WPIL Ltd Q2 FY2027 Concall Summary

Source transcript PDF: https://assets.stockscans.in/docs/mz6rc6d3eagwa2xqtz9rlpjv.pdf

Key Takeaways


Domestic Execution: The West Bengal Overhang

Prakash Agarwal: "We are anxiously waiting to get that funds and start accelerating supplies itself. So very quickly, you should see results."

Product Division: Deferred, Not Lost

Prakash Agarwal: "Geopolitically, the Middle East remains an area of flux, and that is affecting new contract finalization, dispatches to that area to some extent. So I think we will know within the next few months how it plays out."

International Business: The Margin and Cash Flow Anchor

Prakash Agarwal: "The South African execution will be lumpy, and it will gain traction, as we have always mentioned from FY '27. It's lumpy. That means the big payments at one time. It's not civil construction steady run rate projects."

Margins: Healthy Underneath the Revenue Noise

Prakash Agarwal: "We are consistently in our 15% to 20%. If you see the first half itself, we are at 14% on a consolidated basis. We should be up to between 15% to 20%. I think 17%, 18% is our target."

Order Book & Pipeline: Building for the Turn


Guidance & Commitments

CommitmentSpecificsTimeline
West Bengal execution ramp-upRapid acceleration once funds received; client keen, peak construction weather alignedStarting next week (funds expected)
Product dispatch normalizationLarge number of deferred dispatches to be dispatched; backlog moved from ₹450 cr to ₹500 crQ3 and "surely in H2" FY27
Consolidated EBITDA margin17–18% target; H1 at 14%, expect full year between 15–20%FY27
South Africa project tractionMajor traction picks up from year two of 48-month projectsCalendar year 2027 / Q1 FY28
Standalone product revenueHope to improve on last year's ₹1,036 croresFY27
O&M revenue contributionWill pick up as more projects commission; fair picture availableH2 FY27, clearer from next year
MENA region growthKuwait order crystallizing; growth resumes as normalcy returnsWithin next few months (conditional on geopolitics)

Key Metrics

MetricQ2 FY27
Consolidated revenue₹354 cr, decline of 17% YoY
Standalone revenue₹118 cr, down 33% YoY
H1 FY27 consolidated revenue₹855 cr, 6% increase YoY
H1 FY27 EBITDA₹123 cr, decline of 5% YoY
H1 FY27 EBITDA margin14.33%
H1 FY27 PAT from continuing operations₹93 cr, increase of 20% YoY
H1 FY27 PAT margin10.83%
Consolidated EBITDA margin target17%–18% for the full year
Domestic order book₹2,423 cr
International order book₹2,686 cr
Product division total order backlog~₹1,000 cr at end of H1; international orders ~52% of this backlog
Project division order backlog~₹4,079 cr at end of H1; international projects ~53% of this backlog
Domestic project order backlog~₹1,900 cr, of which O&M is ~₹550 cr and JJM is ~₹1,400 cr (per an analyst's math)
South Africa order backlog~₹2,400 cr (product and project combined); product share ~₹250–300 cr
International H1 FY27 revenue₹626 cr, 38% increase YoY
Domestic project division H1 FY27 revenue₹100 cr vs ₹206 cr in H1 FY26
Product division H1 FY27 revenue₹133 cr vs ₹151 cr in H1 FY26
Share of profit from associates and JVs₹3.5 cr, down from ₹11 cr QoQ
O&M order book~₹540–545 cr; recently received an O&M order of ~₹25–27 cr
Rutschi tax claim amount~€6.87 million, claim in process; first feedback expected this quarter
West Bengal share of domestic project backlog~50%–60%
H1 FY27 cash flow from operationsVery healthy, versus negative in H1 FY26