Key Takeaways
- Revenue doubled QoQ, margin jumped: Standalone revenue more than doubled from Q3, and EBITDA margin improved against all previous quarters, translating to PAT rising from ₹6 crore to ₹53 crore.
- Two large projects ignited Q4: The Varanasi-Aurangabad road project and UP Jal Jeevan Mission water project started execution in Q4, driving the revenue and margin uplift.
- Order book provides 3-year visibility: The current order book of ~₹8,400 crore, plus pipeline orders, is to be executed in a 3 to 3.5 year timeframe, with management comfortable on capacity.
- Strategy pivots to EPC and asset-light: New management is shifting from HAM/subcontracting toward developing in-house EPC capabilities, while keeping the execution strategy asset-light.
- What to watch next quarter: Whether the Q4 execution momentum sustains into FY23, the award of MCGM wastewater treatment plant bids, and any concrete progress on asset monetization discussions.
Execution & Project Momentum
- Q4 turnaround driven by two large starts: Varanasi-Aurangabad and UP Jal Jeevan Mission projects began execution in Q4, and the margin improvement also benefited from cost savings on reconciliations for projects reaching PCOD/COD stage.
- Aunta-Simaria completion timeline: Expected to be completed within FY23.
- Varanasi-Aurangabad fully mobilized: An additional 38 km on the same stretch was awarded, giving ease of execution; good revenue building expected in the current and next financial year.
- UP Jal Jeevan Mission phasing: 40% of the work front is currently available, with the remaining 60% to be made available in the next 6–8 months as schemes get approved; each phase cycle runs ~18 months.
- TN project now fully mobilized: Earlier sand and earth material issues have been resolved, and good turnover is expected from this project.
- Mukarba Chowk-Panipat BOT tolling commenced: Toll collections began on 6 April 2022, with management expecting beyond ₹1 crore per day as exemptions are controlled.
- Six of eight development projects now revenue-generating: Achieved PCOD/COD and are contributing revenue.
Ajay Hans: "We take great pride in sharing that our Hon'ble Union Minister of Road Transport and Highways, Mr. Nitin Gadkari recently inaugurated and dedicated to the nation these two projects... and he acknowledged our contribution to Nation building and the superior quality which is comparable to international standards."
Order Book & Bidding Pipeline
- Order book stands at ~₹8,400 crore: To be executed over 3 to 3.5 years, with management stating execution capabilities are in place to deliver within that timeframe.
- Additional ₹1,430 crore awarded on Varanasi-Aurangabad: Announced 30 April 2022, this ex-GST additional work from Soma Indus Varanasi Aurangabad Tollway Project strengthens the existing stretch.
- MCGM wastewater treatment plant bids submitted: The company has bid for three packages under Supreme Court supervision, with award expected within one to two months; bid values were not disclosed as results are awaited.
- No outstanding NHAI tenders in pipeline: Management is comfortable with the current order book providing 2–3 year visibility and is not actively pursuing NHAI tenders right now.
- No order inflow guidance provided: The company has not set specific order inflow targets, stating it will continuously explore good opportunities and take whatever it has capacity to execute.
- Order book mix target is 50:50: Going forward, management is targeting a 50% roads and 50% water and wastewater split.
- Railway station development still exploratory: Studies have been done and consultants engaged, but it is not yet a reality; the company will explore when opportunities arise.
Margins & Cost Protections
- FY23 EBITDA margin expected in line with FY22: Management stated that the full-year FY22 EBITDA margin should be reflected in coming quarters, because the two large projects that started in Q4 signal that margin level.
- Commodity price protection on water projects: For steel pipes, orders were placed at the start so the company is saved from escalations for the current lot; for HDP pipes, there is a 100% pass-through mechanism linked to a base price specified in the contract.
- HAM projects fully covered by escalation clauses: 100% of the project is covered, with 40% paid out during construction and 60% by the entity; the net impact is minimal.
- Subcontractor arrangements are back-to-back: Whatever escalation the company receives, it passes on to subcontractors, insulating margins.
- Interest rate risk nullified on HAM projects: For completed HAM projects with annuity, if costs rise due to RBI rate increases, revenue also rises because annuity is linked to bank rates plus 3%, so the pressure is offset.
- No new loans drawn in FY21-22: On a standalone basis, no loans were drawn; previously drawn loans are protected as the reset has not started yet.
- Finance cost trajectory stable: Barring some repayments this financial year, the finance cost position is expected to remain stable; as revenue picks up, the percentage might drop.
Sanjay Sultania: "whatever EBITDA margins we have seen on the whole year in FY22, that in my views should get reflected in the coming quarters."
Strategy & Management Shift
- New top management in place: Mr. Ajay Hans has taken over, bringing a strategic shift in focus.
- Pivot from HAM/subcontracting to in-house EPC: Previously, projects were more HAM and subcontracting; going forward, EPC is a focus area, with potential development of in-house facilities and capabilities.
- Asset-light execution strategy: While developmental and asset-based projects will continue, the execution strategy is to remain asset-light.
- BOT project equity investment: Close to about ₹100 crore to be invested in FY23 in the BOT project; balance equity for the SNRP project will come in fragments over one to two years depending on project completion stage.
- Oil and gas revenue still years away: No revenue from oil and gas at this moment; only the investment side exists, with revenue expected from FY25-26.
Ajay Hans: "Previously, we were doing projects, which were more of HAM and more on subcontracting. Now, EPC going forward is a thing. So, we may be developing some in-house facilities and in-house capabilities also."
Asset Monetization & Capital Management
- Asset monetization discussions ongoing, no conclusion: Discussions are happening with various parties, but nothing is concrete; management declined to provide a timeline, stating it will update when a conclusion is reached.
- No new debt raised: The company did not raise any additional debt during FY21-22.
- Interest rate reset impact muted: The reset is happening later in the year, but management expects little impact on the cost side because the HAM side is protected by interest on revenue earned, which will nullify the cost edge.
Sanjay Sultania: "I would say that whenever we come to any conclusions, though discussions are happening with various parties, but nothing conclusively yet, once we get a conclusion, we'll come back to you, definitely."
Guidance & Commitments
| Commitment | Specifics | Timeline |
|---|---|---|
| Aunta-Simaria project completion | Project to be completed | Within FY23 |
| UP Jal Jeevan Mission work front | Remaining 60% of work front to be made available | Next 6–8 months |
| FY23 EBITDA margin | In line with full-year FY22 EBITDA margin | FY23 |
| BOT project equity investment | Close to ~₹100 crore to be invested | FY23 |
| MCGM wastewater treatment plant award | Award of bid packages expected | Within 1–2 months |
| Oil and gas segment revenue | Revenue to begin accruing | FY25-26 |
| Order book execution | Current ~₹8,400 crore order book plus pipeline to be executed | 3 to 3.5 years |
Key Metrics
| Metric | Q4 FY22 |
|---|---|
| Standalone revenue | ₹467 cr, more than doubled from previous quarter |
| Standalone EBITDA | ₹85 cr, vs ₹22 cr in Q3 |
| Standalone PAT | ₹53 cr, vs ₹6 cr in Q3 |
| Consolidated revenue | ₹485 cr, vs ₹242 cr in Q3 |
| Consolidated EBITDA | ₹126 cr, vs ₹57 cr in Q3 |
| Consolidated PAT | ₹65 cr, vs ₹33 cr in Q3 |
| Full-year FY22 standalone revenue | ₹1,307 cr, vs ₹1,410 cr in FY21 |
| Full-year FY22 standalone EBITDA | ₹182 cr, vs ₹198 cr in FY21 |
| Full-year FY22 consolidated revenue | ₹1,401 cr, vs ₹1,530 cr in FY21 |
| Full-year FY22 consolidated EBITDA | ₹323 cr, vs ₹306 cr in FY21 |
| Full-year FY22 consolidated PAT | ₹126 cr, vs ₹130 cr in FY21 |
| Order book | ₹8,400 cr, road projects ₹5,950 cr, water segment ₹2,450 cr |
| Additional contract awarded in Q4 | ₹1,430 cr (excluding GST), announced 30 April 2022 |
| Mukarba Chowk-Panipat daily toll collection | ₹80 to ₹85 lakhs per day in April 2022, expectation beyond ₹1 cr per day |
| Total investment in road projects | ~₹2,100 cr (equity plus loans and advances) by March 2022 |
| Investment in oil and gas block | ₹350 to ₹375 cr as of FY22 |
| UP Jal se Nal project executed | ~10% of total allocated value of ~₹2,500 cr, ~₹100–110 cr revenue in Q4 |
| Cost of funds | 7.5% to 8% |
| Equity requirement for next 1–2 years | ~₹203 cr, with ~₹100 cr for BOT project in FY23 |