Key Takeaways
- Strong quarter, transformation underway: Revenue rose 19% YoY and PAT jumped 60% YoY, driven by pipe demand and early traction in new infrastructure products.
- New products are the margin story: Crash barriers, transmission towers, and poles carry 2% to 10%+ higher EBITDA margins than pipe; management expects overall EBITDA to improve by ~2% as the mix shifts toward a 75:25 target.
- Orissa plant is the growth engine: Strategically located near steel mills for cheap raw material, the plant is dispatching 100+ tons/day and has unlocked the Northeast market, though capacity utilization remains below 50%.
- Steel price rally provides a tailwind: Safeguard duties and anti-dumping measures have lifted domestic steel prices by ₹3,000–₹3,500/ton; the company sits on ~25,000 tons of inventory, a gain that will flow through Q4 numbers.
- What to watch next quarter: Whether Power Grid approval materializes to unlock transmission tower orders, the pace of Orissa’s ramp-up toward 30% utilization, and how much of the inventory gain converts to reported margins.
Performance & Product Mix Shift
- Top and bottom line: Revenue grew 19% YoY and PAT rose 60% YoY, with EBITDA margins holding steady at ~3.85%, reflecting consistent operations even as the product mix begins to shift.
- Product mix ambition: Management targets a 75:25 ratio (75% pipe, 25% diversified products) over the coming years, because crash barriers, transmission towers, poles, and monopoles all carry structurally higher margins than pipe. Pipe volumes will still grow in absolute terms.
- Margin hierarchy: Highway guardrail margins are similar to galvanized pipe (maybe 0.2% higher). Transmission line tower EBITDA margins exceed pipe by 3–4%. Pole division margins are 2–3% higher. Monopole margins can reach 8–10% or more. Overall EBITDA is expected to rise by about 2% as all new product lines contribute.
- Inventory tailwind: Rising raw material prices mean pipe inventory on hand should yield higher margins when sold. For order-driven products (crash barriers, towers), margins depend on establishing a foothold in each line rather than inventory timing.
Vibhor Kaushik: "…we are becoming an infrastructure company as we have diversified in crash barrier, as we have diversified in transmission line towers, as we have diversified in poles, octagon poles, high mass, and as we have a very strong vision to diversify and get into monopole as well."
Orissa Plant: Strategic Advantage & Ramp-Up
- Location economics: The Orissa plant sits close to major steel producers (SAIL under 100 km, JSW in the same city, Tata and JSP not far). Raw material is cheaper because logistics cost is low, enabling competitive delivery to distant markets like Vishakhapatnam, Vijayawada, Nagpur, Raipur, and Patna.
- Ramp-up trajectory: The plant crossed a milestone of 2,000 tons dispatched in a recent month, with daily dispatch now running upward of 100 tons, sometimes 120 tons. Pipe volume is increasing every year as the company captures the Northeast market rapidly.
- Capacity utilization still low: Installed capacity in Orissa is much higher than current dispatch; utilization has not yet reached 50%. Management hopes to achieve 30% utilization in Q4. Additional capex for warehouses and inventory space is needed to service pipe more efficiently.
- Galvanizing constraint: Bombay and Hyderabad galvanizing capacity is already full. If demand for galvanized products rises further, the company will need to add more galvanizing lines, including potentially a dedicated line for highway guardrail in Orissa.
- Jindal partnership: The Orissa plant fills a gap in Jindal’s Northeast presence that had existed for almost 20 years, strengthening the pipe division partnership.
Vibhor Kaushik: "There is an abundance of raw material. Raw material is cheaper here because the logistic cost is fairly low, which gives us an advantage of acquiring more and more locations to be able to get orders and to be able to service them in that location."
New Product Lines: Progress & Approvals
- Crash barrier (highway guardrail): The Hyderabad galvanizing plant for crash barriers is running at full capacity. In Orissa, order flow for crash barriers has picked up sooner than expected, with high order flow currently.
- Transmission line towers: Progress has been slower due to state and central approval requirements. The company has obtained approvals in Gujarat, Sikkim, and Meghalaya. Power Grid (PGCL) has completed its first inspection; a report is being prepared. Once PGCL approval is received, order flow is expected to become steady, opening supply to many EPC contractors.
- Monopole entry: A prototype for 132 kVA is being manufactured and will be sent for testing, which will take some time. This marks the company’s planned entry into monopoles, a product line with margins upwards of 8–10%.
- Tendering approach: The company does not currently participate in tenders directly; it works through its dealer network and EPC contractors. It may participate in tenders in the future once approved in certain states.
Steel Market & Demand Environment
- Policy-driven price uplift: Safeguard duty on China and anti-dumping duties on certain steel products have driven the domestic steel market up. Domestic raw material providers are expected to drive sales. The market has picked up significantly in the current month.
- Inventory position: The company is sitting on approximately 25,000 tons of inventory. With a ₹3,000–₹3,500 per ton price jump in steel, this gain will reflect in the balance sheet and Q4 numbers.
- Demand signal: Management pointed to the order book and dispatch momentum as a signal that demand is picking up, which is positive for Q4. Iron ore and coal prices are also rising, and no downside appears at the moment.
- Export optionality: Exports were originally a way to keep galvanizing capacity occupied if domestic demand dipped. Now domestic demand is so strong that Bombay capacity is full. Orissa’s capacity allows the company to entertain more inquiries from Europe and the UK.
Vibhor Kaushik: "I am not allowed to say the future thing but it is evident if we are sitting on an inventory a certain inventory like upwards of 25,000 tons and there is a Rs. 3,000 jump in that inventory it will reflect in your numbers, it will definitely reflect in anyone's number"
Plant Network & Capacity
| Plant | Status | Commentary |
|---|---|---|
| Maharashtra | ▬ Steady | Self-sustained, steady production and dispatch for years; supplies Maharashtra, Gujarat, parts of Madhya Pradesh. |
| Telangana (Hyderabad) | ▲ Full galvanizing | Strategically located for South market; benefits from demand for buildings (firefighting pipes), highways, and railways. Galvanizing capacity is full. |
| Orissa | ▲ Ramping | Manufacturing started in almost all sectors; dispatch at 100+ tons/day; capacity utilization below 50%, targeting 30% in Q4. |
| Hisar warehouse | ▼ Idle | Not being used much; all production from Bombay, Hyderabad, and Orissa is sold locally. Kept as backup for potential North market entry. |
- Bombay/Hyderabad utilization: Expected to remain similar to last year’s levels.
- Working capital: Historically, working capital cycles remain healthy when markets are strong, demand is steady, and prices are rising. Management expects working capital to stay the same or perhaps improve.
Vibhor Kaushik: "we have just entered Orissa and just last month we have 2000 tons dispatched and this month our dispatch it is early to say but every day I am seeing the dispatch is upward of 100 tons sometime 120 tons. So, seems like we are capturing the market of pipe also quite rapidly in this area."
Guidance & Commitments
| Commitment | Specifics | Timeline |
|---|---|---|
| Product mix target | Achieve 75:25 ratio (75% pipe, 25% diversified products) | "Years to come" |
| Overall EBITDA improvement | Higher by ~2% as all new product lines contribute | When mix target is achieved |
| Orissa capacity utilization | Reach 30% utilization | Q4 FY26 |
| Power Grid approval | Obtain PGCL approval to unlock steady transmission tower orders | "Soon"; inspection completed, report in preparation |
| Monopole entry | Prototype for 132 kVA sent for testing; enter product line thereafter | Testing "will take some time" |
| Inventory benefit realization | ₹3,000–₹3,500/ton price gain on ~25,000 tons to reflect in numbers | Q4 FY26 |
Key Metrics
| Metric | Q3 FY26 |
|---|---|
| Revenue growth | 19% YoY |
| PAT growth | 60% YoY |
| H1 revenue achievement | 51% of full-year revenue |
| EBITDA margin | 3.83% in H1 FY26, versus 3.85% in FY25 |
| Installed capacity | 3,77,000 metric tons |
| Export share | 3% to 5% of revenue, steady |
| Capacity utilization | ~50% currently |
| Maharashtra plant capacity | 1,25,000 metric tons |
| Orissa monthly dispatch | 2,000 tons in a recent month, already hit 3,000 levels |
| Orissa daily dispatch run-rate | upward of 100 tons, sometimes 120 tons per day |
| Order book: Bombay | 2,600 tons pending |
| Order book: Hyderabad | 1,800 tons as of yesterday, 500 tons punched in after price revision |
| Order book: Orissa pipe | 800 tons |
| Order book: Orissa highway crash barrier | upward of 600 tons |
| Inventory position | upwards of 25,000 tons |
| Steel price increase this month | ₹3,000 to ₹3,500 per ton |
| Working capital cycle | 70 days |
| Fixed assets | ₹110 crores, up from ₹69 crores in March 2025; capital work in progress ₹45 crores |
| Orissa Q4 capacity utilization target | 30% |
| Bombay monthly sales | more than 10,000 tons last month, typical run-rate 8,000 tons |
| Bombay order book value | ~₹15 to ₹16 crore |
| IPO funds raised | ₹72.17 crore at ₹75 per share; current share price ~₹135 |
| Pre-IPO valuation | ₹100 crore total; net present valuation ₹50 crore to ₹30 crore (per management) |