Key Takeaways
- Strong H1, margin recovery underway: Revenue and PAT grew ~90% YoY in H1 FY23, while EBITDA margin rebounded from 7.2% in Q1 to 11% in Q2 as commodity prices eased.
- Actis deal on track for Q3 close: Lender and client approvals, the major condition precedent, were secured in October; first closing is expected in the current quarter, which would make the company net debt zero.
- Water sector opportunity is massive: Management cited ₹10 lakh crores in UP JJM projects alone, plus ₹22,000 crores in metro wastewater treatment, calling the space "humongous" and at a nascent stage.
- Oil & gas blocks: strategy crystallizes in January 2023: The field development study completes then, after which the board will decide on production, infrastructure, and farm-in/farm-out options.
- What to watch next quarter: Actis deal first close and the resulting balance sheet transformation, the Q3/Q4 margin trajectory, and any revised BOT Toll models from NHAI that could restart the road order book.
Actis Transaction: Mechanics, Timeline & Balance Sheet Impact
- Deal structure: The transaction involves divesting SPVs for pure cash consideration, with no equity issued and no impact on total enterprise equity or outstanding share count.
- Condition precedents met: Approvals from all lenders and clients per concession agreements were obtained in October 2022, clearing the major hurdle; remaining conditions are being fulfilled.
- First closing expected in Q3 FY23: Management is "reasonably confident" the deal shall take place this quarter, stating there is no reason known for it not to occur.
- Net debt zero target: The company expects to become net debt zero after the transaction closes, with the cash surplus allocated to retiring debt, funding the current ₹11,500 crore order book, and building a war chest for future high-margin asset creation.
- Tax computation in progress: Consultants are engaged on the tax impact; the real burden will be known only once finalized.
- Pending equity requirement clarified: The increase in pending equity from ₹175 crores (June) to ₹236 crores reflects the removal of ₹91 crores in short-term loans that are likely to be structured into the Actis deal; the fresh requirement covers only SNRP and minor oil & gas equity over the next 1-2 years.
- Shareholder returns deferred: The board will decide on shareholder rewards at an appropriate time once the Actis deal concludes, with management prioritizing capital for debt retirement, operations, and the next growth phase.
Sandeep Garg: "We have always maintained that we have an asset light business model and we have stayed the course. The impending Actis transaction demonstrates our commitment to act on stated strategy."
Margin Trajectory & Commodity Tailwind
- Sequential recovery driven by input costs: EBITDA margin improved from 7.2% in Q1 FY23 to 11% in Q2 FY23, aided by moderation in commodity prices; if the trend holds, margins are likely sustainable.
- Further improvement expected in H2: Management anticipates Q3 and Q4 margins will exceed Q2 levels, citing both the high revenue expected in those quarters and the current commodity cycle.
- No formal guidance given: Management declined to provide margin guidance, citing volatile commodity price cycles, but shared its anticipation of improvement based on current trends.
- Revenue scale as a margin lever: The expected high revenue in Q3 and Q4 is itself a driver of the margin improvement, alongside input cost moderation.
Sandeep Garg: "As I said guidance is a difficult situation to give in a market where the commodity price cycles are pretty volatile. So, I would refrain from giving a guidance. Our anticipation is that if the current trend is to continue our EBITDA margins will improve further in two quarter primarily on two accounts because of the high revenue that we expect to generate in Q3 and Q4 and also with the commodity cycle that we see up to now."
Water Sector: The Next Growth Engine
- Opportunity scale: Management described the water space as at a "very nascent stage" in India, with opportunities including at least ₹10 lakh crores of UP Jal Jeevan Mission projects, Har Ghar Jal schemes across every state, and ₹22,000 crores in wastewater treatment for metros alone.
- River linking emerging: River linking projects are also taking shape, adding another dimension to the pipeline.
- Differentiation strategy: The company believes there is room for players with differentiation to command value in this space, and it will focus on developmental projects and selective investment opportunities in water, consistent with its return expectations.
- EPC plus selective investments: While open to EPC projects on roads, in water the approach is EPC and selective investment projects where differentiation can be brought.
Road Sector: Temporary Slowdown, Model Reset Ahead
- NHAI order pause is temporary: Management acknowledged a slowdown in NHAI orders but noted substantial work remains at both central and state levels.
- BOT Toll revival in sight: The government is focused on reviving BOT Toll projects with balanced risk-reward schemes to attract private sector financial strength; revised models are expected in the next 2 months, or a few months more, after which the order book uptick will start.
- Strategic posture: The company will continue concentrating on developmental projects where it can bring differentiation, while remaining open to EPC projects on roads.
Oil & Gas: Value Unlocking Timeline
- Field development study underway: The study for the two gas blocks (MB OSN 2005/2 and B-9) is ongoing and expected to complete in January 2023, at which point the complete strategy for production, infrastructure requirements, and commercials will be known.
- All investment options open: The company is looking at all forms of investment including farm-in/farm-out and interest from oil majors; a strategic call will be taken once the FDP is completed and the board has applied its mind.
- Valuation left to analysts: Management refrained from naming a valuation, directing analysts to do the math based on ~1 TCF petroleum initially in place, ~70% producibility for gas blocks, and their own gas pricing assumptions over 10-15 years.
Sandeep Garg: "It's the gas block, I would refrain from…. primarily these are gas blocks. The petroleum initially in the place is about 1 TCF and in the gas block normally 70% of the petroleum initially in place subject to the studies confirming is producible. You can do the math depending upon how you foresee the gas pricing to be move forward over the next 10-15 years as to what these blocks mean."
Execution Runway & Order Book
- H1 FY23 performance: Revenue and PAT grew 90% and 89% YoY respectively, driven by better execution of key EPC projects in both road and water segments.
- FY23 revenue expectation: Management expects the current financial year to close at a run rate close to double that of last year, while explicitly refraining from calling this guidance.
- FY24 execution target: The company will endeavor to achieve a rate of about ₹300 crores per month in FY24; management again refrained from calling this guidance.
- Order book consistent with returns: The company is governed by an order book consistent with return expectations, with concentration on developmental projects where differentiation can be brought.
- Railway adjacency on the horizon: The company will look at developmental railway projects but may stay away from pure EPC railway plays until it builds the requisite strength to deliver them.
- Project completions: Completion certificates were received for the Maharashtra Amravati package AM 2 project (July 2022) and the Chutmalpur-Ganeshpur and Roorkee-Chutmalpur project (October 2022).
Guidance & Commitments
| Commitment | Specifics | Timeline |
|---|---|---|
| Actis deal first closing | First closing of the transaction | Q3 FY23 |
| Net debt zero | Company expected to become net debt zero | After Actis transaction closes |
| Oil & gas field development study | Study completed; full production strategy, infrastructure, and commercials known | January 2023 |
| Oil & gas strategic decision | Board to decide on farm-in/farm-out and investment approach | After FDP completion in 2023 |
| EBITDA margin improvement | Q3 and Q4 margins to exceed Q2 levels, conditional on current commodity trend continuing | Q3 and Q4 FY23 |
| FY23 revenue run rate | Close to double of last year (stated as expectation, not guidance) | FY23 |
| FY24 execution rate | Endeavor to achieve ~₹300 crores per month (stated as endeavor, not guidance) | FY24 |
| Revised BOT Toll models from NHAI/MoRTH | Revised models expected, after which road order book uptick starts | Next 2 months, or a few months more |
| Future equity investment | Only SNRP and minor oil & gas equity to be invested | Next 1-2 years |
| Shareholder reward decision | Board to decide | When Actis deal concludes |
Key Metrics
| Metric | Q2 FY23 |
|---|---|
| Revenue (standalone) | ₹510 cr, +82% YoY |
| EBITDA (standalone) | ₹57 cr |
| EBITDA margin (standalone) | 11%, stable YoY; improved from 7.2% in Q1 FY23 |
| Profit after tax (standalone) | ₹40 cr, +1.8x YoY |
| H1 FY23 revenue (standalone) | ₹1,184 cr, +90% YoY |
| H1 FY23 PAT (standalone) | ₹65 cr, +89% YoY |
| H1 FY23 EBITDA (standalone) | ₹107 cr |
| Order book | ₹11,400 cr as of 30 Sep 2022, including ₹1,796 cr O&M and asset replacement for MCGM STP |
| Order book mix: water and wastewater | 56% of order book |
| Order book mix: roads | 44% of order book |
| Aunta-Simaria project completion | 46% financial progress |
| SNRP project completion | 12% |
| Varanasi Road project completion | 15% |
| Pending equity commitment | ₹236 cr, up from ₹175 cr on 30 Jun 2022 |
| Oil and gas block investment | ₹410 cr cumulative |
| Oil and gas reserves (petroleum initially in place) | ~1 TCF across two blocks |
| Actis transaction: portfolio being monetized | ~₹9,000 cr of developmental projects |
| Actis transaction: anticipated project-level IRR | at least 15% |
| Actis transaction: expected net cash surplus post-deal | ~₹2,100 cr (per an analyst's math) |
| Standalone debt | ~₹650 cr |
| FY24 execution target | ~₹300 cr per month |