Waaree Renewable Technologies Ltd Guidance Report - SOIC x StockScans Report
as of Oct 2026
- FY24 dividend of ₹1 per share
Delivered - In the FY24 annual report, the Board recommended a dividend of ₹1 per share on shares of face value ₹2 each. The ₹1 per share dividend for FY24 was recommended and paid, with a cash outflow of ₹10.41 cr, and a further ₹1 interim dividend followed in Q3 FY25.
- BESS revenue stream to open up during FY27
On track - At the Q4 FY26 call, management expected the BESS revenue stream "will open up during the current financial year" (FY27) on rising BESS-plus-solar inquiries. A 1,520 MWh BESS order was won in Q1 FY27 and a 280 MWh BESS EPC order in Q2 FY27, with a ₹200 cr BESS EPC component in the order book, though no separate BESS revenue figure is disclosed.
- \~227 MWp IPP projects commissioned during FY27
On track - At the Q4 FY26 call, management committed that the additional \~227 MWp of IPP projects under construction would be commissioned during FY27, with CWIP capitalized as incurred. By Q2 FY27, 82.82 MWp was operational with 233.6 MWp under construction and 450 MWp more being developed through a subsidiary, against 54.82 MWp operational at FY26.
- 1 lakh MT T&D manufacturing facility
On track - The company announced expansion of manufacturing capabilities through an additional 1 lakh metric ton facility at Jamnagar, supporting participation in T&D infrastructure requirements. As of Q2 FY27, the facility is under construction at Azamnagar alongside existing Bamangam (36,000 MT) and Manglej (72,000 MT) sites.
- 14 MWp + 37 MWp IPP projects executed in H2 FY26
Partial - At the Q2 FY26 call, the newly approved IPP projects - 14 MWp (two projects, Maharashtra) and 37 MWp (one project, Rajasthan) - were to be executed in H2 FY26 "or maybe a little later than that". FY26 ended with 54.82 MWp operational and 227.10 MWp under construction; by Q2 FY27, 82.82 MWp was operational with the larger pipeline still under construction.
- 3.15 GW order book executed in 12-15 months
On track - At the Q1 FY26 call, management expected the 3.15 GW unexecuted order book to be executed over the next 12 to 15 months, a rolling horizon repeated as the book moved to 3.48 GWp, 2.9 GW, 2.83 GWp, ₹5,300 cr and \~₹3,300 cr through Q2 FY27. FY26 execution was 2,727 MWp, Q1 FY27 889 MWp and Q2 FY27 456 MWp.
- Data center EPC foray via object clause amendment
Pending - At the Q3 FY25 call, the Board approved amending the object clause to foray into data center EPC business, leveraging group synergies. Senior personnel were hired (Q2 FY26) and inquiries and negotiations continued each quarter, but no data center EPC order had been received through Q2 FY27.
- No funded debt - only non-fund-based limits
Missed - At the Q3 FY25 call, management committed not to raise any funded debt, scouting only for non-fund-based limits unless capex is monetized, a stance reiterated at Q4 FY25. In Q1 FY27 the APSPL acquisition was financed \~75% by debt, and debt stood at ₹1,413 cr with D/E of 1.26 as of Q2 FY27.
- Jindal Renewables 2 GW order executed in 8-9 months
Partial - At the Q3 FY25 call, management stated the Jindal Renewables 2 GW BOS order had an execution timeline of "roughly about 8 or 9 months", later confirming partial FY25 execution with completion in FY26. The 2 GW project at Bikaner, Rajasthan remains listed as a key ongoing project through Q2 FY27 with no explicit completion disclosure.
- Annual execution capacity of 3 to 3.5 GW
Delivered - At the Q3 FY25 call, management guided annual execution capacity of "between 3 to 3.5 gigawatt of business" depending on manpower. FY26 execution was 2,727 MWp and Q1 FY27 889 MWp, with management stating in Q1 FY27 it could execute even 5 GW in a year if orders were received.
- No significant capex - 3x business without additional capex
Partial - At the Q1 FY25 call, management stated no significant capital expenditure is needed: "If you want to give me 3x business, I can deliver 3x business without adding any additional capital expenditure". CWIP rose from ₹3.17 cr in FY24 to ₹56.37 cr in FY25 and ₹178 cr in FY26 as IPP assets were built at ₹3-3.5 cr per MW funded through internal accruals, though the EPC business itself stayed asset-light.
- 5B Maverick deployments in coming couple of months
Missed - At the Q1 FY25 call, management said 5B Maverick deployments at Waaree Renewable might be seen "in coming couple of months" after test production was completed. No deployment had been disclosed through Q2 FY27, and at Q3 FY26 management noted no significant development on the tie-up announced a couple of years back.
- O&M portfolio \~2 GW by end of FY25
Partial - At the Q1 FY25 call, management expected an O&M portfolio of "almost like 2 gigawatt" by end of the year or beginning of next, \~3.3-3.5x higher than today's \~500 MW. The portfolio reached 587 MW at Q3 FY25, \~695 MWp at FY25 and \~1,180 MWp at FY26, with 1.5 GWp only at Q2 FY27.
- FY25 execution of 1.8 to 2 GW
Partial - At the Q4 FY24 call, management planned to execute between 1.8 to 2 gigawatt in FY25, seeing "another doubling of our revenues over the next year around 2,800 or 2,500 onwards", with the CFO qualifying "we don't enter into guidance. This is just a plan". FY25 execution was 1,524 MWp and revenue ₹1,597.75 cr, up 82.29% YoY, below the \~₹2,500-2,800 cr ambition.
- Parent Waaree Energies IPO
Delivered - At the Q4 FY23 call, on the parent Waaree Energies going public, management said "Surely, we'll go with the public", adding at Q1 FY24 it would be "in the near time". Waaree Energies Limited, the principal shareholder, was listed on both BSE and NSE per the FY25 annual report.
- NSE listing as the earliest, depending on regulations
Delivered - At the Q4 FY23 call, management said "we intend to list on the NSE as the earliest, depending upon their regulations", with Q1 FY24 reiterating timing depended on fulfilling NSE regulations. The NSE listing was completed in April 2025 per the FY25 annual report.
- 1 MW green hydrogen project in 18-24 months
Missed - At the Q4 FY23 call, management stated the 1 MW green hydrogen project (Maharashtra) had "around 18 to 24 odd months" of execution timeline. Execution was not completed through Q2 FY27, with the project stalled from Q3 FY24 onwards because the PSU customer was yet to hand over land.
- FY24 revenue 100% better than FY23
Delivered - At the Q4 FY23 call, management said for FY24 "probably, we'll do 100% better than what we have done in the FY '23". FY24 revenue was ₹876.44 cr against ₹351 cr in FY23, growth of \~150%, exceeding the target.
- Sustainable EBITDA margin of 15% to 25%
Delivered - At the Q4 FY23 call, management stated a sustainable EBITDA margin range of "anything between the 15% to 25%", applying to the 817 MW order book; revisions narrowed this to \~15% through FY27. OPM was 23.86% in FY23, 23.64% in FY24, 19.46% in FY25, 19.24% in FY26 and 15.12% in Q2 FY27, consistently at or above the \~15% floor.
- \~3 GW bidding pipeline with 35-40% conversion over 12 months
Delivered - At the Q4 FY23 call, management guided a bidding pipeline of \~3 gigawatts over the next 12 months and expected "a minimum of 35% to 40% conversion", a rate later restated as a 25-30% strike rate. FY24 order wins totalled \~2.5 GW+ - implied by starting FY25 with \~2.3 GW unexecuted, executing 1.5 GW and ending at 3.2 GW - against a pipeline that grew to 13 GW by Q4 FY24.
- 817 MW order book executed in 12-15 months
Partial - At the Q4 FY23 call, management stated the 817 MW unexecuted order book should be executed as per contract in 12-15 months, adding "we'll try to do it in the 12 months' time", later pulling this to 9-12 months and planning \~900-950 MW of FY24 execution. FY24 execution was 704 MWp against the \~900-950 MW internal plan, with the book absorbed into a larger 2.3 GW book by Q4 FY24 as FY24 revenue reached ₹876 cr, up 150% YoY.