Key Takeaways
- 20% PAT growth, margin stability held: Net profit rose 20% YoY while EBITDA margins stayed within the guided 13%-15% band; a large forex gain boosted other income but management insists operating margins are intact.
- Order book poised for a step-change: INR3,000 crore of preferred bidder/L1 backlog is convertible in the next few months, with another INR2,000 crore under evaluation; management signalled growth could accelerate beyond 15%-20% if these land.
- Future Energy Solutions opened a new front: Two breakthrough orders in solar ultra-pure water and biogas upgrading mark an entry into a decadal growth space, with India targeting 130 GW of solar cell manufacturing by 2030.
- Balance sheet is a quiet fortress: Net cash positive for the 11th consecutive quarter, debt reduced, and net interest cost flipped to net interest income; working capital lower YoY despite top-line growth.
- What to watch next quarter: Conversion of the INR3,000 crore L1 pipeline, the Kuwait desalination award, and any update on the international investor platform that could unlock 8x-10x asset-light scale.
Profitability & Margin Quality
- Core margins steady, forex distorts the optics: Operating and gross margins are within the guided 13%-15% range when other income is excluded. The apparent QoQ drop in other expenses is a classification artefact: a forex loss in Q1 sat in other expenses, while Q2's forex gain landed in other income.
- Forex gain is structural, not one-off: The INR30 crore forex gain (vs INR9 crore last year) reflects the natural rhythm of a business with ~50% revenue in foreign exchange across 27 countries. Management hedges only the residual delta, relying on natural hedges from payables and USD packing credit.
- EP vs EPC mix drives gross margin variation: The EP share within the EPC backlog is roughly 80%-85%, but the mix shifts with each new order and directly moves gross margin. Last year's average EP mix was about one-third.
- O&M provides a high-margin, cash-and-carry anchor: The O&M business contributed 19% of revenue with quick-turnaround, low-asset characteristics that improve receivable cycles over time.
Mittal: "We only hedge the delta. You must understand that as we receive our money, we also have a liability to pay and sometimes we also take a packing credit in U.S. dollar. So this becomes a natural hedge for us."
Order Pipeline & Growth Ambition
- INR3,000 crore of near-certain backlog: Preferred bidder and L1 positions span seawater desalination, sewage treatment, industrial oil & gas plants, and ceramic-membrane brackish water reverse osmosis. Another INR2,000 crore is under evaluation with good positioning expected in the next couple of months.
- Kuwait desalination award is in advanced stages: Declared L1 for a Ministry project, now in the 4-5 month evaluation phase; management hopes to announce order intake in the next couple of months.
- No upper cap on order intake: Management screens bids for financial and technical fit but sees no capacity constraint; the phrase "Dil Maange More" was used to describe the ambition. If the discussed orders materialise, growth would have to accelerate beyond the 15%-20% band.
- H2 revenue to outpace H1: Management stated H2 is always stronger and "should only be better," though no specific full-year order inflow guidance was given against last year's INR5,600 crore.
- Competition is acknowledged as a fact of a booming sector: Management welcomes it and points to a track record in mega, complex industrial projects that it claims no global peer matches.
Mittal: "I think I can only tell you 'Dil Maange More' that there is no upper cap."
Future Energy Solutions & New Demand Vectors
- Two breakthrough orders mark the entry: An ultra-pure water, effluent treatment and zero liquid discharge plant for RenewSys's solar cell facility in Hyderabad, plus a biogas upgrading unit for compressed biogas production that will leverage SATAT scheme benefits.
- Ultra-pure water demand is tied to India's 130 GW solar target: The jump from ~25 GW today implies 100-150 MLD of ultra-pure water capacity needed by 2030. Similar requirements are emerging from green hydrogen, data centres and semiconductor fabs.
- CBG sector is at an inflection point: Vast feedstock potential exists from existing sewage treatment plants; the company is pursuing multiple tenders.
- Data centre water infrastructure is an active conversation: WABAG is engaging the market to partner on sustainable water infrastructure for data centres, though no orders have been announced yet.
- Margins on these new-sector projects are expected to be normal: Management sees no premium versus existing industrial margins, at least at this stage.
Mittal: "Probably there's no comparable company, not only in India, but globally when we talk about mega, complex, challenging industrial projects."
Asset-Light Platform & Saudi LTOM
- International investor platform is in final negotiation: Marquee investors from Europe or the US will provide capital while WABAG retains all technical, execution and O&M expertise. The structure lets WABAG invest a maximum 25%, targeting 8x-10x leverage on its equity.
- Assets including the CBG project can be transferred in: Once the agreement is finalised, the platform becomes the vehicle for holding funded projects, keeping WABAG asset-light.
- Saudi Long-Term O&M is a pipeline, not yet a backlog: WABAG has participated in LTOM tenders where small upfront investments fund plant upgrades in exchange for 15-year O&M revenues. A big pipeline is expected in the next couple of years, but no win has been secured yet.
- HAM platform margins are not the main story: Management stressed that EP, EPC and O&M remain the bread and butter; platform margins could rise over time depending on the bankability of government-released projects, but no specific margin guidance was given.
Mittal: "We have participated in some of these projects. And it's a matter of time. We will secure one and experiment it. But there's a big pipeline of projects which are expected in the next couple of years."
Balance Sheet & Working Capital
- Net cash positive for the 11th straight quarter: Debt has been reduced and net interest cost has turned into a net interest income scenario, marking the sixth consecutive year of net cash.
- Working capital improved YoY despite revenue growth: Net working capital is lower year-on-year, supported by the cash-and-carry nature of the growing O&M book.
- Non-current debtors are structural, not stressed: They arise from retention money held until the defects liability period ends on large municipal and multilateral projects. Advances received at project start must be shown separately, not netted against receivables. Receivables and payables are broadly back-to-back.
- Billing lumpiness is a timing issue: Large international billings often happen toward the end of a quarter or half-year due to sequential delivery and approval processes. One large late-quarter billing cited had already been 100% collected by the time of the call.
- Credit rating upgrades have been consistent: The profile and outlook have improved steadily over the last five years.
Execution Updates on Major Projects
- Perur desalination (400 MLD, Chennai): All marine activity completed; civil construction progressing; key equipment deliveries started; plant piping pre-fabrication to begin shortly; on schedule.
- Al Haer STP (200 MLD, Saudi Arabia): All activities in full swing, moving swiftly.
- Yanbu mega desalination (300 MLD): Awaiting effective date of commencement; basic engineering package ready; key personnel deployed; long-lead equipment procurement started.
- Lusaka sanitation (Zambia, EIB/KfW funded): Construction drawings for major structures being finalised; purchase orders for key equipment issued; civil subcontractors mobilising.
- One City One Operator: Agra and Ghaziabad continue under WABAG management; robotic sewage cleaning system introduced in Ghaziabad. A national conference on the model was hosted in Agra with over 100 delegates.
- Customs demand of INR87 crore: Being contested through legal and other recourse; management is "very confident" the demand will not stand and expects an important milestone in the next few months, subject to court or appellate authority timelines.
Guidance & Commitments
| Commitment | Specifics | Timeline |
|---|---|---|
| H2 revenue outperformance | H2 revenues to be better than H1 | FY26 second half |
| Order pipeline conversion | INR3,000 crore of preferred bidder/L1 backlog convertible; another INR2,000 crore under evaluation with good positioning expected | Next few months |
| Kuwait desalination award | L1 bid under evaluation; order intake announcement expected | Next couple of months |
| Growth acceleration trigger | If discussed orders materialise, growth goes beyond 15%-20% guided band | Conditional on order conversion |
| International investor platform | Agreement with marquee European/US investors being finalised; assets transferable once closed | In advanced stages |
| Customs demand resolution | Important milestone expected, subject to court/appellate authority timeline | Next few months |
| Saudi LTOM pipeline | Big pipeline of projects expected | Next couple of years |
Key Metrics
| Metric | Q2 FY26 |
|---|---|
| Consolidated revenue (H1) | ₹1,569 cr, over 18% YoY growth |
| Standalone revenue (H1) | ₹1,330 cr |
| Consolidated EBITDA (H1) | ₹216 cr, margin of 13.8%, within 13%–15% guided band |
| Standalone EBITDA (H1) | ₹189 cr |
| Consolidated PAT (H1) | ₹151 cr, margin of 10%, growing 20% YoY |
| Standalone PAT (H1) | ₹131 cr |
| 5-year consolidated PAT CAGR | 38%, EPS up 3.6x over the period |
| Order book | Over ₹16,000 cr, up 17% since start of FY26 |
| Order book mix | 62% EPC, 38% O&M |
| International share of order book | Nearly 50% |
| H1 new order intake | Almost ₹3,500 cr |
| Preferred bidder / L1 pipeline | Over ₹3,000 cr, plus another ~₹2,000 cr under evaluation with high confidence |
| O&M revenue contribution (H1) | 19% of total revenue |
| International revenue contribution (H1) | 47% of total revenue |
| Net cash position | ₹561 cr as of Sep 2025; ₹675 cr excluding transient HAM debt |
| Gross cash balance | ₹798 cr |
| Return on Capital Employed | ~18.5% |
| Return on Equity | 15% |
| Forex gain (Q2) | ~₹30 cr, vs ~₹9 cr in Q2 FY25 |
| EPC order book turnaround time | 3 to 3.5 years on average |
| O&M annual revenue run-rate from current order book | ~₹500 cr to ₹600 cr |