Key Takeaways
- Record quarter, guidance beat in sight: Revenue grew 118.8% YoY and management sees clear visibility of surpassing its FY26 EBITDA guidance of Rs. 5,500–6,000 crores.
- Manufacturing scale is the moat: Waaree became the first Indian solar manufacturer to produce over 1 GW of modules in a single month, with cell utilization now at 80% and climbing toward 90%.
- US strategy is working, tariffs are managed: US revenue crossed Rs. 2,000 crores with realizations jumping above ¢28/watt as the company passes tariffs through and lays out a supply chain that minimizes country-of-origin exposure.
- Order book is deep but lumpy: The Rs. 60,000 crore order book is 65% overseas, and implied quarterly inflow was ~Rs. 20,500 crores, though management declined to provide FY27 guidance.
- What to watch next quarter: Whether cell utilization hits the promised 90% after the G12R upgrade, the pace of US cell manufacturing decision-making, and any margin impact as Chinese export rebates taper and cell prices rise.
Manufacturing Scale & Cell Ramp
- Module production nearly doubled YoY, rising 94%, while cell production increased 35% QoQ, supported by an order book of ~Rs. 60,000 crores and a pipeline exceeding 100 GW.
- Cell utilization is at 80–81% and growing, with teething troubles around effluent and breakages now largely behind. A planned upgrade to G12R cells over the next 3 months is expected to push utilization well above 85%, possibly to 90%.
- New cell capacity of 10 GW will ramp line by line, with each line taking an estimated 4–6 months; the first few lines may take closer to 6 months, but management leans toward a 4-month estimate for the new facility.
- Ingot and wafer manufacturing of 10 GW is planned for FY27, with equipment sourcing negotiations underway across multiple geographies now that restrictions on puller imports have eased.
Paithankar: "From a margin perspective, there is a lot of structural stability associated with this margin."
US Market & Tariff Strategy
- US revenue crossed Rs. 2,000 crores in the top line, with sale volume of 300 MW. The mix includes modules shipped from India and production from US-based factories, though management did not split the two sources.
- Realizations have jumped from earlier levels of ¢24–¢25/watt to north of ¢28/watt, with some orders at ¢30, partly driven by full tariff pass-through to customers.
- Tariff risk is managed by structuring the supply chain so cells are manufactured in locations with minimal tariffs, since the cell's country of origin determines the module's deemed origin under US rules. Waaree also exports modules made with cells manufactured in countries other than India.
- US manufacturing expansion includes taking over assets of Meyer Burger, an HJT manufacturing play, and doubling down on investments including the Texas facility. Management reiterated it will actively consider US cell manufacturing at the right time.
- IRA tax credits are booked at 90% of the ¢7/watt incentive for module manufacturing, with management noting it does not record the full amount and does not yet have US cell manufacturing.
Paithankar: "If you have to be a global multinational player, US happens to be an important market for us and we are manufacturing in the United States. And not only manufacturing, but we are doubling down on the investments as well."
Order Book & Demand Outlook
- Order book stands at ~Rs. 60,000 crores, split 65% overseas and 35% domestic. Within domestic, 80–85% is non-DCR directionally, though this mix shifts as more cells come online.
- Implied order inflow for the quarter was close to Rs. 20,500 crores. Solar remains the largest business at roughly 80% of this, with retail forming a very large portion. Inverters and battery energy storage systems are just beginning, while the transformer order book secured Rs. 245 crores.
- Domestic demand is expected to increase exponentially: retail demand is just kicking in and expected to multiply, while C&I is poised to jump. The first 9 months already reached 35 GW, exceeding the full prior year. Management sees 140 GW as not completely out of reach, with a good portion meant for exports.
- Chinese export rebates are tapering off, pushing cell prices from ¢4–¢4.5 to roughly ¢6/watt-peak. This proves up some of China's costs and makes India a viable alternative as a global supply chain, per management.
Paithankar: "The export rebates are tapering off as you know. And that is actually, in a sense, I would say it's a good news... it actually proves up some of the costs that China has. And so, that makes India also a good viable alternative as a supply chain worldwide."
Margins & Pricing
- Gross margin is managed through multiple levers: back-to-back cell tying for the order book, own wafer and silver procurement for own cell production. Silver impact is less than 9% on a module basis and is compensated by operating leverage.
- Pricing is currently stable, with efficiencies in manufacturing potentially providing room for price movement going forward. Management will observe as it unfolds.
- On margin sustainability amid input cost increases (silver, cells, export rebate impact of 20–25%), management looks at the P&L overall: scale, manufacturing efficiency, and other controllable factors will help. The commitment is to solve for margin and ensure it is constant or improving, using price increases as one of many levers if needed.
- A US investigation provision of ~Rs. 294 crores was booked based on legal advice, though no demand has been received at this point.
Shrivastava: "Gross margin is what we manage at Waaree. And there are multiple levers that we look it into and we don't like to take commodity risks."
New Business Lines & Backward Integration
- Non-Chinese polysilicon supply chain secured through a strategic investment in United Solar Holdings in Oman. The plant is at a very advanced stage with financial closure done, and production is expected to start from the current quarter itself.
- Battery manufacturing: ~Rs. 1,000 crores of equity raised for a 20 GWh advanced lithium-ion battery and pack manufacturing facility, targeted for readiness by FY28. The aim is to indigenize a large part of the value chain including anode, cathode, and electrolyte facilities. Management declined to commit to revenue or profitability numbers at this early stage, though per an analyst's math, a ~$1 billion investment could imply a $1.5–$2 billion revenue range.
- Inverter facility: Phase one of 3 GW commissioned at Sarodhi, Gujarat; phase two of 1 GW to be operational by FY27.
- Transformer capacity expanding to 20,000 MVA with planned capex of ~Rs. 192 crores.
- Green hydrogen: 1 GW electrolyser facility expected to be operationalized by FY27.
- Modules, cells, ingots and wafers all expected to be operationalized by FY27.
Guidance & Commitments
| Commitment | Specifics | Timeline |
|---|---|---|
| FY26 EBITDA guidance surpass | Clear visibility of surpassing Rs. 5,500–6,000 crores | FY26 |
| Cell utilization target | Reach north of 90% utilization after G12R upgrade | Next 3–4 months |
| G12R cell upgrade | Major upgrades to move to G12R cells | Next 3 months |
| Inverter phase two | 1 GW addition operational | FY27 |
| Transformer capacity expansion | Expand to 20,000 MVA (~Rs. 192 crores capex) | Not specified |
| Battery storage facility | 20 GWh facility ready | FY28 |
| Green hydrogen electrolyser | 1 GW facility operational | FY27 |
| Ingot and wafer manufacturing | 10 GW capacity | FY27 |
| Oman polysilicon production | Production start | Current quarter (Q4 FY26) |
| Margin | Constant or improving, solved through multiple P&L levers | Ongoing |
Key Metrics
| Metric | Q3 FY26 |
|---|---|
| Revenue from operations | ₹7,565.05 cr, +118.81% YoY |
| Operating EBITDA | ₹1,928.15 cr, +167.2% YoY |
| EBITDA margin | Beyond 25%, best-ever quarterly operating EBITDA margin |
| Record EBITDA | ₹2,124 cr for Q3 FY26 |
| PAT growth | +118.4% YoY |
| Module production | 3.5 GW, highest-ever quarterly production, +94% YoY |
| Cell production increase | +35% QoQ |
| Cell utilization | ~80% current daily rate, 56% for the full quarter |
| Order book | ~₹60,000 cr, 65% overseas and 35% domestic |
| Order pipeline | Exceeding 100 GW |
| Implied order inflow | ~₹20,500 cr for the quarter, ~80% from solar business |
| US sales volume | 313 MW |
| US production volume | 275 MW |
| US revenue | Over ₹2,000 cr |
| IRA benefit booked | ₹80 cr, recorded at 90% of the ¢7 per watt peak rate |
| Provision for US investigation | ~₹294 cr, based on legal advice, no demand received yet |
| Domestic revenue mix | 67.4% of total revenue |
| Non-DCR module realization (India) | ₹14–15 per watt-peak |
| DCR module realization | ₹23–24 per watt-peak |
| US module realization | ₹24–25 per watt-peak, some orders above ₹28–30 |
| Cell cost of production (India) | ~¢7 per watt-peak |
| Silver cost as percentage of cell cost | ~25% |
| Silver cost as percentage of module cost | Less than 9% |
| FY26 EBITDA guidance | ₹5,500–6,000 cr, management sees clear visibility of surpassing it |
| Equity raised for battery facility | ~₹1,000 cr for 20 GWh lithium-ion battery and pack manufacturing |
| PPA signed | 713 MW |
| Connectivity secured | 6.1 GW |
| Land secured | ~3,500 acres acquired, 13,500 acres tied up under acquisition |
| Transformer order book | ₹245 cr, including a large order from a global multinational |
| Electrolyser PLI | ₹444 cr for 1 GW electrolyser facility |