demand has turned a corner: After Diwali, pipe demand recovered to a pre-COVID pattern, the tonnage deficit from Q2 narrowed, and management expects to meet all raw-material MOU targets fairly easily.
- Steel price corrections are now behind the company: Two years of overdue corrections played out this year, leaving Vibhor well leveraged into a market where end-user demand, not just duties, is driving volumes.
- What to watch next quarter: Whether Jharsuguda gets its electricity connection on the promised one-month timeline, the pace of the production ramp toward 50% of Hyderabad's capacity, and any EPS uplift as galvanized products begin contributing.
Jharsuguda Plant: The Next Growth Engine
- Status: All pipe division machinery is installed and undergoing trial runs on temporary electricity and generators. The galvanizing tank is installed, all government permissions are submitted, and the electricity connection delay (originally expected October) caused by highway-crossing permissions is now resolved with work visible on the ground.
- Timeline to production: Permanent electricity is expected within a month, with commercial production starting soon after.
- Product lineup at launch: The plant will produce pipes, Highway Guard Rail, transmission line products, octagon poles, and high mast poles. Octagon and high mast pole machines are already installed and in test trials, set to start alongside the other lines.
- Monopole addition: A monopole machine is scheduled for delivery by end of April, adding a further product to the Jharsuguda mix.
- Demand visibility: Order enquiries already on hand would fill roughly 50% of Hyderabad's production capacity, and galvanizing products carry a higher markup. Management notes Jharsuguda serves a wider geography (Raipur, Bhubaneswar, West Bengal, Northeast, Vishakhapatnam) than Hyderabad did at its start, suggesting a similar or better revenue ramp.
- Rooftop solar: Already installed at Hyderabad and Mumbai sites; Jharsuguda will be evaluated after production begins, though the state allows only 500 kW versus 1 MW elsewhere.
Vibhor Kaushik: "I cannot see anything which is not positive which is going to come from Jharsuguda."
Highway Guard Rail & New Products
- Highway Guard Rail performance: Order booking is well above 2,000 tons and the galvanizing plant is running at full capacity for this product. Management described it as doing "phenomenally well, more than our expectation."
- Transmission line product: Orders are running at 300–400 tons and the market is eagerly waiting for Jharsuguda to start so the company can cater to more enquiries.
- Hyderabad expansion: The Mahbubnagar factory successfully started square pipe and hollow section production, entering the hollow section market, and added 14-inch diameter pipe production last month. Dealer network response has been positive.
- Octagon and high mast poles: Machines are installed and undergoing test trials at Jharsuguda, with production expected to begin simultaneously with pipes, Highway Guard Rail, and transmission line products.
Demand Environment & Steel Prices
- Pipe demand recovery: After Diwali, demand showed better requirements similar to a pre-COVID pattern. The tonnage deficit from Q2 has narrowed, and Q4 demand is expected to continue at Q3 levels, with January and February showing the same demand and order booking.
- MOU targets: Management expects to fulfill all raw-material supplier MOU targets fairly easily now, reflecting the demand pickup.
- Steel price outlook: The government appears supportive, with safeguard duties being discussed and raw-material suppliers indicating supportive measures. Critically, end-user demand has generated in Q3 and is continuing in Q4, independent of any duty action.
- Corrections complete: Steel price corrections that were due for roughly two years have now played out. Prices rose during COVID and the correction "took its own sweet time," but those adjustments are now behind the company, leaving it well leveraged.
Vibhor Kaushik: "This year there were corrections that have been due for as long as I would say 2 years. The prices of steel, everything went up during COVID and the corrections were expected. ... steel correction happened, it took its own sweet time, now those corrections are behind us."
Financial Position & Capital Structure
- EPS outlook: Management called the previous-year quarter EPS of 5.61 "achievable, maybe even better than that is achievable," though it declined to give a specific figure, citing external factors that make EPS subjective.
- Debt and working capital: The company may need to raise more from banks for working capital as Jharsuguda production starts. Banks have been supportive, and Care Ratings has given a positive outlook.
- Interest rates: Expected to remain at current levels: working capital at 9.5%, BG/LC at 7.5%–8%. Management discussed current rates but did not provide a specific repayment plan or quantify expected interest reduction when asked.
- Product-wise disclosure: Management plans to begin reporting numbers for each product separately so investors can see margin profiles.
Revenue Visibility & Ramp-Up
- Jharsuguda revenue potential: Management declined to put a rupee figure on Jharsuguda's contribution, but noted that entering Telangana historically brought additional turnover from the start, and Jharsuguda's wider geographic reach suggests a similar or better outcome.
- Capacity visibility: Enquiries already on hand would fill roughly 50% of Hyderabad's production capacity at Jharsuguda, and galvanizing products carry a higher markup, supporting margin expansion as the mix shifts.
- Analyst math on scale: When an analyst asked whether Jharsuguda could add more than ₹500 crore in sales next year, management declined to confirm, saying "I will not put it in terms of the value and say 500 is achievable," preferring to speak in tonnage terms.
Vibhor Kaushik: "I can tell this that besides 5, the other product that we have has got inquiries right now which we will be diverting to Jharsuguda. So, it should be running to a very good capacity."
Guidance & Commitments
| Commitment | Specifics | Timeline |
|---|---|---|
| Jharsuguda electricity connection | Permanent power connection received | Within one month |
| Jharsuguda commercial production | Production start across pipes, Highway Guard Rail, transmission line, octagon and high mast poles | Soon after electricity connection |
| Monopole machine delivery | Machine delivered to Jharsuguda site | End of April |
| Q4 demand | Continue at Q3 levels; January and February already showing same demand and order booking | Q4 FY25 |
| MOU targets with raw-material suppliers | Fulfilled fairly easily | FY25 |
| EPS | Achievable at or above previous-year quarter EPS of 5.61 | Q4 FY25 |
| Product-wise margin disclosure | Separate margin numbers for each product | Planned, no date given |
Key Metrics
| Metric | Q3 FY25 |
|---|---|
| Revenue | Not stated, but management noted top-line improvement and reduced tonnage deficit vs Q2 |
| EBITDA margin | Not stated, but galvanizing products carry higher markup and margins expected to improve with new product mix |
| Net profit | Not stated, but management indicated EPS should look healthier with Jharsuguda ramp-up |
| EPS | Not stated, but management called previous-year Q3 EPS of 5.61 achievable or better going forward |
| Total debt | ₹260–270 cr |
| Working capital interest rate | 9.5% |
| BG and LC interest rate | 7.5%–8% |
| Highway Guard Rail order booking | Well above 2,000 tons, running Hyderabad galvanizing plant at full capacity of 2,000 tons |
| Transmission line orders | 300–400 tons currently in Hyderabad |
| Combined enquiry pipeline (transmission line and Highway Guard Rail) | 2,000–3,000 tons |
| Jharsuguda galvanizing tank capacity | Over 4,000 tons |
| Combined visible tonnage from Jharsuguda | 2,000–4,000 tons, approximately 50% of Hyderabad's production capacity |
| Product price range | ₹70,000–₹75,000 per ton |
| Jharsuguda plant status | Trial runs underway, permanent electricity expected within one month |
| New products commenced in Hyderabad | Square pipe and hollow sections, plus 14-inch higher-diameter pipe |