Key Takeaways
- Record H1, debt-free balance sheet: H1 FY27 delivered the highest-ever half-yearly revenue and operating profit, while repaying all IREDA debt in August, leaving the company debt-free with a net worth of INR780 crores.
- Cell utilization hit 91%: The cell line ran at 91% utilization in Q2, a level management flagged as critical for consistent production, fixed-cost absorption, and reliable customer supply.
- TOPCon upgrade on track for March 2027: The 600 MW MonoPERC to 750 MW TOPCon conversion is targeted for commercialization by the last quarter of this financial year, with equipment shipped and civil work underway.
- Greenfield capex is the next big bet: A 4 GW integrated facility on 54.2 acres at Falta is moving forward, with the first 2 GW phase targeted to start by December 2027 at an estimated cost of INR 1,350 crores, funded 30% equity and 70% debt.
- What to watch next quarter: Whether the TOPCon upgrade stays on its March 2027 timeline, the capex number for the wafer-and-ingot backward integration plan, and any margin compression as new capacity comes online.
Quarterly Performance & Cash Generation
- Revenue and profit surge: Q2 revenue grew 114.6% YoY, EBITDA 77.3% YoY, and net profit 73.2% YoY, reflecting continued improvement in operating performance.
- Cash conversion strong: H1 FY27 cash from operations reached ₹244 cr versus ₹137 cr in H1 FY26; net operating cash flow after taxes was ₹212 cr versus ₹132 cr, giving greater flexibility to fund expansion.
- Debt-free milestone: The company repaid its IREDA debt of around ₹110 crores in August, becoming debt-free and strengthening the balance sheet. A land payment of ₹28 crores was also made.
- Order book visibility: An outstanding order book of ₹1,280 crores at the end of Q2 provides visibility on near-term execution and reflects continued demand.
- Cost management levers working: Moderation in silver prices, together with efforts to optimize silver consumption, supported cost management and helped maintain overall blended margins. Disciplined procurement, better input utilization, and process efficiencies remain ongoing focus areas.
Agarwal: "I attach importance to this because it is one thing to install equipment and the other to keep it running at these levels quarter and after quarter."
Capacity Utilization & Production Stability
- Cell line at 91% utilization: The cell line operated at 91% utilization in Q2, a level management credits to the production and engineering team at the Falta plant. Module utilization stood at 68%.
- Why high cell utilization matters: Stabilization at these levels helps maintain predictable production, absorb fixed costs more efficiently, and serve customers consistently, a capability management sees as a competitive differentiator in Indian solar manufacturing.
- Industry capacity lagging announcements: India added approximately 20 GW in the first six months of the year, which was less than expected; ambitious announcements exist but actual on-ground capacity is coming slower.
Agarwal: "The companies that do well will be the ones that can manufacture consistently, control costs, and adapt quickly when the market changes."
TOPCon Upgrade & Greenfield Expansion
TOPCon conversion (current facility)
- Timeline and capacity: The 600 MW MonoPERC line is being converted to 750 MW TOPCon, with commercialization targeted by March 2027, the last quarter of this financial year. The plan still holds good.
- Execution status: The equipment list has been finalized, advances paid, and orders placed; most equipment is shipped and on the way to the facility. Civil work and utility readiness are ongoing at the plant.
- Funding: The ₹270 crore upgrade is well prepared to be funded from internal accruals, though management may still take on some leverage since appetite exists post the IREDA repayment.
Greenfield integrated facility (Falta Industrial Park)
- Land and scope: The company received allotment of 54.20 acres at Falta Industrial Park, West Bengal, for a proposed integrated facility of 4 GW, planned in two phases. Land development has commenced.
- First 2 GW phase: Targeted to start by December 2027, with construction expected to commence by January next year (PEB structure; civil work starts January). The learning curve from the TOPCon upgrade will be fully utilized, and new plants nearby allow training on the current line.
- Project cost and funding: The first 2 GW phase carries an estimated project cost of ₹1,350 crores. The equity portion is expected to be funded through internal accruals; the remaining part through debt. Management is targeting a 30% equity, 70% debt ratio and may utilize more internal funds as debt if available.
- Equipment partner continuity: Centrotherm is likely to be the aggregator for the 2 GW expansion as well.
Khaitan: "We want to take a 70, 30 sanction from a perspective that we see further capex coming our way. We have another 2 gigawatts to execute ahead of the first 2 gigawatts. We have wafer ingot also coming up. And given that currently we have no leverage on our books, I think it would be prudent to potentially raise some substantial debt at this stage to be able to cushion for the upcoming capex."
Backward Integration & New Verticals
- Wafer and ingot evaluation: The company is in touch with technical providers for evaluation and is at an advanced stage. It expects to confirm the capex requirement by next quarter. The wafer and ingot facility will be at a different location, not on the 54.2-acre land.
- ALMM List-III timing: Management is working as per a June 2028 timeline for backward integration but is monitoring closely for any delay, waiting on clarity of ALMM List-III deadlines before committing capital.
- China equipment restrictions not a constraint: China has put an embargo on certain equipment, mainly furnaces, but the company already has suppliers outside China for the same and is not constrained by the restrictions.
- New business verticals approved: The board approved pursuing opportunities in EPC, solar IPP, solar parks, and energy trading, along with a proposed subscription to 40% of Bright Earth Cell Private Limited for energy trading. These businesses will be undertaken through separate subsidiaries to be incorporated in due course.
- EPC vision is captive and capital light: The EPC vertical is designed to help build the company's own IPP and park projects and serve module customers wanting turnkey supply. Manufacturing will remain the core business and take the majority of capital.
- BESS under evaluation: Management sees battery energy storage as a good complement to solar but has no firm plans yet; it will update investors once there is clarity.
Khaitan: "So the vision for EPC at Websol is captive and capital light. ... So the idea behind this vertical is that it can help us emerge as complete energy solution providers and it should help us enable to capture the entire energy value chain."
Margins & Balance Sheet
- H1 margin level: H1 FY27 EBITDA margin stood at 35%. Management expects some moderation, stabilizing around 30% for the full financial year, as new capex comes online.
- Further moderation possible but hard to predict: Exact FY28 and FY29 EBITDA margins are difficult to forecast due to external forces including capacity additions and demand dynamics. Management believes the industry will continue to generate a decent set of EBITDA margins given its high-tech nature.
- Balance sheet strength: The company is debt-free with a net worth of ₹780 crores as of September results. The IREDA loan of around ₹110 crores has been fully repaid.
- Cash flow outlook: Cash flow in the latter half of FY27 is also expected to be strong and will be used for expansion activities. Management did not provide a numerical range or forward projection when asked.
- Equity raise not decided: Management believes expansion can be done with internal accruals and current funds. If an equity requirement arises, it will look to raise from the secondary market, but no decision to raise equity or issue warrants has been made as of now.
Daga: "We still believe this is a high-tech industry and this industry will continue to generate a decent set of EBITDA margins."
Industry Context & Competitive Position
- Cell-module gap persists: The deadline for ALMM List II implementation has been extended because the necessary cell capacity is still not present in India. Websol benefits as a cell-focused manufacturer with DCR and ALMM-compliant modules.
- TOPCon pricing premium uncertain: When asked for the exact price realization premium for TOPCon over MonoPERC, management said it was very difficult to comment, noting only that the current gap is around 1 cent.
- Capacity by end of FY27: By the end of FY27, the company expects cell capacity of 1.35 GW (600 MW MonoPERC plus 750 MW TOPCon) and module capacity of 550 MW.
Khaitan: "The fact that the deadline for ALMM List II implementation has been extended indicates that that necessary cell capacity is still not there in India."
Guidance & Commitments
| Commitment | Specifics | Timeline |
|---|---|---|
| TOPCon upgrade commercialization | 600 MW MonoPERC converted to 750 MW TOPCon | By March 2027 (last quarter of FY27) |
| Greenfield construction start | Civil work and PEB structure commence | January next year |
| First 2 GW greenfield integrated facility | Trial runs and production start | By December 2027 |
| Full-year EBITDA margin | Stabilize around 30%, with some moderation expected as new capex comes on | FY27 |
| Wafer and ingot capex confirmation | Capex requirement to be confirmed | By next quarter |
| End-of-FY27 capacity | 1.35 GW cell, 550 MW module | End of FY27 |
| Greenfield project cost (first 2 GW) | ₹1,350 crores, 30% equity / 70% debt | Over construction period |
Key Metrics
| Metric | Q2 FY27 |
|---|---|
| Revenue | ₹361 cr, +114.6% YoY |
| EBITDA | ₹128 cr, +77.3% YoY |
| Net profit | ₹80 cr, +73.2% YoY |
| EBITDA margin | 35% (H1 FY27), expected to stabilize around 30% for full year |
| Cash from operations | ₹244 cr (H1 FY27), vs ₹137 cr in H1 FY26 (management also stated ₹213 cr in Q&A) |
| Net operating cash flow after tax | ₹212 cr (H1 FY27), vs ₹132 cr in H1 FY26 (management also stated ₹212 cr as cash from operations in Q&A) |
| Net worth | ₹780 cr, debt-free as of September 2026 |
| Cell capacity utilization | 91% in Q2 |
| Module capacity utilization | 68% in Q2 |
| Cell production | ~255 MW in Q2 |
| Outstanding order book | ₹1,280 cr at end of Q2 |
| Current cell capacity | 1.2 GW (Mono PERC), expanding to 1.35 GW by end FY27 |
| Current module capacity | 550 MW |
| Greenfield capex (Phase 1, 2 GW) | ₹1,350 cr, targeted 70:30 debt-to-equity; ₹400–500 cr from internal accruals |
| TOPCon upgrade capex | ~₹270 cr at current Falta plant |