Key Takeaways
- Record quarter, accelerating momentum: Revenue grew 31% YoY, EBITDA 83% YoY, and PAT 93% YoY, all records, as India alone added 10.6 GW of solar capacity in Q1 versus 24 GW for all of last year.
- US factory is bursting at the seams: The 1.6 GW US facility is fully booked and driving an expansion to 3.2 GW, with the new lines already fully booked before they even exist.
- Massive capacity buildout fully funded: Board approved an additional ₹2,754 Cr to reach 10 GW each of cells and ingot-wafers, plus 6 GW of modules, all funded from existing cash of ₹7,500 Cr+ and internal accruals, with the company currently debt-free.
- Order book provides 1-1.5 year visibility: The consolidated order book stands at 25 GW (₹49,000 crores), and the shop floor is flush with orders for the next one to one and a half years.
- What to watch next quarter: Whether the cell factory reaches full utilization and delivers on the DCR cell supply promise, the pace of input cost pass-through from China, and any update on the ADD investigation timeline.
Financial Performance
- Top-line growth: Revenue hit a record, driven by 31% YoY growth, with domestic demand backed by a favourable policy environment and accelerating solar capacity additions in India.
- Profitability surge: EBITDA grew 83% YoY and PAT 93% YoY, both record-breaking, while management reiterated its primary focus is managing gross margins in tandem with input costs.
- Indosolar contribution: The acquired subsidiary contributed ₹196 crores of revenue and roughly ₹65 crores of EBITDA this quarter, ramping well since commencing operations in Q2 of FY25.
- Module revenue lag: Module production rose 64% YoY but module revenue rose only 21% because a significant quantity of export orders was shipped and is in transit, so revenue recognition will flow through next quarter.
- Overseas mix surprise: Q1 overseas revenues were 32% versus earlier full-year guidance of ~20%, due to increased US module demand, and management sees this elevated proportion continuing into the current quarter.
- Gross margin philosophy: Management manages the company through gross margin, solving the equation regardless of input cost rises from China or solar glass supply issues, and includes change-of-law clauses in customer contracts for protection.
Sonal Shrivastava: "The endeavour really at our level here is to manage the gross margins. We manage the gross margins, which is the input costs and how it kind of marries in with the prices. So, we both look at both in tandem, and that's what we are looking at."
US Market & Trade Policy
- Three structural demand drivers: AI and data centers (growing from 2.2% of US power to 7.5-8% by 2030), manufacturing reshoring, and transportation electrification underpin the US opportunity.
- Factory utilization: The 1.6 GW US factory is fully booked and "bursting through seams," driving expansion to 3.2 GW, with new lines already fully booked before coming into existence.
- 45X tax credits retained: The Big Beautiful Bill preserved 45X manufacturing credits, which management called helpful.
- FEOC rules as competitive advantage: FEOC regulations are clearly elucidated and beneficial to Waaree because the company is completely India-owned with an FEOC-free supply chain, giving it a leg up in serving the US market while others struggle to comply.
- Trump tariff exposure: In many contracts there is potential to go back to the customer with change orders to pass through tariffs, but in some cases there is not, leaving partial exposure.
- ADD investigation timeline: Anti-dumping duty investigations typically take a minimum of 6 months and optimally 1 year or more, and management will not get ahead of itself on outcomes.
Amit Paithankar: "FEOC rules are quite exacting from that perspective. It extends to ownership. It extends to value chain. It extends to where you buy your raw materials from. So it's a fairly broad-based requirement, which by the way, Aman, is a good news for Indian manufacturers like us who have a footprint both in the US and in India, because that gives us a leg up in actually making sure that we are fully compliant with FEOC from the perspective of both ownership as well as supply chain, and then serves the American market."
Capacity Expansion
- Module capacity milestone: The company will reach 25 GW of module manufacturing capacity within the next six months, with a 6 GW plant in Gujarat ready by end of this calendar year.
- Cell and ingot-wafer scale-up: Board approved an additional outlay of ₹2,754 Cr to expand cell and ingot-wafer capacity by 4 GW each, bringing total to 10 GW each, with all facilities operational by FY27.
- 6 GW module plant: Located in Gujarat, using a fully done-up facility that only needs retrofitting, with activity ongoing as management speaks.
- 10 GW cell facility: Being constructed near the current gigafactory in Chikhli, with land already in possession, construction in full swing, and most permitting already in place.
- Ingots and wafers facility: Located in Butibori, Nagpur, Maharashtra, on MIDC land already in possession, with engineering work complete and preliminary land preparation ongoing.
- Adjacency buildout: A 3 GW inverter facility will be operational this fiscal, a 300 MW hydrogen electrolyser plant and a 3.5 GWh battery energy storage system factory will be operational in FY27, and renewable power infrastructure discussions with Enel Green Power are ongoing with PPAs worth 170 MW signed.
- Funding secured: The ~₹15,000 Cr capex over two years is funded from existing cash (₹7,500 Cr+), two years of internal accruals, and bank facilities, with management conservative on debt-equity and the company currently debt-free.
- Sangam Solar structure: The 6 GW integrated facility and the additional 4 GW cell plus 4 GW ingot-wafer expansion will come under Sangam Solar One, a 100% subsidiary of Waaree.
Technology & Supply Chain
- TOPCon shift accelerating: The current technology mix is veering more towards TOPCon, and over the next 3-7 months TOPCon will be dominant while Mono PERC reduces, though older orders will still need Mono PERC in the minority.
- Cell factory ramp-up: The 5.4 GW solar cell facility is operational, with earlier lines at almost 80% utilization and newer lines at 40-50%, and the factory should be fully operational by the end of the current quarter.
- DCR cell supply: Cells produced in the facility are used for retail (PM Surya Ghar), PM Kusum, and several orders demanding DCR cells, and the company should be in a position to supply DCR cells and modules next year.
- Input cost pressure emerging: Input costs from China, which had been moving downwards most of the time, are now seeing an upward trend that will have an impact on numbers, and management expects to revise prices accordingly.
- Solar glass supply: Capacity is being built in India and other countries, so management expects the supply chain to balance out.
- ALMM expansion: ALMM now applies to behind-the-meter government projects from June 1, 2026, and the cell deadline of June 1, 2026 remains unchanged, though grandfathered project dates have been extended to end of August or mid-September, potentially adding another 10 GW.
- Battery manufacturing approach: The company will reverse-integrate all the way to cell level in batteries (pack to cell), mirroring its module strategy.
Order Book & Demand Outlook
- Order book size: The consolidated order book stands at 25 GW (₹49,000 crores / ~$5.5-6 billion), comprising modules and EPC, with US projects carrying longer gestation of 2-2.5 years versus Indian utility projects at 8-14 months.
- Near-term visibility: The shop floor is flush with orders for the next one to one and a half years, putting the company in good stead for that period.
- Multi-decadal opportunity: Management sees demand continuing unabated and only growing because solar energy is one of the cheapest forms of energy, and front-loading of demand in the next 12 months is "quite possible."
- Geographic ambitions: The company is extremely keen to expand beyond India and the US, following cues from Indian government trade agreements, constantly studying EU incentives (Germany, Italy), and eyeing the Middle East, Africa, Australia, and the Pacific region for EPC potential.
- Wallet share expansion: With 40-45% wallet share in the core solar business, management aims to become a one-stop solution for clients' energy transition needs by expanding into power infrastructure, hydrogen electrolysers, inverters, and battery energy storage.
Amit Paithankar: "We are fully booked for 1.6 gigawatts. In fact, we are bursting through our seams and that's the reason why we are actually going for the next edition, taking the overall capacity to 3.2 gigawatt. In fact, those lines even before they have come into existence, are already fully booked, which is a good problem to have or a problem, nevertheless."
Guidance & Commitments
| Commitment | Specifics | Timeline |
|---|---|---|
| EBITDA guidance | Deliver ₹5,500 - ₹6,000 Cr EBITDA | FY26 |
| Module capacity | Reach 25 GW of module manufacturing capacity | Within next 6 months |
| 6 GW module plant (Gujarat) | Plant ready and operational | End of calendar year 2025 |
| Cell factory (5.4 GW) | Fully operational | End of current quarter (Q2 FY26) |
| Next cell factory (10 GW) | Ready to supply DCR cells and modules | Next fiscal (FY27) |
| US capacity expansion | 3.2 GW total capacity fully ramped up | Next 6 to 9 months |
| Inverter facility (3 GW) | Operational | This fiscal (FY26) |
| Hydrogen electrolyser plant (300 MW) | Operational | FY27 |
| BESS factory (3.5 GWh) | Operational | FY27 |
| All new facilities (modules, cells, ingot-wafers, electrolyser, BESS, inverters) | On track | Per individual timelines |
| ALMM cell requirement | Applicable for government behind-the-meter projects | June 1, 2026 |
| Grandfathered project window | Extended deadline for grandfathered projects | End of August / mid-September 2025 |
Key Metrics
| Metric | Q1 FY26 |
|---|---|
| Revenue | ₹4,597 cr, +31.5% YoY |
| EBITDA | ₹1,169 cr, +83% YoY |
| EBITDA margin | 25.4%, expansion of over 700 bps YoY |
| Profit after tax | ₹773 cr, +93% YoY |
| Production | 2.3 GW, highest ever |
| FY26 EBITDA guidance | ₹5,500 – ₹6,000 cr, on track |
| Order book | 25 GW, equivalent to ₹49,000 cr |
| Order book India mix | 41% from India, balance overseas |
| Revenue split | 1/3rd international, 2/3rd domestic |
| US new orders | 2.23 GW secured during the quarter |
| India solar capacity added in Q1 | 10.6 GW, vs 24 GW in all of FY25 |
| Indosolar revenue | ~₹196 cr |
| Indosolar EBITDA | ~₹65 cr |
| Cash on balance sheet | >₹7,500 cr, zero debt |
| Total capex plan (next 2 years) | ₹15,000 cr, including 4 GW expansion, 6 GW integrated facility, battery and adjacencies |